钻孔灌注桩施工方法2
南川区工业园区龙岩组团纵四路道路工程
钻孔灌注桩施工方案
审批人:
审核人:
编制人:
南川区工业园区龙岩组团纵四路道路工程子项目部
二零一七年八月
目录
1.编制依据...........................................................................1
2.编制原则...........................................................................1
3.工程概况...........................................................................2
3.1工程简介..............................................................................2
3.2拟建桥梁工程地质评价及建议..........................................2
3.3结论及建议..........................................................................3
3.4工程数量..............................................................................4
4.施工组织.............................................................................5
5.关键工程施工方案.............................................................6
5.1施工准备...............................................................................6
5.2护筒埋设...............................................................................10
5.3泥浆制备...............................................................................11
5.4钻孔.......................................................................................12
5.5检孔.......................................................................................12
5.6清孔.......................................................................................13
5.7钻碴废浆的处理...................................................................14
5.8制作、安装钢筋骨架...........................................................14
5.9灌注水下混凝土...................................................................15
5.10截除桩头.............................................................................15
6.质量控制措施、存在问题及原因分析预防措施............15
6.1质量控制措施.....................................................................15
6.2存在问题.............................................................................16
6.3原因分析预防措施.............................................................17
7.汛期施工措施...........................................................................24
8.夜间施工措施...........................................................................24
9.安全文明保障措施............................................................24
9.1工人班前教育及技术交底...........................................25
9.2施工现场.............................................................................25
9.3机械操作安全技术要点.....................................................25
9.4施工用电安全保证技术要点.............................................26
9.5临水作业安全保障.............................................................26
10.环境保障措施.................................................................27
10.1施工废水............................................................................27
10.2施工粉尘.............................................................................27
10.3施工噪声.............................................................................28
10.4施工废气.............................................................................28
11.钻孔灌注桩施工应急措施...............................................28
11.1钻孔施工常见事故预防与处理.........................................28
11.2水下浇注混凝土事故.........................................................30
11.3钻孔灌注桩质量检测.........................................................31
11.首批混凝土数量计算.......................................................32
12.验收...................................................................................33
1.编制依据
(1)《公路工程技术标准》(JTGB01-2014)
(2)《城市道路工程设计规范》(CJJ37-2016)
(3)《城市桥梁规范》(CJJ11-2011)
(4)《公路桥涵通用规范》(JTGD60-2015)
(5)《公路桥涵施工技术规范》(JTJ/TF50-2011)
(6)国家及地方相关的法律、法规、设计规范、施工规范、验收标准、规则和指令性文本等
(7)重庆市设计研究院提供的《施工图设计文件》
(8)施工现场实际情况。
2.编制原则
(1)遵循合同文件标准条款的原则,积极响应合同文件的各项条款,严格执行合同文件的规定,标准统一,格式规范。
(2)遵循设计文件、规范和质量验收标准的原则。
在编写主要工程项目施工方法和技术措施中,严格按设计标准、现行规范和质量验收标准办理,正确组织施工,确保工程质量优良。
(3)坚持实事求是的原则,在制定施工方案中,充分发挥我单位施工的优势和专业化、机械化联合作业的特点,坚持科学组织,合理安排,均衡生产,确保高速度、高质量、高效益地完成本项工程的建设,确保施工组织的先进性和合理性。
(4)坚持遵循“GB/T19002-1994ISO9002:
1994生产、安装和服务的质量保证模式和由此编制的质量体系文件,优质、高效、重信、守诚,完成业主要求的质量目标。
(5)坚持施工过程严格管理的原则。
在施工过程中,严格执行业主及监理工程师的指令。
(6)重视特殊工程地质、水文地质,建立以地质工作内容为先导、以量测为依据的信息化施工管理体系。
(7)重视生态环境,在施工期间保证不发生水土流失,保证不破坏当地环境。
贯彻执行国家和当地政府的方针政策,遵守法律法规,尊重当地的民风民俗。
3.工程概况
3.1工程简介
本工程为南川区工业园区龙岩组团纵四路道路工程,起始桩号K0+000,终点桩号K0+448.856,路线全长448.856m。
其中设桥梁一座,跨越凤嘴江,桥跨结构布置为1—45m预应力砼箱梁,斜交15度,桥梁起点桩号K0+310.00,终点桩号K0+366.00,桥梁设计全长56.0米,中心里程K0+337.50。
本工程采用四车道城市次干路标准,规划红线宽24米,设计速度40公里/小时,工程位于南川区工业园区龙岩组团内。
3.2拟建桥梁工程地质评价及建议
3.2.1桥梁墩台工程地质评价
0号桥台位于凤嘴江北岸,周边地形平缓,0#台边与河岸地势为陡坎,上覆土层0~0.50m,土层为红粘土,下伏基岩为中等风化灰岩。
主要不良地质现象为岩溶发育,据现场钻孔揭露,未发现岩溶发育,岩溶发育的规律性差,岩溶的空间分布形态变化大,具有突变性,由于岩溶发育的复杂性以及勘察手段的局限性,可能局部地段有岩溶发育而未被发现,因此建议:
对桥台底部持力层进行施工勘察,查明下部持力层情况,0号桥台经施工勘察查明下部持力层完整后,拟建位置场地稳定。
1号桥台位于凤嘴江南岸。
拟建地段地形平缓,素填土0~0.60m,红粘土0~4.40m。
素填土松散,红粘土呈可塑状,下伏基岩为中等风化灰岩。
主要不良地质现象为岩溶发育,据现场钻孔揭露,未发现岩溶发育,岩溶发育的规律性差,岩溶的空间分布形态变化大,具有突变性,由于岩溶发育的复杂性以及勘察手段的局限性,可能局部地段有岩溶发育而未被发现,因此建议:
对桥台底部持力层进行施工勘察,查明下部持力层情况,1号桥台经施工勘察查明下部持力层完整后,拟建位置场地稳定。
0号桥台采用轻型桥台,桩基础;盖梁长24.582m,宽2.2m,高1.8m;单排4根桩,桩径1.8m,桩长为16m,桩间距为