沈阳市某土地整理工程施工组织设计最终版.docx

《沈阳市某土地整理工程施工组织设计最终版.docx》由会员分享,可在线阅读,更多相关《沈阳市某土地整理工程施工组织设计最终版.docx(64页珍藏版)》请在冰豆网上搜索。

沈阳市某土地整理工程施工组织设计最终版.docx

沈阳市某土地整理工程施工组织设计最终版

(此文档为word格式,下载后您可任意编辑修改!

 

沈阳市某土地整理工程施工组织设计

 

152

一、工程概况··························································································4

二、编制依据··························································································6

三、施工部署·························································································7

1、技术准备················································································7

2、现场准备················································································8

四、主要工程施工方法···········································································9

1、测量放线·············································································9

2、土方工程·············································································9

3、水利工程

4、桥涵工程

5、道路工程·············································································18

6、植被工程·············································································19

7、砌筑工程·············································································20

8、砼与钢砼工程·······································································21

9、喷灌工程

五、开竣工日期、施工总进度设计························································27

1、开工日期、竣工日期······························································27

2、控制性施工进度······································································27

3、施工总进度表···········································································28

4、进度保证措施···········································································30

252

六、施工组织管理················································································34

1、施工组织机构的设置····························································34

2、岗位职责················································································35

3、人员配备情况········································································37

4、机械设备情况········································································38

5、相关措施················································································39

1)、安全保证措施···································································39

2)、雨季施工保护措施····························································41

3)、成本控制措施···································································41

4)、文明施工措施···································································41

5)、环境保护措施···································································42

6、施工现场平面布置图····························································43

1)、布置原则···········································································43

2)、施工交通运输···································································43

3)、供电系统·············································································44

4)、供水系统···········································································45

5)、消防设施

6)、房建设施···········································································46

7)、施工工厂设施···································································46

七、工程质量··························································································48

1、工程质量目标········································································48

2、质量保证措施········································································50

352

1、位置

一、工程概况

项目区位于沈阳市某县县城西北部10km处,东经123°07’-123

°15’,北纬42°45’-42°50’。

2、气候

处于温带大陆性季风气候区,冬冷夏热四季分明,雨热同季降水集

中,日照充足温差较大,春秋风多,年平均温度6.9°C,年降水量525

mm,无霜期151天。

3、水文

项目区内径流量系由降水形成,由于受自然气候的影响,降水量在

年际间波动较大,年内分布不均匀,项目区位于东马莲、西马莲河的河

间区,地下水资源丰富,地下水埋藏较浅,埋深0.5-3.5m,地下水类型

为冲洪积平原空隙潜水。

4、地形地貌土壤

项目区位于东马莲河2.5km处,康彰公路北侧,紧靠541排干的北

侧,属于低洼平原,地势走向由西南到东北,地面高程为西高东低,略

有起伏,地面高差小。

5、土地利用状况

项目区地势比较平坦,耕地已经成型,局部有些坑洼和废弃的沟渠

需要平整,项目区内为低洼盐碱土,土壤质量差,需要人工平整土地和客

土改良土壤。

452

6、土壤

项目区土层厚度达3m以上,土壤质地为壤土,土壤类别为草甸土和

盐碱土。

552

二、编制依据

1、本施工组织设计是以《土地开发整理复垦项目规划设计报告》、《土

地利用现状图》、《土地整理开发规划设计图》和《土地整理开发

标准》为编制依据,结合本项目的特点编制的

2、相关部门(水利、交通、农业、林业、环保、电力、旅游)对本

工程建设期间的要求及协议。

3、当地城镇现有修配、加工能力,生活、生产物资和劳动力供应条

件,居民生活、卫生习惯等。

4、本工程采用的技术规范(但不限于)如下:

①、TDT《土地开发整理规划编制规程》

②、TDT《土地开发整理项目规划设计规范》

③、TDT《土地开发整理项目验收规程》

④、SL72-94《水利建设项目经济评价规范》

⑤、GB《灌溉与排水工程设计规范》

⑥、

⑦、GBT16453..6-1996《水土保持综合治理技术规范》

⑧、SL207-98《节水灌溉技术规范》

⑨、GBT《泵站设计规范》

⑩、GBJ201-83《土方与爆破工程施工及验收规范》

652

三、施工部署

㈠、技术准备

1、实行项目经理负责制,一切工作由项目经理部负责主持和召集。

项目经理按施工组织设计的要求负责统筹部署和实施本工程施工

的各项工作。

2、由项目经理组织各专业施工人员,熟悉审查图纸,做好图纸洽商和

会审,掌握地质基本情况,明确国家标准水准点的编号、标高,明

确纵横坐标,掌握河流、输电线路、道路、植被等基本资料。

图纸

洽商和会审内容应保证齐全、有效,经设计部门、现场指挥部门、

监理部门签字(盖章)生效后,及时送发相关部门,并保存其原件。

3、编制材料预算,对安装的设备、外购构件、部件作好明细表,表明

名称、数量、规格、型号等及进场时间,提前订货及时进场。

4、编制机具计划,落实机具和进场时间。

5、编制好周转材料计划,准备好物资。

6、进场前,由项目经理部组织对参与施工的技术、管理人员、班组长

责任,落实责任到人。

7、组织参与施工的技术管理人员、班组长进行施工规范及质量标准的

学习,并对安全、文明施工的要求进行交底。

培训施工人员,让其

掌握土地开发、整理、复垦工程中最新应用的新技术、新工艺,凡

考核合格的方可上岗

752

8、对劳动力进行与工程有关的施工规范及质量