DOCUMENTCONTROL
1.Thisdocumentisa“ControlledDocument”
CopyNumber.-----------------------------
IssueTo-------------------------------------
2.Unauthorizedduplicationofthisdocumentisnotallowed.PleaseseedetailinDocumentControlprocedure(QMR-PR-002).Pleasecontactdocumentcontrolcenterforanydistributionorrevisionofthisdocument.
DOCUMENTDISTRIBUTIONLIST
Thisdocumentisdistributedtothefollowingrecipient:
CopyNumberRecipient
2.0QMR
3.0QCdepartment
4.0ProductionControl&
MaterialControldepartment
5.0Engineeringdepartment
6.0Purchasingdepartment
7.0PDK/Bdepartment
8.0MembraneManufacturedepartment
9.0Moldingdepartment
1.0Purpose
TodefinethefunctionandprocedureofIQCsectionwhichisresponsibleforensuringthatonlypurchasedpartsthatwhichconformedtothespecifiedpurchasingrequirementareallowedtouseinproductionlinebysamplinginspection.
2.0Scope
ThisprocedureisappliedforthepartsthatunderIQCinspectionfromthefollowingsources:
a)Localparts(fromChina)
b)Rawmaterial(RawmaterialforIM,MBproduction)
c)ProductionChemicals(Paints,Inks,Greases,Oils,etc.)
3.0References
a)PurchasingProcedure(PS-PR-002)
b)FirstArticleRequestApprove(EN-PR-003-F01-I)
c)AmericanNationStandardforSamplingProcedureandTableforInspectionANSI/ASQCZ1.4-1993
d)SupplierQualityEngineeringProcedure(QC-PR-009)
e)ProhibitedandRestrictedSubstancesManagementSystem(EN-PR-008)
4.0Definition
IQC:
IncomingQualityControl
QC:
QualityControlDepartment
IQE:
IncomingQualityEngineering
SQE:
SupplierQualityEngineering
IM:
InjectionMoldingDepartment
MB:
MembraneDepartment
KB:
KeyboardDepartment
FAA:
FirstArticleApproval
DO:
DeliveryOrder
SCAR:
SupplierCorrectiveActionRequisition
MC:
MaterialControl
PC:
ProductionControl
PCBA:
PrintedCircuitBoardAssembly
AQL:
AcceptableQualityLevel
VOIR:
VendorOutgoingInspectionReport
IRR:
InspectionReportandRecord
DIR:
DailyInspectionRecord
COC:
Certificatedofconformance
WI:
WorkInspection
DIL:
DailyInspectionLog
NDRR:
Nonconformingdispositionrequest&
record
PCS:
Partschecksheet
BOM:
BillOfMaterial
EMR:
EnvironmentManagementRepresentative
PRE:
ProhibitedandRestrictedSubstancesControlEngineer
PRS:
ProhibitedandRestrictedSubstances
PRSS:
ProhibitedandRestrictedSubstancesManagementSystem
II:
InspectionInstruction
5.0Responsibility
ItisresponsibilityofIQCsectionheadtoensurethatthisprocedureisappliedtotheproductsunderabovescope(clause2.0)andtoensurethatthisprocedureiswelltrainedtotheIQCpersonnelandcompletelyfollowed.
6.0Procedure
6.1PartsClassification
Foreaseofcontrolmanagementandimprovement,theincomingpartsareclassifiedto
Followinggroups:
a)Localparts(partfromvendorinlocalChina)
b)Rawmaterial(rawmaterialofIM,MB)
c)ProductionChemicals(Paints,Inks,Greases,Oils,etc..)
6.2IQCStandardandControl
AsfollowingaredocumentsandstandardswhichIQCsectionusedtobereferenceforinspectionandcontroloftheincomingparts.
NameReceivedFrom
a)PCSEngineeringDepartment
b)FirstArticleRequestandApproval(FAA)EngineeringDepartment
c)ApprovedColorChipEngineeringDepartment
d)ProcessChangeNotice(PCN)EngineeringDepartment
e)BOMofnewpartfornewmodelEngineeringDepartment
f)PRSApprovalReportandPRSApprovalRecordEngineeringDepartment
6.2.1PCS
a.)PCS(approvalbyFJSW)isworkinginstructionforinspectortoinspectmeasureandtesttheincomingpartsprioracceptanceofpartquality.Anypart/materialthatengineeringorFJSWnotestablishPCSisnotrequiredtoinspect.
b.)OncereceivingBOM&
PCSfornewmodelornewversionfromProjectEngineer,IQCGroupLeadershallstarttoprepare/requesttheequipmentforindividualpartinspection.AndIQEshouldprepareIIofthenewpartsforinspectortoinspectcorrectly.
c.)TheIQCGroupleaderorIQEshallpreparetheinstructionoftestingandjig/fixture.Thentraintheinspectortounderstandtheinstructionbeforestartingtoinspecteachpart.
d.)ThePCSshallalsobeareferenceforpartqualitycontrolandPRScontrolatvendoroutgoinginspection.
e.)FollowcheckitemsinPCSdoesnotvacatetheresponsibilityofvendorandIQCfromotherspecifiedpointsinthedrawingorSpec.sheet,includingPRS’controlrequirement.
f.)ThePCSshallbepreparedthenapprovedfromprojectorengineerorFJSWtobereadyforusagepriorthearrivaloffirstlotofnewpart.
6.2.2FAA/FAIorToolingapproval
a.)IQCshallreceivetheFAA/FAIorToolingapprovalsampleanddatathatapprovedbyFJSW/ProjectEngineer,andPRSApprovalReportfromPRE.
b.)FAAsampleorToolingapprovalsampleanddatauseasstandardqualitysamplereferencebeforeIQCstarttoinspecteachpart/materialforensuringthequalitybeforesenttoproductionline.
c.)IQCshallnotinspecteachpart/materialifnothaveFAA/FAIorToolingapprovalsamplefromFJSW/ProjectEngineerandPRE.
d.)MastersampleanddataofFAI/FAAorToolingapprovalshallbekeepingatvendorIQCsectionandEngineerDepartment.
e.)FAA/FAIorToolingapprovalsampleanddatashallbekeepuntilmodel/part/materialchangetherevisionofstopproduction/using.
f.)FAA/FAIorToolingapprovalsampleInspectionshallbedonebyEngineering/ProjectEngineerandQCofvendor.ButsometimeIQCshallbehelpthemtoinspectwhenevertheyrequestandIQChavetime,WI,PCSandmanpowerenoughtosupportthem.
g.)OnceIQCreceivedFAI/FAAorToolingapproveddocumentorsamplemustrecordinconcernformatforevidencethenkeepinfile/cabinet.
6.2.3ApprovedColorChip
ProjectEngineer/EngineeringDepartmentshallsendtheApprovedColorChiptoIQCsectionheadorIQCGroupLeader.WhenIQCreceive,itmustrecordinconcernformatforevidencethenkeepincabinet,iffoundanydefectormorethan1yearthenreviewitagainfoundanydefectshouldrequestnewcolorchipfromengineeringDepartment.
6.2.4PCN
ProjectEngineer/EngineeringDepartmentshallsendthePCNtoIQCsectionheadorIQCGroupLeader.WhenIQCreceive,itmustrecordinconcernformatforevidencethenkeepincabinet.
6.2.5BOMofnewpartfornewmodel
ProjectEngineer/EngineeringDepartmentshallsendthepartlisttoIQCsectionheadorIQCGroupLeadertoprovidenecessaryresourceofIQCforinspectionofnewpartofnewmodel.WhenIQCreceive,itmustrecordinconcernformatforevidencethenkeepinfile/cabinet.
6.2.6WIofelectronictestingmachine/equipment
a.)IQEorIQCgroupleadershallprepareWIofelectronictestingmachine/equipmenttouseitcorrectlyandsendtoISOcenterforregister.
b.)ISOcentershallbeissueWIofelectronictestingmachine/equipmenttoIQCtoprovidenecessaryresourceofIQCforinspectionanduseastrainingdocumentfortrainIQCinspectoralso.
6.2.7PRSApprovalReportandRecord
a.)Whenapprovalofnewpartofnewmodel,PREshallpassPRSApprovalReportandPRSApprovalRecordtoIQC
b.)ThesedocumentsarethereferenceforIQCtoverifythecomplianceofPRScontrolrequirementbeforeacceptanceofdelivery.
c.)VerificationCriteriaandmethodshallrefertoQC-I-WI-400.
6.2.8ProductionChemicalsinspection
ProductionChemicalsinspectionshallrefertoQC-I-WI-536.
6.3InspectionInstruction(II)
6.3.1IQEshallprepareinstructionforinspectionofmaterialcompliancebeforeacceptanceofdelivery.
6.3.2Thecheckitems,methods,tool/equipmentused,referencestandard,frequency,etc.,shallbeaccordingtoIQCStandardandControlin6.2.
6.3.3ItshallapprovedbyQCmanager,andifitneedmodify,itshouldbeapprovedagainafterupdate.
6.4IQCInspector
6.4.1IQCinspectorisresponsiblepersonwhoconductinspectionofincomingpartqualitybyfollowingIIandPCS.
6.4.2IQEandIQCGroupLeaderistheresponsiblepersontotraintorelatedIQCinspectorhowtousetools、equipmentorjig/fixtureforinspection、measuringandtesting,toknowvariousIQCstandard,inspectionreportandjudgmentskill,priortoconductinspection.
6.5InspectionReportandRecord
6.5.1“InspectionReportandRecord”(IRR,QC-PR-002-F01)isusedforrecordingthedatathatisinspected,measuredandtestedbyIQCinspector.Inaddition,IRRisalsousedtobeinspectionhistoryofindividualpartandalsousedforrecordingofPCN,correctiveaction,switchingofinspectionlevelandotherremarks,commentandcautionofpartqualityproblemforremindingIQCinspectorinthenextinspection.Ifnecessarybaseonthenatureofparts,theadditional“DataSheet”(QC-PR-002-F02-1,-2,-3,-4,-5)mayberequiredifthenumberofpointtobemeasuredmorethanthedatatableprovidedintheIRR.
6.5.2“DailyInspectionRecord”(DIR,QC-PR-002-F03)isusedforrecordingdailyworkofeachinspectorforcapacityevaluationandhistorykeeping.Ifanylotisrejected,therecordshouldbewrittenin