SupervisionPlan
SupervisionPlan
FromOctober20,2004toSeptember10,2005
Contents
Generaldescriptionoftheproject
Thescopeofsupervisionwork-----goalandbasis
Theorganizationchart-----personnelandresponsibilities
Thedetailsofsupervisionwork-----methodsandactions
Thesupervisionsworkingregulationsandprocedures
Supervisionfacilities
SupervisionCompany(Signature):
Chiefsupervisor:
Chiefengineer:
Date:
Contents
Chapter1Generaldescriptionoftheproject3
1.Generaldescriptionoftheproject3
2.Theprojectgoal3
Chapter2Supervisionwork4
1.Thescopeofsupervisionworkandperformancegoal4
2.Thesupervisionbasis4
3.Supervisionworkandtheworkingprocedures6
4.Supervisiononthecriticalpartsoftheproject14
Chapter3Thesitesupervisionorganization15
1.Thefigureoforganizationstructureofthesitesupervisiondepartment15
2.Supervisionpersonnelresponsibility15
Chapter4Controlmeasuresofthesupervisiongoal17
1.Constructionqualitycontrolmeasureanddocumentinformationmanagement17
1.1Qualitycontrolbeforeexecution17
1.2Qualitycontrolduringtheexecution…………………….18
1.3Qualitycontrolaftertheexecution
1.4Qualitycontrolofthenecessaryrawmaterials,semi-finishedgoodsandplantandequipmentoftheproject…………………………………………………………………………….22
2.Progresscontrolmeasuresandorganizationcoordination………………………….23
2.1Advancecontroloftheprogress…………………………………………..24
2.2Coursecontroloftheprogress……………………………………………..24
2.3Followingcontroloftheprogress…………………………………………..25
3.Investmentcontrolmeasuresandcontractmanagement……………………………………26
3.1Advancecontroloftheinvestment………………………………………………..26
3.2Coursecontroloftheinvestment……………………………………………………26
4.Managementmeasuresforsafetyconstruction………………………………………………29
5.Managementmeasuresforcivilizationconstruction………………………………………….30
Chapter5Sitesupervisionworkingregulations…………………………………………………..32
1.Regulationsforthetwo-levelexaminationofthedesigndocumentsanddrawings…………….32
2.Regulationsforthetechnologycommunication…………………………………………………33
3.Regulationsfortheapprovalofthecommencementreport……………………………………33
4.Regulationsfortheexaminationandreexaminationofthematerialsandcomponents…….33
5.Regulationsforthedesignvariations…………………………………………………………….33
6.Regulationsfortheexaminationsoftheconcealedwork………………………………………..33
7.Regulationsfortheconstructionqualitysupervision…………………………………………….34
8.Regulationsfortheconstructionqualitytest……………………………………………………..34
9.Regulationsforthehandlingoftheconstructionqualityaccidents…………………………….34
10Regulationsforthesupervisionandreportoftheprogress…………………………………….35
11.Regulationsforthesupervisionoftheinvestment…………………………………………….35
12.Regulationsforthesupervisionregularmeetingandreport…………………………………..35
13.Regulationsforthecompletionacceptance……………………………………………………36
14.Regulationsforthesupervisiondocumentmanagement………………………………………36
15.Regulationsforthesupervisorypersonnelself-discipline……………………………………..37
16.Regulationsforthesupervisionstand-by………………………………………………………37
17.Regulationsforthesupervisionsampleperformanceandtesting.……………………………...38
Chapter1Thegeneraldescriptionoftheproject
1.TheGeneraldescriptionoftheProject
1.1Client:
BLPConstructionMaterial(SuZhou)LTD.
1.2NameoftheProject:
BLPConstructionMaterial(SuZhou)LTD.FactoryandOfficeBuildingProject
1.3SiteLocation:
SuZhouSND
1.4ProjectScale:
About58000㎡
1.5ProjectInvestment:
About70,000,000RMB
1.6Contractor:
ChinaJinYeConstructionEngineeringCompany
2.ProjectGoal
2.1Timeschedule:
280Days
2.2Quality:
ConstructionQualityissatisfactory.
Chapter2SupervisionWork
1.Thescopeofsupervisionworkandperformancegoal
1.1Supervisionscope
Thesupervisionworkmainlyincludesqualitycontrol,progresscontrol,contractmanagement,informationmanagement,HSEmanagementandcomprehensivecoordinationandtrackservicesduringthemaintenanceperiodonallthecivilengineeringworks,M+Einstallations,decorationworksandoutdoorworksoftheproject.
1.2Thesupervisionperformancegoal
1.2.1Thequalitycontrolgoal:
makingtheprojectsatisfactoryinquality.
1.2.2Thetimeschedulecontroltarget:
meetingthecontractrequirements.
2.Thesupervisionbasis
2.1Thelaws,legislations,regulationsandpoliciesrelatingtotheconstructionsupervisionconstitutedbythenationandlocalgovernmentsandthedepartmentsatalllevels.
2.1.1ConstructionQualityAdministrationStatutes(OrderNo.279ofStateCouncil)
2.1.2RelevantdocumentsattachedtotheConstructionQualityAdministrationStatutes.
2.1.3The“CompulsoryConstructionStandard”(2002latestversionofthebuildingpart)
2.1.4JiangSuprovincialconstructionadministrationregulations.
2.2Theconstructionsupervisioncontractbetweentheclientandthesupervisioncompany.
2.3Theprojectdesigndocuments(includingdesigndrawingsandvariations),memos,minutesandotherdocumentsapprovedbytheclient.
2.4Theconstructioncontractbetweentheclientandthecontractor,tenderingdocumentsandotheransweringdocuments.
2.5Theprevailingcostestimatebasisandcostadministrationdocuments.
2.6Themaindesigncodesandconstructionspecificationsusedintheproject
2.6.1ConstructionsupervisioncodeGB50319-2000
2.6.2Unifiedstandardfortheconstructionqualitycheck.
2.6.3ThequalitycheckandacceptanceforthefoundationworksGB50202-2002
2.6.4ThequalitycheckandacceptanceforofthemasonrystructureworksGB50203-2002
2.6.5ThequalitycheckandacceptancefortheconcretestructureworksGB50204-2002
2.6.6ThequalitycheckandacceptanceforthesteelstructureworksGB50205-2001
2.6.7ThequalitycheckandacceptancefortheroofworksGB50207-2002
2.6.8ThequalitycheckandacceptanceforfloorworksGB50209-2002
2.6.9ThequalitycheckandacceptanceforthebuildingdecorationworksGB50210-2002
2.6.10ThequalitycheckandacceptanceforthewatersupplyanddrainageandheatingworksGB50242-2002
2.6.11Thequalitycheckandacceptancefortheventilationandair-conditioningworksGB50243-2002
2.6.12ThequalitycheckandacceptancefortheelectricalinstallationworksGB50303-2002
2.6.13SpecificationfortheporousblockstructureJGJ137-2001
2.6.14UnifiedstandardforthereliabilityofthedesignofthebuildingstructuresGB50068-2001
2.6.15DesignCodeforfoundationsGB50007-2002
2.6.16DesignCodeforconcretestructuresGB50010-2002
2.6.17DesignCodeforanti-earthquakeofthebuildingGB50011-2001
3.Supervisionworkandworkingprocedures
3.1Preparationperiod
3.1.1Examinationoftheconstructiondrawings.
3.1.2Examinationofthenecessaryapprovalsandqualificationsbeforecommencement.
3.1.3Inspectionoftheconstructionsite.
3.2Constructionperiod
3.2.1Toassisttheclientinorganizingthediscussionondesigndrawingsandinexaminingthedesignchanges.
3.2.2Tocheckthepreparationworkofeachcontractor,tosupervisethemsetupandperfectqualityassurancesystem,safetyandcivilizationconstructionsystemandensuretheirnormaloperations.
3.2.3Checkthecontractor’sConstructionPlan,ConstructionTechnicalSchemeandConstructionProgressPlanandsoon,andputforwardsuggestionsandensurethereviseandimplementation,issuethecommencementinstructionafterreportingtotheclient.
3.2.4Checkthesubcontractingworkwhichisputforwardbythecontractor.
3.2.5Helptheclienttopreparethemonthlypaymentplan,checkthecompletedquantity,approvethemonthlypaymentreport,checkthevariationbudget,andreportthevariationsduringtheexecutionperiodforapprovalintime.
3.2.6Checkthequalityofthematerials,semi-manufacturedgoodsandequipmentusedintheproject,requirethereexaminationorchangeoftheunqualifiedmaterials,semi-manufacturedgoodsandequipment.
3.2.7Supervisethecontractorexecutestheconstructioninaccordancewiththecurrentcodes,norms,standardsanddesignrequirementsstrictly.Supervisetheexecution24hoursadayonsitetocontrolthequalityoftheworkwhennecessaryandduringthekeypointexecution.
3.2.8Checkthequalityofthework,examineandsigntheacceptanceoftheconcealedworkandsections,ensurethecontractorimplementthecontractstrictly,instructthecontractorcorrecttheworkwhichviolatesthecodes,normsseriouslyandissuetheinstructionofstoppingworkwhennecessary.Participateindealingwiththeinvestigationandanalysisofthequalityaccidentandsupervisetheimplementationofthedecision.
3.2.9Coordinatetheconstructionprogressofeachcontractor,supervisethecontractorimplementthecontractanddealwiththecontractor’stimeandcostclaimscorrectly.
3.2.10Keepthecopyoftheinsurancedocuments,remindtheclientorthecontractortransacttheinsuranceandassisttheclientorthecontractorcarryouttheinsuranceclaims.
3.2.11Supervisetheimplementationofthecontract,assistdealingwiththecontractdisputeandclaims,settlethedisputebetweentheclientandthecontractorandtheinternalcontractors.
3.2.12Examinethecontractor’sprogressplan,controltheprogressandensuretheprojectcompletedontimeaccordingtothecontract.
3.2.13Examinethedesignvariationsstrictlyandgettheclient’sapprovalwhenbeyondtheagentauthority.
3.2.14IssuethepaymentcertificateaftertheexaminationofthequalityandquantitybythesupervisorystaffaccordingtotheConstructionContract.
3.2.15Supervisethecontractorarrangethecontractdocumentsandconstructiontechnicaldocumentsaccordi