TheContractor'sRoleinBuildingCostReductionAfterDesign
Ithasbecomeevidentfromrecentnewsarticlesthatinflationarypressuresandincreasedconstructionactivityarecausingmanybuildingprojectstocomeinwelloverowner'sbudgets.Thistrendhasincreaseddramaticallyoverthepastfewyears,asmuchoftheconstructionindustryhasbeenimpactedbyanunprecedentedincreaseinthecostofconstruction.Thehistoricalrateofincreaseinconstructioncosthasbeenunderfivepercentperyear,asreportedbytheEngineeringNewsRecord.Overthelastfewyears,theindustryhasseenasignificantincreasefromhistoricalescalationrates,upto10-15percentperyearinmanyregionsoftheUS.Theseincreaseshavebeencausedbyavarietyoffactors,includingthefollowing.
•ShortageofsteelresultingfromrapidgrowthinChina.
•DemandformaterialsintheUSresultingfromincreasedhurricanedamage.
•Risingoilpricesleadingtohighermanufacturingandtransportationcost.
•Risinglaborcostbecauseofincreasedconstructionactivity.
Tobesuccessfulinhavingoverbudgetprojectsawarded,thebuildingcontractorhashadtotakeaproactiveroleinworkingwithownersanddesignteamstoreduceprojectcosttoamountsthatownersareabletoaward.Thiscostreductionisnormallyaccomplishedthroughthefollowingmethods.
•valueengineering;
•scopereduction;
ValueEngineering
Valueengineering(VE)hasbeendefinedasasystematicmethodtoimprovethevalueofgoodsandservicesbyusinganexaminationoffunction.Value,asdefined,istheratiooffunctiontocost.Valuecanthereforebeincreasedbyeitherimprovingthefunctionorreducingthecost.
Itisaprimarytenetofvalueengineeringthatqualitynotbereducedasaconsequenceofpursuingvalueimprovements.VEisaprocessoriginatingatGeneralElectricCompany(GE)duringWorldWarII.Becauseofshortagesofskilledlabor,rawmaterials,andcomponentparts,engineersatGE
lookedforacceptablealternatesandoftenfoundsubstitutionsthatresultedinreducedcostsand/orproductimprovement.
GEdevelopedasystematicprocessthattheycalledvalueanalysis.OvertheyearsthenamegraduallychangedtoVE.ThebasicstepsofVEincludethefollowing:
•Informationgathering:
projectrequirementsdefined,functionanalysis.
•Alternates:
variouswaysofmeetingtherequirementsandfunctions.
•Evaluation:
assessmentofalternatesonhowwelltheymeetrequirementsandcostssavings.
•Presentation:
selectionofbestalternativestobepresentedtoclientfordecisions.
TrueVEevaluateslifecyclecostssuchasinitialcost,maintenancecost,operationalcost,lifespan,timevalueofmoney,replacementcost,andfrequencyofreplacement.VEcanbeundertakenatanystageofthebuildingdesignprocess;however,itismosteffectiveintheearlystages,sinceitislesscostlytomakechangestopreliminarydocuments.
ScopeReduction
Scopereductioninvolvesidentifyingareasoftheprojectscopeofworkthatcanbereducedinquality,quantity,orbothinamannerthatisacceptabletotheowner.
Scopereductionitemsofworkoftenconsistofmaterialorequipmentsubstitutionsthatlowerthecostoftheproject,butmaynotbeanequalsubstitute.Anexampleofquantityscopereductionwouldbetoreducethegutteringsystemonapitchedrooffromtheentireroofperimetertoentrancesonly.Aqualityscopereductionexamplewouldbetoprovidevinylcompositionfloortiles(VCT)inlieuofceramicfloortiles.
Afteraprojecthasbeendeterminedtobeoutofbudgetbecauseofhighbids,theprojectisnormallyeithercancelled,redesignedandre-bid,ornegotiationsareheldwiththelowbiddertoreachanacceptablecontractamount.Forthebuildingcontractorthatisselectedfornegotiations,thisisanopportunitytomovetowardprojectawardandtoalsobuildarelationshipoftrustandopennesswiththeowneranddesignteamthatcouldleadtofutureprojects.
First,thebuildingcontractorshouldmeetwiththeowneranddesignteamtofullyunderstandtheownersprojectrequirements,priorities,lifecycleconsiderations,andbudget.
Next,thebuildingcontractor'sroleistousehisestimatingandconstructionexpertisetoanalyzevariouscomponentsandsystemswithintheprojectforalternatesolutions.Thecontractorshouldalsobringinkeysubcontractorsandsupplierswhoareoftenabletoidentifyalternatematerialsand/orsystemswithintheirspecialties.EachdivisionofworkshouldbeexaminedandevaluatedforVEsolutions.Inpastyears,thisprocessandservicewasconsideredpartofthebuildingcontractorsoverhead.However,intoday'smarket,somecontractorswillnegotiateratesandbereimbursedforthetimeandeffortthattheyspendinthisprocessintheeventthatthe
projectisnotawardedtothem.
Theworkbreakdownstructure(WBS)canbeahelpfultooltothebuildingcontractorinanalyzingthevariouscomponentsandsystemswithinabuildingproject.TheWBSisatree-typestructureoffunctionalsystemsusedtoclassifytheprojectonalevel-by-levelbasis.Thisbreakdownstructurefacilitatestheevaluationofeachsystemoftheprojectfromthebuildingfoundationstothecompletedsitework.
QuestionstoAskorAreasand/toConsiderbyWBS
Thissectionprovidesalistofareasforthebuildingcontractortoexamineand/orquestionstoaskintheWBSsystemlevelformatforcostsavingalternatives.Someofthesechangescanbeaccomplished
withoutmajorre-designcostandincorporatedintotheconstructiondocumentsintheformofanaddendum.Otherchangeslistedwouldrequireextensivere-designandtimedelays.
SUBSTRUCTURE
—Havealternatetypesoffoundationsystembeenconsidered?
•woodpilesinlieuofprecast;
•drilledcaissonsvs.piles;
•matfoundationsinplaceofpilesorcaissons.
—Evaluatesandbaseinplaceofgravelorstoneunderslabongrade.
SUPERSTRUCTURE
—Havealternatetypesofbuildingstructuresbeenevaluated?
•structuralsteel,precastconcrete,castinplaceconcrete,lightgaugesteelframingorwoodframingsystems.
—CompareAlternateStairSystems.
•steelpanstairsvs.precastconcreteorcastinplaceconcrete.
EXTERIORCLOSURE
—Evaluateexteriorwallsystems.
•Lightgaugemetalframinginlieuofreinforcedconcretemasonryunits.
•Canwallwidthsorgaugesbereduced?
—Comparesheathingsystems.
•Fibersheathingsinplaceofcementboards.
—Reviewalternatewallinsulationsystems.
•Battinsulations,rigidinsulationmaterials,loosefillblockinsulation.
—Consideralternateexteriorwallveneers.
•Conventionalstuccoversusexteriorinsulationfinishsystem.
•Brickorprecastinlieuofstone.
—Evaluatealternateglazingsystems.
•Canexteriorglazedareasbereduced?
•Storefrontsinlieuofcurtainwallsifcodeallows.
•Paintedaluminuminlieuofstainlesssteelorbrassframing.
—Reviewexteriorentrances.
•Manualentrancedoorsinplaceofautomaticentrances.
•Automaticentrancesinlieuofrevolvingdoors.
•Cedarentrancedoorsratherthanmahogany.
—Examineexteriorrailingsystems.
•aluminumorcablesystemsinlieuofglass;
•standarddesignsinplaceofcustomelements;
ROOFING
—Evaluatethespecifiedroofingwithalternativematerials.
•Combinedmetaldecking/insulationsystemsinlieuofseparatesystems.
•Interiorbattinsulationinplaceofrigidroofinsulation.
•Built-uproofingvs.singleplymembranes.
•Fiberglassorconcretetilesinlieuofclaytiles.
•Paintedmetalsinplaceofcopper.
•Canthespecifiedgaugeofmetalroofingbelowered?
•Eliminateorreducethegutteringsystem?
•Canskylightsbereducedorstyleschanged?
•Arestandardwarrantiesspecified?
INTERIORCONSTRUCTION
—Examineinteriorwallsystems.
•Canlightgaugemetal-framedwallsbeusedinlieuofconcretemasonryunits?
•Canwallthicknessesorgaugesbereduced?
•Aredrywallsystemsbeingusedinlieuofplaster?
Examineinteriordoorsandhardware.
•Arethespecifieddoorsstandardsizesorcustom?
•Havealternatewooddoorspeciesbeenconsidered?
•Havealternatehardwarestylesormanufacturersbeencompared?
•Canmanualdoorsbeusedinlieuofautomatic?
•Arethedoorspre-machinedforhardwareinstallation?
•Comparepre-finishingdoorswithfinishingon-site.
—Reviewinteriorspecialties.
•Havealternatetypesoftoiletpartitionsbeenconsidered?
•Prefinishedmetalsvs.plasticlaminates.
•Canvinylcornerguardsbeusedratherthanmetal?
•Metallockersvs.wood.
•Havespecialpartitionsbeenevaluated?
•Plasticveneersinlieuofwood.
•Canthesoundratingbereduced?
•Deferinstallation?
•Hastheaccessflooringsystembeenevaluated?
•Standardfloorfinishesratherthancustom?
INTERIORFINISHES
—Evaluateinteriorwallfinishes.
•Paintedwallfinishesinlieuofwallcovering.
•Epoxycoatingsinplaceoftilefinishes.
•FRPinsteadofstainlesssteel.
•Aretextureddrywallsystemsbeingusedratherthanplaster?
—Examineinteriorfloorfinishes.
•Resilientflooringvs.ceramicorwood.
•Ceramicflooringinlieuofstone.
•Tileorstoneinplaceofterrazzo.
•Alternatecarpetmanufacturers.
—Reviewalternateceilingfinishes.
•Standardceilingvs.custom.
•Fiberceilingvs.metal.
CONVEYINGSYSTEMS
—Reviewspecifiedelevatorsandescalators.
•Havealternatemanufacturersbeenconsidered?
•Arestandardinteriorelevatorcabfinishesspecifiedorcustom?
•Canglasswallsbeeliminated?
•Arestandardwarrantiesspecified?
SITEPREPARATION
•Hasasiteworkanalysisbeenperformedtobalancecutsandfills.
SITEIMPROVEMENTS
•Canpavedareasbereducedormoreeconomicalpavingmaterialsused?
•Hasresurfacing