FIDIC招标程序.docx
《FIDIC招标程序.docx》由会员分享,可在线阅读,更多相关《FIDIC招标程序.docx(44页珍藏版)》请在冰豆网上搜索。
FIDIC招标程序
FIDICTenderingProcedure
国际咨询工程师联合会,中国工程咨询协会编译,中国计划出版社
Foreword
TheInternationalFederationofConsultingEngineers(FIDIC)publishedthefirsteditionofTenderingProcedurein1982・ThefirsteditionprimarilyaddressedprocedureswhichFIDICrecommendedfortheselectionoftenderersandthepreparationandevaluationoftendersforcivilengineeringcontracts・Thedocumentreflectedtheprovisionsofthethencurrent(thirdedition)oftheFIDICConditionsofContract(International)forWorksofCivilEngineeringConstruction.
Followingthepublicationofthe4theditionoftheConditionsofContractforWorksofCivilEngineeringConstnictionandthe3rdeditionoftheConditionsofContractforElectricalandMechanicalWorksin1987,andtakingintoaccountcurrentthinkingofthemajorinternationalfinancinginstitutions(IFIs),FIDICdecidedtoreviewandupdatethe1982edition,reflectingcurrentpracticeintheindustry.
Inviewofthewideacceptanceandacknowledgedusefulnessofthefirstedition,itwasfurtherdecidedtoretain,asfaraspossible,thebasiclayoutandformatinorderthatusersofthedocumentwouldstillbefamiliarwiththeproceduresdescribed・
Muchoftheupdatingworkhasinvolvedmodificationofterminologyandprocedurestomakethedocumentequallyapplicableinrespectofbothcivilworksandelectricalandmechanicalprojects.Inaddition.thedocumentmorecloselyreflectstheproceduresrecommendedbytheIFIs,anddrawsattentiontothoseareaswheretheIFIprovisionsaremandatory.
Thedocumentprovidesafreedomandflexibilitywhichisnotfoundinallsimilardocuments・Thismeansthattheproceduresdescribedcanbeadaptedandusedinconjunctionwith,forexample,proceduresnormallyadoptedbyemployersorproceduresrequiredbytheIFIs.Usersshouldhoweverbeawareoftheprevailingrequirementsand/orrestrictionsintroducedwhenusingparallelproceduresandensurethatallmandatoryprovisionsofsuchproceduresareproperlyincorporated.
AusefuladditiontobefoundinthisneweditionisthefirstchapterentitledProjectStrategy,whichprovidesguidelinesandpracticalsuggestionsonhowtoestablishaneffectiveandappropriatemethodforprojectprocurement.Thischapterissupportedbyanewappendix(AppendixI)whichshows,intabularform,thedifferentmodelscommonlyusedforprojectimplementation.
FIDICbelievesthattheneweditionprovidesacomprehensiveandcompleteprocedure,compatiblewithotherrecognizedtenderingprocedures,whichwillencourageandenhancetheultimateobjectiveofreceivingresponsiveandcompetitivetenders・
Introduction
Thisdocumentpresentsasystematicapproachfortenderingandawardingofcontractsforinternationalconstructionprojects.Itisintendedtoassisttheemployer/engineertoreceivesoundcompetitivetendersinaccordancewiththetenderdocumentssothattheycanbequicklyandefficientlyassessed.Atthesametime・anefforthasbeenmadetoprovidetheopportunityandincentivetocontractorstorespondeasilytoinvitations*otenderforprojectswhichtheyarequalifiedtoimplement.Itishopedthattheadoptionofthisprocedurewillminimisetenderingcostsandensurethatalltenderersreceiveafairandequalopportunitytosubmittheiroffersonareasonableandcomparablebasis・
Experiencehasshownthatforprojectsinvolvinginternationaltendering,prequalificationisdesirablesinceitenablestheemployer/engineertoestablishthecompetenceofcompaniessubsequentlyinvitedtotender,itisalsointheinterestofcontractorssince,ifprequalified.theywillknowthattheyarecompetingagainstalimitednumberofotherfirms,allofwhompossesstherequiredcompetenceandcapability.
Themodelproceduredescribedinthetextisaccompaniedbynoteswhich,foreaseofreference,followeachclause.Thenotes,initalics,areaddedtothetextinordertoexpanduponthemoreimportantaspeersofeachclauseand,whereappropriate,givealternativecoursesofactionthatmayhavetobeconsideredaccordingtocircumstances・Thetextisillustratedbyaflowchartwhichfollowsthisintroductionandservesasasunimary.Boththetextandthenoteshavebeenkeptasbriefaspossibleinorderthatthebookletcanbeeasilyusedasaworkingdocument.
Theprocedureissuitablefortenderingformostinternationalconstructionworks,butitmaybeadaptedtosuittheparticularrequirementsoccasionedbythesizeandcomplexityofaproject,andanyspecialconditionsimposedbytheestablishedproceduresoftheemployerorthefinancinginstitutions・Itreflectsgoodcurrentpractice・FIDICrecommendsitsusebyemployers,engineers,contractorsandothersinvolvedintheinternationalconstmctionindustry.TheprocedureisrelatedtoFIDIC's'ConditionsofContractforWorksofCivilEngineeringConstruction”and''ConditionsofContractforElectricalandMechanicalWorks11butcanbereadilyadaptedtoanyacceptablecontractform.
PROCEDURALFLOWCHARTS
RECOMMENDEDPROCEDUREFORTHEPREQUALIFICATIONOFTENDERERS
为投标人资格预审推荐使用的程序
SECTION
EMLOPYEIVENGINEERING
CONTRACTOR
1.0
Establishmentofprojectstrategy
Establishprojectstrategycomprising:
•Procurementmethod
•Formoftendering
•Timeschedules
2.1
Preparationofprequalificationdocuments
Prepareprequalificationdocumentscomprising:
•Letterofinvitation
•Informationabout
prequalificationprocedure
•Projectinformation
•Prequalificationapplication
2.2
InvitationtoPrequalify
Placeprequalificationonadvertisementinpress,embassiesetc.Asappropriatestating:
•EmployerandEngineer
•Outlineofproject(scope,location,programme,sourceoffinance)
•Datesforissueoftenderdocuments&submissionoftenders
•Instructionsforapplyingforprequalification
•Minimumrequirementsforprequalification
•Submissiondateforcontractors'
2.3
Issue&submissionofprequalificationdocuments
Issueprequalificationdocuments&questionnairesrequestingfromeachcompany/jointventure:
•Organisation&structure
•Experienceintheintended
typeofwork&theregion
•Resources:
-managerial
-technical
-labour
-plant
•Financialstatements
•Currentcontract
commitments
•Litigationhistory
Requestprequalificationdocuments
Complete
&
submit
PQ
documents
&
questionnaires
Acknowledgereceiptv
2.4
Analysisofprequalificationapplications
Analysisprequalificationdata:
•Company/jointventurestmeture
•Experience
•Resources
•Financialcapability
•Generalsuitability
2.5
SelectionofTenders
Preparelistoftenderers
RecommendedProcedureforobtainingtenders
推荐的招标程序
Preparetenderdocuments
•Letterofinvitationtotender
•Instructionstotenderers
3・1•Conditionsofcontract
Preparationotlender•Formoftenderandappendicesdocuments•Drawings
•Billofquantities
•Scheduleofadditional
information
•Informationdata.
Visit(s)tositebytenderersaccompaniedbyemployer/engineer
3.4
Submitqueriesinwritingbygivendate
A)Preparereplies
Tenderers1queries
A)correspondenceMethod
B)tenderer'sconferencemethod
B)Informtendererspresentofqueriesandrepliessubmittedinwritingrepliestoqueriesraisedatconference
Acknowledgereceipt
Sendminutestoalltenderers
3.5
Addendato
Issueaddendaincludingrepliesto
Acknowledge
TedenderDocuments
queriestoalltenderers
Receipt
3.6
SubmissionandreceiptofRecorddateandtimeofreceiptSubmitTenders
tenderers
Acknowledgereceiptorreturnunopenedtenderersreceivedlate
RecommendedProcedurefortheopeningandevaluationoftenders
推荐的开标和评标程序
5.1
Reviewoftenders
Establishconformityandcompletenessoftenders
•Rejectsubstantially
unresponsivetenders
6.0
Awardofcontract
Ouestions:
LHowmanystagesdoesthetenderingprocedurecomprise?
2.Whatistherecommendedprocedurefortheprequalificationoftenderers?
3・WhatistheRecommendedProcedureforobtainingtenders?
WhatistheRecommendedProcedurefortheopeningandevaluation
oftenders?
ProcedureandNotes
1.0PROJECTSTRATEGY
1.1EstablishmentofProcurementMethodantiFormofTendering
InthecontextofthisdocumentthewordHprojcctHcoversallthestagesfromtheinitialideatoconstiiictagivenphysicalassettothefinaltaking-overbytheemployerofthecompletedwork.
Projectsmaybeorganizedandimplementedinaccordancewithdifferentstrategics・AbriefdescriptionofsomeoftheseisgiveninAppendixI.Whichstrategyisbestsuitedforthepurposedependson,forexample,thenatureandcomplexityoftheproject,theaccesstofinance.lifec\clccostsoftheproject,thetechnicalandadministrativecapabilityoftheemployerandthegeneralpoliticalandeconomicenvironment.
Theprojectstrategydefinesthewayinwhichtheprojectwillbeimplemented,determinestheroleofeachpartyinvolvedand.whereappropriate,specifiesthewaytheprojectwilloperate・Toalargedegreecontractualrelationshipsbetweenthepartiesandtheirindividualrights,dutiesandrisksaretherebyalsodeterminedbytheprojectstrategy.
Attheimplcincntationstageofaproject,tenderingservesasamethodtoensurethattheworkisprocuredatcompetitiveterms・
Thechoiceofstrategyisamajordecisionwhichhasfar-reachingconsequences・Onceastrategyhasbeensettleditisofgreatimportancethatitbefollowedthroughouttheimplementationoftheproject.Lackofstrictadherencetothestrategymayleadtoflawsintheprocurementprocess,resultinginclaims,disputesandextracostsforallconcerned.
Anypartofaprojectwhichcanbecoveredbyaseparatecontractmayinprinciplebemadesubjecttotendering・
Assoonastheprojectstrategyhasbeendec