卓良模板施工方案Word下载.docx
《卓良模板施工方案Word下载.docx》由会员分享,可在线阅读,更多相关《卓良模板施工方案Word下载.docx(6页珍藏版)》请在冰豆网上搜索。
四直墙模板简述..........................................................................................2
模板的组成.....................................................................................2
墙体模板组成配件.........................................................................3
工作原理.........................................................................................4
组合钢木模板的优点.....................................................................4
五模板施工要点..........................................................................................4
直墙模板拼缝结点.........................................................................4
阳角连接节点.................................................................................5
阴角连接节点.................................................................................5
六拼装模板..................................................................................................6
七模板拼装注意事项..................................................................................6
八模板吊装注意事项..................................................................................7
九单侧支架的组成......................................................................................7
十模板及支架安装......................................................................................7
埋件部分安装...............................................................................7
模板及单侧支架安装...................................................................8
十一模板及支架拆除..................................................................................9
拆模准备.......................................................................................9
拆模流程.......................................................................................9
十二单侧支架安装安全技术交底..............................................................9
一北京卓良模板有限公司简介
北京卓良模板有限公司是一家从事建筑模板及脚手架的设计、加工、开发及供应为一体的专业化公司,在近几年来的业务中,先后参加了一些国内外大型工程的模板及脚手架的设计及供应工作,如国家大剧院曲线墙体模板,国家体育场,三峡大坝永久船闸悬臂模板,二滩水电站坝体模板埋件及进水塔模板,小浪底多功能电站悬臂模板配件及明流洞隧道台车。
巴基斯坦甘孜—巴罗塔水电站厂房及引水渠的悬臂模板及支撑系统。
天生桥水电站的厂房模板及引水发电洞针梁台车。
通过业务的交往,我公司也和国内外的一些知名承包商建立了广泛的合作关系,如德国的HoctiefAG,ZueblinAG.法国的Dumez,SAE,意大利的ImpregiloSPA.中国的水电七局、八局、武警水电总队、北京城建、中建、建工和新兴等。
经过多年研究、开发及和国外著名的模板公司的合作培训,加之数年来的现场实践,北京卓良模板有限公司无论是在工民建模板,水工模板或是在道桥模板等方面均积累了丰富的经验。
目前公司下设技术部,开发部,工程部,经营部,合同部,财务部,经理办等,组织机构健全,技术及现场服务力量雄厚。
工程图片剪集
二编制依据
三工程概况
1、本工程为北京联合大学特教学楼改造工程单侧墙体施工,墙高为米,其中米为先浇反梁,对应支撑系统为1600+3600单侧支架。
2、单侧墙体长度按25米考虑
四直墙模板简述
模板的组成
模板面板为18mm厚胶合板,竖肋为方木(工地自备,规格自选),横肋为双[12号槽钢。
木梁胶合板模板具有结构合理,经济实用,标准化程度高等特点。
在单块模板中,胶合板与竖肋(方木)采用自攻螺丝连接,竖肋与横肋(双槽钢背楞)采用钩头螺栓连接,在竖肋上两侧对称设置两个吊钩。
两块模板之间采用芯带连接,用芯带销固定,从而保证模板的整体性,使模板受力更加合理、可靠。
墙体模板组成配件
篇二:
墩身施工方案
目录
1.编制说明及编制依据....................................32.工程概况..............................................3
结构介绍..............................................................................3工程特点..............................................................................4
3.施工总体部署..........................................5
施工管理及劳动力组织......................................................5质量目标及控制..................................................................6施工准备..............................................................................8施工进度计划....................................................................11劳动力组织........................................................................12资金准备............................................................................13
4.测量控制.............................................13
测量规范............................................................................13仪器配置............................................................................14人员配置:
........................................................................14施工测量............................................................................14
5.主要施工方法及技术措施...............................15
模板工程............................................................................16概述.................................................................................16翻模(卓良模板)的构造特点.....................................17预埋件安装顺序.............................................................18翻模施工工艺步骤.........................................................20
承包商:
重庆桥梁工程总公司(ChongqingBridgeEngineeringCorporation)共38页第1页
空心墩模板内支架.........................................................21双肢墩支架.....................................................................21空心墩内模.....................................................................22模板加固.........................................................................22模板安装质量要求.........................................................22墩顶实心段施工...........................................................23钢筋工程............................................................................24钢筋进场及试验............................................................24钢筋贮存.........................................................................24钢筋加工.........................................................................25钢筋接头.........................................................................25钢筋安装.........................................................................26钢筋隐检.........................................................................27钢筋加工、安装质量标准.............................................27砼浇筑工程........................................................................28
六、质量控制措施........................................35
质量控制............................................................................35质量记录............................................................................35质量控制标准....................................................................36质量保证措施....................................................................36
七、安保措施及现场文明施工:
............................37
1.编制说明及编制依据
编制说明:
本施工方案为重庆石板坡长江大桥加宽改造工程正桥1~7#桥墩墩身施工工艺。
编制依据:
设计提供的《重庆市石板坡长江大桥加宽改造工程(正桥)桥墩施工联络图》及其它参考资料。
林同炎国际(重庆)工程咨询有限公司提供的《重庆石板坡长江大桥加宽改造工程(正桥)土建及安装施工技术规范》。
《重庆长江大桥施工组织与技术》及相关资料。
相关国家标准、行业标准、技术要求及验收规范。
国家及有关部门在施工安全、工地保安、人员健康、环境保护等方面的具体规定。
我司编制的ISO9002质量体系《质量保证手册》和《程序文件》。
2.工程概况
结构介绍
主跨5#、7#桥墩为双壁实体钢筋砼桥墩,每个墩壁宽,双壁间净距,横桥向墩身总宽,由两个分水尖和9m的墩身构成,墩身高。
1#、2#桥墩墩身采用(纵)×
9m(横)的单箱单室薄壁结构,1#墩身高,2#墩身高。
1#、2#墩顶留3m高的墩顶实心段,并各设两个支座。
3#及4#桥墩墩身采用(纵)×
9m(横)的单箱单室薄壁结构,3#桥墩墩身高,4#桥墩墩身高。
空心薄壁墩壁厚均为。
立柱主筋净保护层厚度为=,保护层较大,砼表面容易开裂。
5#、7#单肢墩身截面图
1#~4#墩身截面图
墩身高度、高程、工程量统计表
工程特点工期紧迫
大桥总工期控制为20个月,工程量大,时间紧。
阶段工期要求
在洪期前必须将墩柱施工出洪水面,即在5月15日前必须将所有墩身施工至以上,此时长江水位大致为左右,确保墩身能够连续施工。
质量要求高
本工程为市政桥梁工程,桥建成后将是主城区又一道亮丽的风景线,因此,除要求结构内在质量满足设计及规范要求外,对本桥的外观质量要求也很高。
施工精度要求高
桥墩外形尺寸,钢筋位置及间距,墩轴线控制均有很高要求。
洪水影响
根据进度计划安排,在墩身施工期间,长江水位会逐渐上涨,直至施工材料无法通过从珊瑚坝陆路运输到位时,要相应考虑洪水期间施工的特殊措施。
3.施工总体部署
施工管理及劳动力组织
为保质保量完成本分项工程,在项目经理部的领导下,由施工承台的6个施工分队,分别各自负责6个墩身的施工。
每个分队选派4名精干的管理成员,具体负责现场的技术、质量、安全、进度、文明施工等。
每个分队配设钢筋工30人、模板工20人、吊装20人、质量员1人、其他工种30人。
参与墩身施工管理的现场技术人员,都经历过多座大桥施工,对
篇三:
核心筒自爬模方案
核心筒液压自爬模施工方案
一北京卓良模板有限公司简介
北京卓良模板有限公司是一家从事建筑模板及脚手架的设计、加工、开发及供应为一体的专业化公司,是中国模板协会优秀会员单位,并通过了ISO9001:
XX质量管理体系认证。
卓良模板以其优良的产品质量、优越的性价比、一流的售后服务体系、追求卓越勇于创新的工作作风和先进的设计理念受到国内外广大用户的一致赞许。
卓良模板经过多年的研究、开发以及与国内外诸多著名模板公司的精诚合作,吸收先进的设计理念和施工技术,通过对国内材质的攻关,充分利用国内运费的优势,公司逐步稳健的壮大起来,成为国内、中东地区建筑模板行业最具影响力的公司。
目前,卓良模板拥有先进的木工字梁加工车间和钢构件加工车间,主要产品均由公司自己加工制成并进行严格地质检保证了产品加工质量和精度,而与砼亲密接触的面板部分主要从欧洲芬兰著名胶合板生产厂家进口维萨?
板,保证了砼的外观质量和面板的周转次数。
公司在超高层建筑、体育场馆、桥梁、水利、厂房、隧道及核电等工程的模板体系积累了丰富的经验,以其产品受力科学、坚固耐用、拼装灵活、周转次数多、设计理念先进等优点,拥有各类模板技术专利10余项,其中主要产品已经通过了中国工程建设部级鉴定。
技术水平在国内外同行中名列前茅。
自公司成立以来,卓良模板向国内外诸多大型工程项目提供了优质的模板体系和技术服务,如:
苏通长江大桥、舟山西堠门大桥、湖北龙潭河特大桥、湖北沪蓉西高速七道沟大桥、长沙三汊矶湘江大桥、湛江海湾大桥、深圳湾公路大桥、广西谷拉河特大桥、重庆菜元坝长江大桥、钱江四桥、润扬长江大桥、上海东海大桥、陕西禹阎公路特大桥、北京乐喜金星大厦(LG大厦)、国家大剧院、国家奥体馆、三峡大坝永久船闸悬臂模板、二滩水电站坝体模板埋件及进水塔模板、小浪底多功能电站悬臂模板配件及明流洞隧道台车、巴基斯坦甘孜—巴罗塔水电站厂房及引水渠的悬臂模板及支撑系统、天生桥水电站的厂房模板及引水发电洞针梁台车。
通过业务的交往,公司和国内外的一些知名承包商建立了广泛的合作关系并受到了其广泛的好评,如德国的HoctiefAG,ZueblinAG.法国的Dumez,SAE,意大利的ImpregiloSPA.中国的水电七局、八局、武警水电总队、中铁大桥局、二公局、二航局、中铁十八局、中铁十六局、贵州路桥、四川路桥、广东长大、香港明泰、中建国际、北京城建、中兴等。
目前公司下设技术部、研发部、海外部、质检部、售后服务部、合同部、财务部、经理办等,组织机构健全、技术力量雄厚、具备全面的技术指导和培训能力,拥有一支良
好的售后服务队伍,是各类建筑承包商的理想合作伙伴。
卓良模板以”服务客户,发展自我”为目标,奉行”以人为本,技术领先”的经营理念,倡导敬业、服务、竞争、创新的企业精神,弘扬”追求卓越,品质精良”的服务理念,为用户提供优质的服务,来实现节省材料、缩短工期、降低成本,以简便的操作和低成本的摊消费用,为用户带去一流的工程质量和经济效益。
”员工智慧得到更大发挥,客户利益得到更大保护”是我们的承诺,为您提供最新的技术、最合理的价格、最可靠的质量、最完善的售后服务是我们的宗旨。
让我们携手并肩、合作博弈、共同开创美好明天。
二工程概况
结构形式
本工程为双塔钢框核心筒剪力墙结构,核心筒外形为四方形,根据吊塔设备的布臵及工期的要求,模板拟采用液压自爬。
三设计说明
概述
针对超过标准层高的楼层墙体,外墙分两次浇筑,爬模爬升两次
四液压自爬模
主要性能指标
1.名称型号:
ZL-QPM-50型液压自爬模
架体系统:
架体支承跨度:
≤5米(相邻埋件点之间距离,特殊情况除外);
架体高度:
米;
电控液压升降系统
额定压力:
25Mpa;
油缸行程:
350mm;
液压泵站流量:
/min;
伸出速度:
约300mm/min;
额定推力:
50KN;
双缸同步误差:
≤20mm。
2.爬升机构:
爬升机构有自动导向、液压升降、自动复位的锁定机构,能实现架体与
导轨互爬的功能。
3.承载能力:
①平台宽度米,设计承裁KN/sqm(爬升时/sqm);
②平台宽度米,设计承裁/sqm;
③平台宽度米,设计承裁/sqm;
④平台宽度米,设计承裁/sqm;
⑤平台宽度米,设计承裁/sqm;
⑥平台宽度米,设计承裁/sqm;
只允许两层平台同时承载;
模板爬升及模板未处于合模状态时,①平台不得放重物。
液压自爬模的爬升工艺
液压自爬模是以液压为动力,通过导轨与支架互爬实爬模板的自爬升,整个爬升过程均