土木工程施工课程设计完整版
土木工程施工课程设计
专业:
姓名:
班级:
学号:
导师:
时间:
第一章工程概况····················································1
一、建筑、结构概况···············································1
二、施工条件概况·················································1
第二章工程量计算··················································
一、土方工程量····················································
二、基础工程工程量················································
三、柱工程量······················································
四、梁工程量······················································
五、楼梯工程量····················································
六、预制板工程量··················································
七、工程量清单表··················································
第三章施工方案····················································
一、施工段划分····················································
二、工期控制······················································
三、施工顺序······················································
四、施工工艺······················································
五、施工方法·····················································
六、施工时间·····················································
七、模板方案·····················································
第四章机械设备选择················································
第五章主要技术措施················································
第六章施工总平面图··············································
第七章施工进度计划表···········································
第一章工程概况
一、建筑、结构概况
建筑设计特点:
本工程为某无线电厂生产车间,总体呈矩形分布,建筑物总高16.90m,总长54.30m,总宽21.3m;共四层,首层层高为4.5m,二、三标准层层高均为4.2m,顶层层高4.0m,屋顶为平屋顶。
结构设计特点:
本工程采用钢筋混凝土框架结构,框架柱统一截面尺寸为400mm×450mm,梁截面300mm×400mm、300mm×500mm和300mm×600mm等,楼面铺设180mm厚预应力钢筋混凝土空心板。
采用柱下独立基础,尺寸均为2050mm×2050mm,阶梯形;基础埋深为2.0m,下设100厚混凝土垫层;采用现浇混凝土板式楼梯;室外设计地坪标高为-0.45m。
二、施工条件概况
地形:
平坦
土质:
亚粘土
雨季:
4-6月份
地下水位:
最高地下水位位于地面以下2.0m
开工时间:
2016年7月8日
施工工期:
275天(根据施工定额)
钢筋:
由加工厂加工成型后运至现场。
混凝土:
采用商品混凝土,水电由市区供应。
交通:
厂内可通行车辆
材料:
建筑材料齐全,技术力量雄厚,劳动力由公司工程处统一调配。
第二章工程量计算
根据施工段的划分原则,每层分两个施工段,分界线在5号轴线柱右侧。
取1~5轴基础层为第1施工段,6~10轴基础层为第2施工段,其他层依次类推。
一、土方工程量
根据土的类别取基坑放坡系数为0.5。
基础尺寸:
2.05m×2.05m。
下底:
(四周考虑0.3m的工作面)。
上底:
。
采用机械挖土,考虑到基坑开挖尺寸及运输车辆的进出,选择采用条形开挖;不考虑地基梁所需挖土的土方量。
(1)、开挖工程量
第1施工段:
[(3×6+0.15+1.025+0.1+0.3)+(4×6+0.15+1.025+
0.1+0.3)×2+(3.75+1.025+0.1+0.3-1.325)+(6+1.025+0.1+0.3)×2]×
×(2.1-0.45)×(2.65+4.3)=512.74
第2施工段:
×6-0.15+1.025+0.1+0.3)×3]×
×(2.1-0.45)×(2.65+4.3)=538
(2)、填方工程量
a、基础回填:
第1施工段:
×[(1.2-0.45)×0.45×0.45+2.25×2.25×0.1]=459.38
第2施工段:
×[(1.2-0.45)×0.45×0.45+2.25×2.25×0.1]=493.54
b、房心回填:
第1施工段:
×(7.5-0.3)×7+(6-0.3)×(3.75-0.3)+(6-0.3)×(6-0.3)×2]×0.45=167.4
第2施工段:
×(7.5-0.3)×10×0.45-0.3×0.4×(6-0.3)
=184.0
二、基础工程工程量
(1)、基础混凝土工程量
第1施工段:
×(2.05×2.05×0.4+1.25×1.25×0.4)=41.51
第2施工段:
×(2.05×2.05×0.4+1.25×1.25×0.4)=34.59
(2)、基础钢筋工程量
第1施工段:
×36=1.5t
第2施工段:
×36=1.25t
(3)、基础模板工程量
第1施工段:
×(2.05×4+1.25×4)×0.4=95.04
第2施工段:
×(2.05×4+1.25×4)×0.4=79.2
(4)垫层混凝土量
第1施工段:
×0.1×[19.275+25.275×2+3.55+7.125×2]
=18.14
第2施工段:
×0.1×([(5×6-0.15+1.025+0.1)×3]
=19.24
三、柱工程量
(1)柱混凝土工程量
第1施工段:
×0.4×0.45×(4.5+1.2)+0.2×0.3×(4.5+0.2)
=18.75
第2施工段:
×0.4×0.45×(4.5+1.2)+0.25×0.3×(4.5+0.2)×2=16.1
第3、5施工段:
×0.4×0.45×4.2+0.2×0.3×4.2=13.86
×0.4×0.45×4.2+0.2×0.3×4.2=13.86
第4、6施工段:
×0.4×0.45×4.2+0.25×0.3×4.2×2=11.97
×0.4×0.45×4.2+0.25×0.3×4.2×2=11.97
第7施工段:
×0.4×0.45×4.0+0.2×0.3×4.0=13.2
第8施工段:
×0.4×0.45×4.0+0.25×0.3×4.0×2=11.4
(2)柱钢筋工程量
02118.75×130/1000=2.44t
02216.1×130/1000=2.1t
02313.86×130/1000=1.8t
02411.97×130/1000=1.56t
02513.86×130/1000=1.8t
02611.97×130/1000=1.56t
02713.2×130/1000=1.72t
02811.4×130/1000=1.48t
(3)柱模板工程量
第1施工段:
×(0.4+0.45)×2×(4.5+1.2)+(0.2+0.3)×2×(4.5+0.2)=179.12
第2施工段:
×(0.4+0.45)×2×(4.5+1.2)+(0.25+0.3)×2×2×(4.5+0.2)=155.69
第3、5施工段:
×(0.4+0.45)×2×4.2+(0.2+0.3)×2×4.2=132.72
×(0.4+0.45)×2×4.2+(0.2+0.3)×2×4.2=132.72
第4、6施工段:
×(0.4+0.45)×2×4.2+(0.25+0.3)×2×2×4.2=116.34
×(0.4+0.45)×2×4.2+(0.25+0.3)×2×2×4.2=116.34
第7施工段:
×(0.4+0.45)×2×4.2+(0.2+0.3)×2×4.0=132.52
第8施工段
×(0.4+0.45)×2×4.0+(0.25+0.3)×2×2×4.0=110.8
四、梁工程量
(1)梁混凝土工程量
第1施工段:
基础梁:
×0.3×0.5×(6-0.4)+0.3×0.5×(6-0.2-0.15)+2×0.3×0.5×(6-0.45)+0.3×0.5×(7.5-0.45)+0.3×0.5×(3.75-0.45)+0.3×0.6×(7.5-0.45)+6×0.3×0.4×(6-0.4)+0.3×0.4×(6-0.45)+7×0.3×0.4×(7.5-0.45)=21.85
首层梁:
×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.03
×0.4)×(0.25×0.5+0.2×0.18)]+[(6×6-6×0.4)×(0.25×0.32+0.18×0.45)]+[(4×6-4×0.4)×(0.25×0.5+0.2×0.18)]=12.86
第2施工段:
基础梁:
×0.3×0.5×(6-0.4)+2×0.3×0.5×(7.5-0.45)+2×0.3×0.6×(7.5-0.45)+6×0.3×0.4×(6-0.4)+6×0.3×0.4×(7.5-0.45)=16.86
首层梁:
×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.18
×0.4)×(0.25×0.5+0.2×0.18)]+[(5×6-5×0.4)×(0.25×0.32+0.18×0.45)]+[(5×6-5×0.4)×(0.25×0.5+0.2×0.18)]=13.53
第3、5施工段:
×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.03
×0.4)×(0.25×0.5+0.2×0.18)]+[(6×6-6×0.4)×(0.25×0.32+0.18×0.45)]+[(4×6-4×0.4)×(0.25×0.5+0.2×0.18)]=12.86
第4、6施工段:
×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×0.3×0.8+(6-0.3)×0.2×0.4=17.18
×0.4)×(0.25×0.5+0.2×0.18)]+[(5×6-5×0.4)×(0.25×0.32+0.18×0.45)]+[(5×6-5×0.4)×(0.25×0.5+0.2×0.18)]=13.53
第7施工段:
×0.45)+(7.5×2+6-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×0.3×0.7+[(24-4×0.4)×0.25×0.5]+[(6×6-6×0.4)×(0.25×0.5]+[(4×6-4×0.4)×0.25×0.5]=24.35
第8施工段:
×(7.5×2-2×0.45)×0.3×0.7+[(30-5×0.4)×0.25×0.5]+[(5×6-5×0.4)×0.25×0.5]+[(5×6-5×0.4)×0.25×0.5]=25.31
(2)梁钢筋工程量
1(21.85+12.86)×115/1000+17.03×150/1000=6.55t
×115/1000+17.18×150/1000=6.07t
×115/1000+17.03×150/1000=4.03t
×115/1000+17.18×150/1000=4.14t
×115/1000+17.03×150/1000=4.03t
×115/1000+17.18×150/1000=4.14t
×150/1000+9.8×115/1000=3.31t
×150/1000+10.50×115/1000=3.43t
(3)梁模板工程量
第1施工段:
×0.5×2×(6-0.4)+0.5×2×(6-0.2-0.15)+2×0.5×2×(6-0.45)+0.5×2×(7.5-0.45)+0.5×2×(3.75-0.45)+2×0.6×(7.5-0.45)+6×0.4×2×(6-0.4)+0.4×2×(6-0.45)+7×0.4×2×(7.5-0.45)=146.96
×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=136.90
×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(6×6-6×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(4×6-4×0.4)×(0.18+0.2+0.32+0.25+0.5)]=113.68
第2施工段:
×0.5×2×(6-0.4)+2×0.5×2×(7.5-0.45)+2×0.6×2×(7.5-0.45)+6×0.4×2×(6-0.4)+6×0.4×2×(7.5-0.45)=136.54
×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=160.93
×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(5×6-5×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(5×6-5×0.4)×(0.18+0.2+0.32+0.25+0.5)]=121.8
第3、5施工段:
×0.45)+(7.5×2+6-3×0.45-0.25)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=136.90
×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(6×6-6×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(4×6-4×0.4)×(0.18+0.2+0.32+0.25+0.5)]=113.68
第4、6施工段:
×(7.5×2-2×0.45)+2×(7.5×2-2×0.45-2×0.2)+(7.5×2-2×0.45)]×(0.3+0.8×2)+(6-0.3)×(0.2+0.4×2)=160.93
×0.4)×(0.5+0.25+0.32+0.2+0.18)
]+[(5×6-5×0.4)×(0.18+0.1+0.32+0.25+0.32+0.1+0.18)]+[(5×6-5×0.4)×(0.18+0.2+0.32+0.25+0.5)]=121.8
第7施工段:
×0.45)+(7.5×2+6-3×0.45)+(7.5×2+6-3×0.45)+(7.5×2-2×0.45)]×(0.3+2×0.7)+[(24-4×0.4)×(0.25+2×0.5)]+[(6×6-6×0.4)×(0.25+2×0.5)]+[(4×6-4×0.4)×(0.25+2×0.5)]=218.51
第8施工段:
×(7.5×2-2×0.45)×(0.3+2×0.7)+[(30-5×0.4)×(0.25+2×0.5)]+[(5×6-5×0.4)×(0.25+2×0.5)]+[(5×6-5×0.4)×(0.25+2×0.5)]=224.85
五、楼梯工程量
(1)楼梯混凝土工程量
×2×(6-0.3)×(3.75-0.325)×0.2
=23.43
(2)楼梯钢筋工程量
×55/1000=1.29t
(3)楼梯模板工程量
×2×(6-0.3)×(3.75-0.325)=117.14
六、预制板工程量
(1)预制板混凝土工程量
×72×0.34=97.92
×90×0.455=163.8
第1施工段:
YKB6062:
32
YKB6092:
44
第2施工段:
YKB6062:
40
YKB6092:
46
(2)预制板钢筋工程量
×72×17.18/1000=4.95t
×90×24.23/1000=8.73t
七、工程量清单表
表一:
土方工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
第1施工段挖方
亚粘土
1.65m
512.74
2
第2施工段挖方
亚粘土
1.65m
538
3
第1施工段基础回填
亚粘土、原土及郊区运来
459.38
4
第2施工段基础回填
亚粘土、原土及郊区运来
493.54
5
第1施工段房心回填
亚粘土、原土及郊区运来
167.4
6
第2施工段房心回填
亚粘土、原土及郊区运来
184
表二:
基础工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
第1施工段基础混凝土
基础高0.8m
阶梯形
41.51
3
2
第2施工段基础混凝土
基础高0.8m
阶梯形
34.59
2.5
3
第1施工段基础钢筋
螺纹钢
t
1.5
0.5
4
第2施工段基础钢筋
螺纹钢
t
1.25
0.5
5
第1施工段基础模板
基础高0.8m
阶梯形
95.04
装10.5
拆4
6
第2施工段基础模板
基础高0.8m
阶梯形
79.2
装9
拆3.5
7
第一施工段基础垫层
C15
厚10
18.14
1.5
8
第二施工段基础垫层
C15
厚10
19.24
1.5
表三:
柱工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
第1施工段柱砼
矩形柱
普通砼
18.75
3.5
2
第2施工段柱砼
矩形柱
普通砼
16.1
3
3
第3施工段柱砼
矩形柱
普通砼
13.86
2.5
4
第4施工段柱砼
矩形柱
普通砼
11.97
2
5
第5施工段柱砼
矩形柱
普通砼
13.86
2.5
6
第6施工段柱砼
矩形柱
普通砼
11.97
2
7
第7施工段柱砼
矩形柱
普通砼
13.2
2.5
8
第8施工段柱砼
矩形柱
普通砼
11.4
2
9
021
第1施工段柱钢筋
螺纹钢
t
2.44
1
10
022
第2施工段柱钢筋
螺纹钢
t
2.1
1
11
023
第3施工段柱钢筋
螺纹钢
t
1.8
0.5
12
024
第4施工段柱钢筋
螺纹钢
t
1.56
0.5
13
025
第5施工段柱钢筋
螺纹钢
t
1.8
0.5
14
026
第6施工段柱钢筋
螺纹钢
t
1.56
0.5
15
027
第7施工段柱钢筋
螺纹钢
t
1.72
0.5
16
028
第8施工段柱钢筋
螺纹钢
t
1.48
0.5
17
第1施工段矩形柱
400×450、
250×300
179.12
装29
拆8.5
18
第2施工段矩形柱
400×450、
250×300
155.69
装25.5
拆7
19
第3施工段矩形柱
400×450、
250×300
132.72
装21.5
拆6
20
第4施工段矩形柱
400×450、
250×300
116.34
装19
拆5.5
21
第5施工段矩形柱
400×450、
250×300
132.72
装21.5
拆6
22
第6施工段矩形柱
400×450、
250×300
116.34
装19
拆5.5
23
第7施工段矩形柱
400×450、
250×300
132.52
装21.5
拆6
24
第8施工段矩形柱
400×450、
250×300
110.8
装18
拆5
表四:
梁工程量清单
序号
项目编号
项目名称
项目特征
计量单位
工程量
人工/天
1
第1施工段基础梁砼
普通砼
21.85
4.5
2
第1施工段矩形梁砼
普通砼
17.03
3
第1施工段异形梁砼
普通砼
12.86
4
第2施工段基础梁砼
普通砼
16.86
4.6
5
第2施工段矩形梁砼
普通砼
17.18
6
第2施工段异形梁砼
普通砼
13.53
7
第3施工段矩形梁砼
普通砼
17.03
3
8
第3施工段异形梁砼
普通砼
12.86
9
第4施工段矩形梁砼
普通砼
17.18
3
10
第4施工段异形梁砼
普通砼
13.53
11
第5施工段矩形梁砼
普通砼
17.03
3
12
第5施工段异形梁砼
普通砼
12.86
13
第6施工段矩形梁砼
普通砼
17.18
3
14
第6施工段异形梁砼
普通砼
13.53
15
第7施工段矩形梁砼
普通砼
24.35
2.5
16
第8施工段矩形梁砼
普通砼
25.31
2.5
17
1
第1施工段钢筋量
螺纹钢
t
6.55
3
18
2
第2施工段钢筋量
螺纹钢
t
6.07
2.5
19
3
第3施工段