target cost contracts 2.docx
《target cost contracts 2.docx》由会员分享,可在线阅读,更多相关《target cost contracts 2.docx(10页珍藏版)》请在冰豆网上搜索。
![target cost contracts 2.docx](https://file1.bdocx.com/fileroot1/2023-1/31/36288659-80b5-4c4b-92fe-a300f9d5876f/36288659-80b5-4c4b-92fe-a300f9d5876f1.gif)
targetcostcontracts2
CONTINUINGPROFESSIONALDEVELOPMENT
MaximumPeriod3Hours
TARGETCOSTCONTRACTS
By
RogerKnowles
CONTENTS
NewApproach
StandardTargetCostContracts
ReferencetoTargetCostintheContract
WhenShouldtheTargetBeFixed
CalculatingtheTargetCost
AdjustingtheTargetCost
Fee
GainShare/PainShare
TARGETCOSTCONTRACTS
NewApproach
Traditionallycontractsforconstructionworkhavebeenplacedonthebasisofalumpsumbeingpaidtothecontractorforcarryingoutthework.Thissumwillusuallybeadjustedforemployerchangesandallemployersriskitemsprovidedforinthecontractforsuchmattersasdesignerrors.Thecultureisfortheworktobeundertakenbythecontractorwhosubmitsthelowestprice.Inrecenttimesthismethodofprocurementhasfallenintodisreputeinrespectofpublicsectorworkwherebestvaluehasbeenthepreferredprocurementroutewithlowestpricefallingbythewayside.
Itisnowcommonplaceinthepublicsectorwherebestvalueappliesforprocurementsystemstoprovideforpaymenttothecontractorbaseduponitsrecordedcosts.Toensurethatcostsarenotallowedtogetoutofhandatargetforthesecostsisfixedattheoutset.Thetargetisadjustedtotakeaccountofanyemployerchangesandotherpricerisksallocatedtotheemployerunderthetermsofthecontract.Toensurethatthereareincentivesinplacesothatcostsarekepttoaminimumitisusualforthetargetcosttobelinkedtoagainshare/painsharemechanismwhichisfixedattheoutset.Therecordedcostsarecomparedwiththetargetcostandanysavingsharedbetweenthecontractorandemployerinapre-agreedmanner.Inlikemanneranyoverexpenditurecomparedwiththetargetisshared.
StandardTargetCostContracts
Thefollowingcontractsarestandardtargetcostcontracts:
1.PublicSectorPartneringContracts
∙Option2–TermMaintenance
∙Option5-AuthorityDesign
∙Option6-ContractorDesign
2.ICEConditionsofContractTargetCostVersion
3.PPC2000StandardFormforProjectPartnering
ThiscontractprovidesforaPriceFrameworkwhichleavesthepartiestodevisetheirownpaymentmechanism.Itiscommonplaceforacostreimbursablewithtargetcosttobeused.ThereisprovisionforincludinganAgreedMaximumPriceintheFormofCommencementAgreement.
4.NewEngineeringContract
∙OptionC-TargetContractWithActivitySchedule
∙OptionD-TargetContractWithBillofQuantitiescontract
Subcontracts
5.1PublicSectorPartneringContract
∙Option8–SubcontractTargetCostWithCostReimbursable
5.2SPC2000StandardFormofSpecialistContractforUsewithPPC2000
ReferencetoTargetCostintheContract
1.PublicSectorPartneringContract
Option2TermMaintenanceprovidesinclause23.1forthecalculationoftheTargetCostbymeasuringandvaluingtheworkinaccordancewiththeScheduleofRatesreferredtointheAppendix.
Options5AuthorityDesignandOption6ContractorDesign;inclause18.0itstatesthattheTargetCostisindicatedintheArticlesofAgreement.ThereisnomethodprovidedastohowtheTargetistobecalculated.
Option6Subcontract:
Inclause21.0itstipulatesthattheTargetCostisstatedintheArticlesofAgreement.ThereisnoindicationastohowtheTargetistobecalculated.
2.ICETargetCostVersion
TheTargetCostandtheFeearegivenintheAppendixPart2totheFormofTender.
3.ECCContract
TheTargetCostisreferredtoasthetotalofPriceswhichareincludedintheDatasubmittedbytheContractorwithhistender.
4.PPC2000
PartneringDocumentsreferredtointhecontractincludeaPriceFramework.TheGuidestatesinsection5.4thatatthedateoftheProjectPartneringAgreementthePriceFrameworkshouldincludetheagreedamountpayablefortheConstructor’sservices,agreedprofit,centralofficeoverheadsandsiteoverheads.Thisdocumentwhenagreedwillprovideamechanismwhichwillenablethesesumstobecalculated.ItisusualfortheConstructor’scoststoformthebasisforthesumstobepaid.InthedefinitionsectionreferenceismadetoanAgreedMaximumPricewhichisthepricepayabletotheConstructorpursuanttothePriceFramework.ThereisnospecificguidanceastohowitisintendedtooperateandhowtheAgreedMaximumPriceistobecalculated.Thiswillbeamatterforthepartiestoagreebeforethecontractisenteredinto.ItiscommonplacehoweverforthepartiestoagreeaTargetPricetobeincludedinthePriceFrameworkastheAgreedMaximumPrice.
TheAgreedMaximumPriceisstatedintheCommencementAgreement.
5.SPC2000StandardFormofSpecialistContractforUsewithPPC2000
PaymentwillbeinaccordancewiththeSpecialistPaymentTermstobeagreedbytheparties.ThepartiesmayagreethataTargetCostwillformthebasisoftheSpecialistPaymentTerms
WhenShouldtheTargetBeFixed
Thereisnohardandfastruleastowhenthetargetshouldbefixed.Thefollowingprovideexamples:
1.Someclientsopttointroduceanelementofcompetitionintotheprocess.ItisthereforecommonforcontractorstoberequestedtoindicatetheTargetCostaspartofthetendersubmission.Thisisregardedbymanyasbeingcontrarytothespiritofpartneringasitcanleadtoalowestpriceselectionpolicy.
2.AvariationonthismethodisforthecontractortoberequestedtosubmitwiththetendertheamounttobeincludedintheTargetCostforoverheadsandprofit.
3.OnmostpartneringcontractsitiscustomaryfortheTargetPricetobefixedaftertendershavebeenreceivedbutbeforethecontractissigned.SomecontractssuchasthePPC2000includeaprovisionfortheTargetCostreferredtoastheAgreedMaximumPricetobeincludedinthePrePossessionAgreement.
4.Onmostcontractsitisusualforavalueengineeringprocesstobeundertaken.Itcantaketheformofafairlymajorexerciseduringtheearlydesignstageandbeongoingduringtheremainderofthedesignandconstructionphase.IftheTargetCostisfixedbeforethefirstmajorvalueengineeringexercisehasbeenundertakenitislesschallengingforthecontractortoachieveacostfortheprojectwithintheTargetCost.ThereasonbeingthatduringthefirstmajorvalueengineeringphaseasignificantamountofcostmaybetakenoutwhichwouldbenefitthecontractoriftheTargetCosthasalreadybeenfixed.
CalculatingtheTargetCost
ThereareseveralmethodsofcalculatingtheTargetCostandincludethefollowing:
1.Measuredquantitiesmultipliedbyunitrates
2.Costperunitegbedspace
3.Employinganelementalcostanalysistechnique
4.Floorareamultipliedbycostpersquaremetre
Oftenabuildingblockapproachisemployedcomprising:
1.Unitcost
2.Sumincludedforrisk
3.Overheads
4.Profit
UnitCosts
Theunitcostsmaybecalculatedusingascheduleofratesforworkwhichisinclusiveoflabour,materialsandplant.Measuredquantitiesfortheworkarethenappliedtotheratestoarriveattheunitcosts.Wherethetargetisfixedatastagewhenlittledesignworkhasbeenundertakenamorebasicapproachisoftenusedbyemployingthefloorareaofthebuildingandapplyingaratepersquaremetreforthelabour,plantandmaterials.Itissometimesconvenienttocalculatetheareasofthevariouselementssuchascladdingandroofsofthebuildingandapplyaseparateratepersquaremetreforeachelementinrespectofthecostoflabour,plantandmaterialstoprovideatotalcostforeachelement.Thesecostsshouldalwaysbeinclusiveofwhatareoftenreferredtoassitepreliminariessuchasthecostofsiteaccommodation.
Wherealargepartoftheworkistobedesignedandconstructedbysubcontractorstheunitcostsareoftenbuiltupusingquotationsreceivedfromthesubcontractorswhowillbeundertakingthework.
RiskAllowance
Thecontractshouldbeveryclearastohowtherisksaretobesharedbetweentheparties.Thisisoftenachievedbyusingariskregister.Inbuildingupthetargetpriceasumshouldbeincludedinrespectoftheriskswhicharetobebornebythecontractor.Forexampleitisusualintimesofrelativelylowinflationforthetargetpricetoincludeforinflation.Onmanycontractsthecontractorisrequiredtoincludeinthetargetpricetheestimatedcostofanygroundconditionswhichmaybeencounteredwhethertheyareforeseeableorotherwise.Afinancialprovisionshouldbeincludedinthetargetpriceforthistypeofrisk.Wheretheextenttowhichgroundconditionsareanticipatedtobeunfavourableisunknownbeforeworkcommencesitisbetterforaprovisionalsumtobeincludedinthetargetpricewhichcanbeadjustedatalaterdatetotakeaccountofthecontractor’sactualcosts.Itshouldhoweveralwaysbemadeclearattheoutsetastowhichofthepartiesbearstherisk.
HeadOfficeOverheads
Theheadofficeoverheadsareusuallyprovidedforseparatelyinthebuild-upofthetargetprice.Itneedstobemadeclearattheoutsetwhichcostsareincludedunderthisheadingandwhicharesitecosts.Forexamplequantitysurveyorsmaybesitebasedandincludedintheunitcostswhereasthecommercialdirectorandchiefquantitysurveyormaybeheadofficebasedandformpartoftheheadofficeoverheads.Itisusualfortheheadofficeoverheadelementtobecalculatedbytheadditionofapercenttothetotaloftheunitcosts
Profit
Theprofitistherewardpaidtothecontractorforsatisfactorilycompletingthework.Itisusuallycalculatedbyaddingapercentagetothetotaloftheunitcosts,riskandoverheads.NormallyprofitisthemajorelementoftheFee.
AdjustingtheTargetCost
ThecontractwillusuallyprovidedetailsastohowtheTargetCostistobea