  ContractforExportingMiningEquipment

 

ContractNo.____

 

 

ThisContractismadeandenteredintoonthe15th,Oct.inSulaiminiyhbyandbetweenMassIraqCementCo,Ltd(astheBuyer)andChinaJiangsuGrandEconomicDevolpmentCo.,Ltd.acompanyincorporatedunderthelawsofChina(hereinafterreferredtoastheseller).

 

Whereas,theBuyerdesirestoengagetheSellertoprovidetheMiningEquipment,allrelateddesign,technicaldocument,technicalserviceandtechnicaltrainingandtoobtainfromtheSelleralicenseofknow-howandothertechnicalinformationinrelationwiththeEquipment’sdesign,erection,commissioning,operationandmaintenance.Nowitisherebymutuallyagreedasfollows:

 

Article1Definitions

 

1.1“Acceptance”meanstheBuyeracceptedtheEquipmentinaccordancewithArticlexx.

 

1.2“Commissioning”meanstheoperationoftheEquipmentinaccordancewithArticle9.4forthepurposeofcarryingoutPerformanceTest.

 

1.3“Contract”meansthisContractsignedbyandbetweentheBuyerandtheSeller,includingAppendicesattachedwhichshallformanintegralpartofthisContract.

 

1.4“EffectiveDateoftheContract”meansthedatewhentheContractentersintoforceuponfulfillmentofalltheconditionsstatedinArticle16.1.

 

1.5“Equipment”meanstheequipment,machinery,instruments,sparepartsandmaterialssuppliedbytheSelleraslistedinAppendix3.

 

1.6“Erection”meanstheinstallationoftheEquipmentincludingplacingandconnectingpartstotheirpositionsaccordingtothedesigndrawing.

 

1.7“JobSite”meansthesitewheretheEquipmentshallbelocatedand/orerected,namelyMassIraqCementPlant.

 

1.8“LastShipment”meanstheshipmentwithwhichtheaccumulatedinvoicevalueofshippedgoodshasreached100percentofthetotaltheEquipmentprice.

 

1.9“PerformanceTest”meansthetestsforexaminingwhethertheEquipmentisabletomeetguaranteefigures.

 

1.10“TechnicalDocument”meansthetechnicalindices,specifications,drawings,manualandinstructionsrelatedtothedesign,erection,test-run,commissioning,acceptance,operationandmaintenanceoftheEquipmenttobeprovidedbytheSeller.

 

1.11“TechnicalService”meansthetechnicalinstruction,assistanceandguidancerenderedbytheSeller.

 

1.12“TechnicalTraining”meansthetrainingrenderedbytheSeller.

 

1.13“TestRun”meanstheinitialrunofasinglemachineorthewholesystemoftheEquipmentwithoutmaterials.

 

1.14“WarrantyPeriod”meanstheperiodofthewarrantygivenbytheSellerasspecifiedinArticle10.2,duringwhichtheSellerisresponsibleforthedefectsoftheEquipmentasperArticle10.

 

 

Article2ScopeoftheContract

 

2.1TheSeller’sObligation

2.1.1TheSellershallsupplytheEquipmentandspareparts,providethedesign,TechnicalDocument,andconducttheTechnicalServiceandTechnicalTraining,andgrantanon-exclusiveandnon-transferablerighttousetheknow-howandothertechnicalinformationrelatedtotheEquipment’sdesign,Erection,Commission,operationandmaintenance.

 

2.1.2TheSellershallprocureandsupplytheEquipmentandsparepartswhichislistedinAppendix,thespecificationisdetailedinAppendix.

 

2.1.3TheSellershallprovidedesigninrespecttotheEquipmentandsubmittotheBuyertheTechnicalDocument.

 

2.1.4TheSellershallconducttheTechnicalServicesattheJobSite.

 

2.1.5TheSellershallconducttheTechnicalTrainingoftheBuyer’straineesasperAppendix.

 

2.1.6TheSelleragreestograntnon-exclusiveandnon-transferablerighttousetheknow-how,othertechnicalinformationrelatedtotheEquipment’sdesign,Erection,Commission,operationandmaintenancefreeofcharge,whichtheSellerprovidesanddisclosestotheBuyerduringtheimplementationoftheContractperiod.

 

2.2TheBuyer’sObligation

 

2.2.1TheBuyershallathisowncostsandexpenses,providetheSellerwithallinformationanddataconcerningthedesignasperAppendix.TheBuyershallensurethecorrectnessandexactitudeofallsuchinformationanddata.

 

2.2.2TheBuyershallathisowncostsandexpenses,obtainallnecessaryimportpermits,undertakecustomsclearance,takedeliveryoftheEquipmenttobesuppliedbytheSellerandtransportthemfromporttotheJobSiteintime.

 

2.2.3TheBuyershallathisowncostsandexpenses,performallthecivilworks,construction,Erection,TestRunandCommissioninginaccordancewiththeTechnicalDocumentandundertheTechnicalServicesrenderedbytheSeller.

2.2.4TheBuyershallathisowncostsandexpenses,performnecessaryadministrationandsecurityguardattheJobSite.

 

 

Article3Price

 

3.1TheBuyeragreestopaythetotalContractpricetotheseller,TechnicalTrainingandServicefeeisfree.

 

3.2ThetotalContractprice,includingpriceoftheEquipment,designandTechnicalDocument,shallbe____.

Thebreakdownisasfollows:

ThepriceforEquipmentis____.

Feefordesignis____.

FeeforTechnicalDocumentis____.

 

3.2.1ThetotalContractpricefortheEquipmentisfordeliveryCIFShanghai.CIFtermisinaccordancewithINTERNATIONALRULESOFTHEINTERPRETATIONOFTRADETERMS(INCOTERMS),2000edition,issuedbytheINTERNATIONALCHAMBEROFCOMMERCE(ICC).

 

3.2.2ThetotalContractpriceincludesthepriceforsparepartslistedinAppendix.However,thetotalContractpricealsocoverthesupplyofanyothersparepartsusedintheMiningconstruction.AttheBuyer’srequest,theSellermayprovidewithanyotherspareparts.Aseparateagreementwillbesignedbetweentwoparties.

3.2.3Theabovepriceisfixedandfirm.

 

3.3ThetotalContractpricecovertheTechnicalServicefeeandTechnicalTrainingfee.

 

Article4Payment

 

4.1DownPayment

AftersigningtheContract,theBuyershallpay30%percentoftheeachequipmentContractpricebyT/TtotheSellerwhenthesellerisfinishedtheindentwiththefactorandinformtheBuyer.

 

4.2

ThebalanceofthetotalContractpriceamounting___(says___only)shallpaidbyaconfirmedirrevocableLetterofCreditatsight,issuedwithin20daysaftersigningtheContractbyareputablebankandacceptabletotheSeller’sBankinfavoroftheSeller.TheLetterofCreditshallbeavailableuponthepresentationofthefollowingdocuments:

 

4.2.1For70percentofthetotalContractpriceamounting____(say___only)atdelivery:

(a)BillofLadinginoneoriginal.

(b)CommercialInvoiceinthreeoriginals

(c)Packinglistinoneoriginal(s)andtwocopies

(d)CertificateofOrigininoneoriginal(s)andtwocopies

(e)InsurancePolicyinoneoriginal(s)andtwocopies

 

4.3AllthebankingchargesincurredintheSeller’sbankshallbebornbytheSellerwhilethoseincurredoutsidetheSeller’sbankshallbebornbytheBuyer.

 

Article5Delivery

 

5.1TheDeliveryoftheEquipment

 

5.1.1ThedeliveryoftheEquipmentlistedinAppendixshallbecompletedwithin____()monthsfromtheEffectiveDateofContract.

 

5.1.2Within____()monthsaftertheEffectiveDateoftheContract,theSellershallsendtotheBuyerapreliminarydeliveryschedulebyEmail..

Notlaterthan____()daysbeforethefirstshipment,theSellershallsubmittotheBuyerthefinaldeliveryscheduleinthree(3)copiesindicatingContractnumber,dispatchnumber,nameoftheEquipment,quantity,approximatedimensions,volumeofeachpackageandtimeofeachshipment.

 

5.1.3TheloadingportisShanghaiChina,whiletheunloadingportis____.

 

5.1.4Advanceshipment,partialshipmentandtransshipmentareallowed,however,theSellershallinformtheBuyerthirty(30)daysbeforesuchshipment.

 

5.1.5ThedateofBillofLadingforeachshipmentshallbeconsideredastheactualdeliverydate.

ThedateoftheLastShipmentshallbeconsideredastheactualwholedeliverydateoftheEquipmenttobesuppliedbytheSeller.

 

5.1.6IftheEquipmentareshippedondeck,theSellershallberesponsiblefortheirproperpackingandtakespecialprotectivemeasures.

 

5.1.7TheSellershallnotifytheBuyerbyEmailbbbofthefollowingwithinfive(5)workingdaysaftereachshipmentiseffected:

(a)Contractnumber

(b)Nameofthevesselandloadingport

(c)NameoftheEquipmentshipped

(d)NumberanddateofBillofLading

(e)Totalvolume

(f)Totalgrossandnetweight

(g)Totalnumberofpackages/cases

 

5.1.8TheSellershallairmailthefollowingdocumentsinduplicatetotheBuyer:

(a)BillofLading

(b)CommercialInvoice

(c)PackingList

(d)CertificateofOrigin

(e)InsurancePolicy.

 

5.2TheLateDeliveryoftheEquipment

 

5.2.1IftheSellerfailstodelivertheEquipmentinaccordancewiththefinaldeliveryschedule,theSellershallpaytotheBuyerliquidateddamagesforsuchdelayatthefollowingrates:

(a)Fromthefirstweektothefourthweek,theliquidateddamagesshallbe   

____()percentofthevalueofthedelayedportionoftheEquipmentper

week

  (b)Fromthefifthweektotheeighthweek,theliquidateddamagesshallbe

____()percentofthevalueofthedelayedportionoftheEquipmentper

week

(c)Fromtheninthweek,theliquidateddamagesshallbe____()percentof

thevalueofthedelayedportionoftheEquipmentperweek

 

5.2.2Thefractionsoffourdaysormoreshallbecountedasoneweekandfractionsoflessthanfourdaysshallbeomitted.Thetotalaggregateamountoftheliquidateddamagesshallnotexceed____()percentofthevalueofthedelayedportionEquipment.

 

5.2.3ThepaymentofliquidateddamagesunderArticle5.2.1aboveshallbeincompletesatisfactionoftheSeller