PMP Preparation Overview Updated for PMBOK.docx

上传人:b****3 文档编号:27456602 上传时间:2023-07-01 格式:DOCX 页数:25 大小:22.14KB
下载 相关 举报
PMP Preparation Overview Updated for PMBOK.docx_第1页
第1页 / 共25页
PMP Preparation Overview Updated for PMBOK.docx_第2页
第2页 / 共25页
PMP Preparation Overview Updated for PMBOK.docx_第3页
第3页 / 共25页
PMP Preparation Overview Updated for PMBOK.docx_第4页
第4页 / 共25页
PMP Preparation Overview Updated for PMBOK.docx_第5页
第5页 / 共25页
点击查看更多>>
下载资源
资源描述

PMP Preparation Overview Updated for PMBOK.docx

《PMP Preparation Overview Updated for PMBOK.docx》由会员分享,可在线阅读,更多相关《PMP Preparation Overview Updated for PMBOK.docx(25页珍藏版)》请在冰豆网上搜索。

PMP Preparation Overview Updated for PMBOK.docx

PMPPreparationOverviewUpdatedforPMBOK

PMArea

AreaProcess

ImportantToolsandTechniques

MajorDeliverables(Outputs)

ProcessGroup

OtherNotes

ProjectIntegrationManagement–Processesrequiredtoensurethatthevariouselementsoftheprojectareproperlycoordinated

ProjectPlanDevelopment–takingtheresultsofotherplanningprocessesandputtingthemintoaconsistent,coherentdocument

♦ProjectPlanningMethodology

♦ProjectPlan

Planning

ProjectPlanshouldinclude:

ProjectCharter,ScopeStatement,WBS,Budget,Schedule,Risks,andothers.

ProjectPlanExecution–carryingouttheprojectplanbyperformingtheactivitiesincludedtherin

♦GeneralManagementSkills

♦WorkAuthorizationSystem

♦PMIS

♦WorkResults

♦ChangeRequests

Executing

PM’sroleistointegrateallpiecesofaprojectintoacohesivewhole.Itismanagement’s(e.g.seniormanagement)responsibilitytodefinetheprojectand“protect”itfromchanges.

OverallChangeControl–Coordinatingchangesacrosstheentireproject

♦ChangeControlSystem

♦PerformanceMeasurement

♦PMIS

♦ProjectPlanUpdates

♦CorrectiveAction

♦LessonsLearned

Controlling

PMmustbeconcernedwiththefollowingforoverallchangecontrol:

1.Influencingthefactorsthataffectchange.

2.Ensuringthatchangeisbeneficial.

3.Determiningthatachangehasoccurred.

4.Managingchangesastheyoccur.

ProjectScopeManagement–processesrequiredtoensurethattheprojectincludesalltheworkrequired,andonlytheworkrequired,tocompletetheprojectsuccessfully

Initiation–committingtheorganizationtobeginthenextphaseoftheproject

♦ProjectSelectionMethods

♦ExpertJudgment

♦ProjectCharter

♦Constraints

♦Assumptions

Initiating

ProjectManagershouldbeidentifiedinthisphase.PMIconsidersthisanoutput.

ScopePlanning–developingawrittenscopestatementasthebasisforfutureprojectdecisions

♦ProductAnalysis

♦Benefit/CostAnalysis

♦AlternativesIdentification

♦ExpertJudgment

♦ScopeStatement

Planning

ScopeStatementshouldinclude:

♦ProjectJustification

♦ProjectProduct

♦ProjectDeliverables

♦ProjectObjectives

ScopeDefinition–subdividingthemajorprojectdeliverablesintosmaller,moremanageablecomponents

♦WBSTemplates

♦Decomposition

♦WorkBreakdownStructure

Planning

WBSisusedasabasisformanyplanningactivitiesandisconsideredveryimportantbyPMI.

ScopeVerification–formalizingacceptanceoftheprojectsscope

♦Inspection

♦FormalAcceptance

Executing

ScopeVerificationdealswiththeacceptanceofthework,notthecorrectnessofthework.QualityControldealswiththecorrectnessofthework.

ScopeChangeControl–controllingchangestotheprojectscope

♦ScopeChangeControlSystem

♦PerformanceMeasurement

♦ScopeChanges

♦CorrectiveAction

♦LessonsLearned

Controlling

CorrectiveAction–Anythingdonetobringexpectedfutureprojectperformanceintolinewiththeprojectplan.

ProjectTimeManagement-Processesrequiredtoensuretimelycompletionoftheproject

ActivityDefinition–identifyingthespecificactivitiesthatmustbeperformedtoproducethevariousprojectdeliverables

♦Decomposition

♦ActivityList

Planning

Decompositionheregeneratesactivities(actionsteps)whereasdecompositioninScopeDefinitiongeneratesdeliverables.

ActivitySequencing–identifyinganddocumentinginteractivitydependencies

♦PrecedenceDiagrammingMethod(PDM)a.k.a.activity-on-node

♦ArrowDiagrammingMethod(ADM)a.k.a.activity-on-arrow

♦ConditionalDiagrammingTechniques(e.g.GERT)

♦ProjectNetworkDiagram

Planning

PDMhas4typesofdependencies(F-S,F-F,S-S,S-F).ADMonlyusesF-Sdependencies.

ADMusesdummies,PDMdoesn’t.

ActivityDurationEstimating–estimatingthenumberofworkperiodswhichwillbeneededtocompleteindividualactivities

♦ExpertJudgment

♦AnalogousEstimating(i.e.TopDownEstimating)

♦Simulation

♦ActivityDurationEstimates

Planning

PERTandCPMestimatingcanonlybedrawnonanAOAdiagram.

CriticalPathisthelongestpaththroughanetworkdiagramandshowsearliestcompletionofaproject.ItcanbederivedusingCPM,PERT,orMonteCarlo.

ScheduleDevelopment–analyzingactivitysequences,activitydurations,andresourcerequirementstocreatetheprojectschedule

♦MathematicalAnalysis

♦DurationCompression

♦Simulation

♦ProjectSchedule

♦ScheduleManagementPlan

Planning

CPMtechniqueprovidesonly1estimatepertask(i.e.themostlikely).

PERTtechniqueprovides3estimates(Optimistic(O),Pessimistic(P),andMostLikely(M)).

PERTFormulas:

♦(P+4M+O)/6

♦StandardDeviation–(P-O)/6

♦Variance–((P-O)/6)2

ScheduleControl–controllingchangestotheprojectschedule

♦ScheduleChangeControlSystem

♦PerformanceMeasurement

♦ScheduleUpdates

♦CorrectiveAction

♦LessonsLearned

Controlling

Revisionsareaspecialscheduleupdate,whicharechangestothestartandfinishdatesinapprovedschedule.Theyareusuallyrevisedonlyinresponsetoscopechanges.

ProjectCostManagement-processesrequiredtoensurethattheprojectiscompletedwithintheapprovedbudget

ResourcePlanning–determiningwhatresources(people,equipment,materials)andwhatquantitiesofeachshouldbesuedtoperformprojectactivities

♦ExpertJudgment

♦AlternativesIdentification

♦ResourceRequirements

Planning

CostEstimating–developinganapproximation(estimate)ofthecostsoftheresourcesneededtocompleteprojectactivities

♦AnalogousEstimating(i.e.top-downestimating)

♦ParametricModeling(e.g.regressionanalysisandlearningcurve)

♦Bottom-UpEstimating

♦CostEstimates

♦CostManagementPlan

Planning

Analogousestimatingisgenerallylesscostlyandlessaccuratethanothertechniques.

Bottom-upestimatingaccuracyisdrivenbysizeofworkitemsbeingestimated.Smalleritemsincreasebothcostandaccuracy.

Formulastoremember:

♦SV=BCWP-BCWS

♦CV=BCWP-ACWP

♦SPI=BCWP/BCWS

♦CPI=BCWP/ACWP

CostBudgeting–allocatingtheoverallcostestimatetoindividualworkitems

♦CostEstimatingToolsandTechniques

♦CostBaseline

Planning

Costbaselineisatime-phasedbudgettomeasureandmonitorcostperformance.

CostControl–controllingchangestotheprojectbudget

♦CostChangeControlSystem

♦PerformanceMeasurement

♦RevisedCostEstimates

♦BudgetUpdates

♦CorrectiveAction

♦EstimateatCompletion(EAC)

♦LessonsLearned

Controlling

Formulastoremember:

♦EAC=BAC/CPI

♦ETC=EAC-ACWP

♦VAC=BAC–EAC

ProjectQualityManagement–processesrequiredtoensurethattheprojectwillsatisfytheneedsforwhichitwasundertaken

QualityPlanning–identifyingwhichqualitystandardsarerelevanttotheprojectanddetermininghowtosatisfythem

♦Benefit/CostAnalysis

♦Benchmarking

♦Flowcharting

♦QualityManagementPlan

♦Checklists

♦OperationalDefinitions(i.e.Metrics)

Planning

Quality:

Thetotalityofcharacteristicsofanentitythatbearonitsabilitytosatisfystatedorimpliedneeds.

CustomerSatisfaction:

Conformancetorequirements,specifications,andfitnessforuse.

Qualityisplannedin,notinspectedin.

QualityAssurance–evaluatingoverallprojectperformanceonaregularbasistoprovideconfidencethattheprojectwillsatisfytherelevantqualitystandards

♦QualityPlanningToolsandTechniques

♦QualityAudits

♦QualityImprovement

Executing

Kaizen(ContinuousImprovement):

Smallimprovementsinproductsorprocessestoreducecostsandensureconsistencyofproductsorservices.

ISO9000:

Aninternationalstandardthatdescribesarecommendedqualitysystem.Doesnotincludequalityproceduresorforms.

Heuristicisaruleofthumb(e.g.RuleofSeven)

QualityControl–monitoringspecificprojectresultstodetermineiftheycomplywithrelevantqualitystandardsandidentifyingwaystoeliminatecausesofunsatisfactoryperformance

♦Inspection

♦ControlCharts

♦ParetoDiagrams

♦QualityImprovement

♦AcceptanceDecisions

♦Rework

Controlling

♦+/-1sigma=68.26%

♦+/-2sigma=95.46%

♦+/-3sigma=99.73%

♦+/-6sigma=99.99%

Variable:

Characteristictobemeasured(e.g.size,shape)

Attribute:

Themeasurement(e.g.inches,pounds)

StatisticalIndependence:

Theprobabilityof1eventoccurringdoesnotaffecttheprobabilityofanothereventoccurring.

ProjectHumanResourceManagement–processrequiredtomakethemosteffectiveuseofthepeopleinvolvedwiththeproject

OrganizationalPlanning–identifying,documenting,andassigningprojectroles,responsibilitiesandperformingrelationships

♦StakeholderAnalysis

♦HumanResourcePractices

♦OrganizationalTheory

♦Roleandresponsibilityassignments

♦StaffingMgmtPlan

♦OrganizationChart

Planning

PMFormsofPower:

♦Formal(legitimate)–BasedonPosition

♦Reward–GivingRewards

♦Penalty(coercive)–Penalizing

♦Expert–KnowledgeandExperience

♦Referent–Basedonreferencingsomeoneelse’spositionandpower.

PMIsaysbestformsofpowerareExpertandReward.Formal,Reward,andPenaltyarederivedfromPM’spositioninorganization.

StaffAcquisition–gettingthehumanresourcesneededassignedtoandworkingontheproject

♦Negotiations

♦Pre-assignment

♦Procurement

♦ProjectStaffAssigned

♦ProjectTeamDirectory

Planning

ConflictResolutionTechniques:

♦ProblemSolving(Confronting)

♦Compromising

♦Withdrawal

♦Smoothing

♦Forcing

PMIrecommendsProblemSolvingasbestchoicefollowedbycompromising.Forcingislast.

TeamDevelopment–developingindividualandgroupskillstoenhanceprojectperformance

♦TeamBuildingActivities

♦RewardandRecognitionSystems

♦Collocation

♦Training

♦Performa

展开阅读全文
相关资源
猜你喜欢
相关搜索

当前位置:首页 > 外语学习 > 韩语学习

copyright@ 2008-2022 冰豆网网站版权所有

经营许可证编号:鄂ICP备2022015515号-1