Planofmeasuresforenvironmentalprotection
undertheroadconstructionprojectofInternationalTransitCorridorWesternChina–WesternEurope
“Khorgos–Almaty–Shimkent-Uzbekistanrepublicboard”Motorwayreconstruction,km632-674
Contract:
SWRP-632-674-ICB(W)-002/2013
Contractor:
SinohydroCorporationKazakhstanBranch
Theplanofmeasuresforenvironmentalprotectionhasbeendevelopedtodetermineconsequencesoftheplannedeconomicandotheractivityforenvironment,includinghealthandsafetyofpeople,atmosphericair,watersources,floraandfauna,subsoil,soils,alandscape,cultural-historicalandnaturalmonumentsandothermaterialobjects,interrelationbetweenthesefactors,andalsoworkingoutrecommendationsonenvironmentimprovement,preventionofdestruction,degradation,damageofecologicalsystemsandnaturalresources.
Environmentalcomponents
Basicconstructionalandassociatedcomponentsandtheirlocation
Kindsofprospectiveinfluence
Contacttime
Environmentalmitigationmeasures
Workexecutionterms
Responsibleforworkexecution
Landresources
1.“Khorgos–Almaty–Shimkent-Uzbekistanrepublicboard”Motorwayreconstruction,km632-674
isnewly-built/rehabilitatedroad,doubledirectionswithfourlanes.
Thewholewidthofroadis27.5m,themaximumwidthoffilledslopeis12.25m,andtheminimumwidthis3.77m.Amongofall,sectionsПК634+427,ПК635+170,
ПК635+170,ПК637+427,
ПК638+580,ПК640+190,
ПК641+310,ПК644+130,
ПК646+810,ПК647+960,
ПК650+106,ПК651+580,
ПК653+170,ПК654+519,
ПК655+920,ПК660+330,
ПК661+370,ПК662+450,
ПК665+500,ПК668+215,
ПК670+175иПК648+486(П),
ПК648+484(Л),
ПК682+400(П),
ПК682+710(П).arediversionlanesandbusstations.
2.ConstructioncampwillbesetupatKm665+500,50mapartfromthenewroad,withthelengthof383m,thewidthof360m,andthegrossareaof10acres.ThelivingcampwillbebuiltatKm660+240,420mapartfromthenewroad,andthestorageareaforroadconstructionmachinerieswillbeplaced200mapartfromthelivingcamp,concretemixingplantandtankwillbesetup150mapartfromthelivingcamp.
Excludingthelandsfromagriculturalturnover
Permanent
Landfortemporaryusage
InaccordancewithPage31,43and44undertheLandLawofKazakhstan,thedocumentconcerningtherightforlongtermusageoflandmustbemade.
1.Priortothecommencementofworks,theContractorshouldsubmittotheEngineerwithplanofcarsontheproductionbasewiththelocationsofthefollowing:
asphaltconcretemixingplant,cementconcretemixingplant,ДСУ,stockpileareaforroadconstructionmachineries,stockpileareaforПСП,quarryforsoil,waterintakingareaandotherbuildings.
2.TheContractorshouldobtainallpermissiondocumentanddocumentfortheusageoflandaccordingtoPage32,36and43oftheTechnicalSpecificationundertheLandLawofKazakhstan.
Priortocommencementoftheroadconstruction
CommitteeofHighways
Ground(soilstratum)
Climateofthesubzonewheretheroadconstructionwilltakeplaceischaracterizedbyconsiderablearidityofair,andlittleamountofprecipitations..Soilsalongtheroadalignmentarepresentedbyserozemsandcommonloamyandmeadowserozemheavyloamy.Soilsarenotsalineandweaklyandaverageaggressiveornon-aggressivetoconcrete.Inthegeologicalstructureoftheroadalignmenthavebeenrevealedalluvial-proluvialdeposits,representedbyloamysand,loam,sandandpebble.Thevegetationlayerheightmakesup0,20-0,40m.Humuscontentis1,5-3,5%
Destruction,damageandcontaminationofthesoilstratumwithwasteproductsandproductionresidue.Contaminationofthesoilstratumwithheavymetalsnamelywastesof“PKJuzhpolimetal”arepossible.
Periodofperformanceofconstructionworks
1.AccordingtoP400,500oftheTechnicalStandard,clearanceoflandshouldbeconductedpriortoremovingthetopsoil,includingtoppletreesandplants,thenmoveawaythefellingmaterials.
2.Takingoffthesoilfertilelayer(SFL)withstratum0,36m,removalatthedistancenolessthan10mfromtheoperatingarea,warehousingandstorageinpiles,ontheleveledsurfaceofthetemporarilyoccupiedlands,fortheirfurtheruseatreclamation.Totakeoffthetopsoilinthawedconditionattheperiodofwarmanddryweather.
2.Strengtheningtheslopesofthesubgradeandexistingcavitiestopreventthesoilerosion.
3.Excludingunderfloodingoftheterritoriesadjoiningthehighway,soildegradationfrommotortransportimpact.
4.Excludingcasesofoilproductsandwasteoilsspillageinthesoil.Repairsofroadconstructionequipment,replacementofwastemotorandtransmissionoilsmustbeperformedonconstructiongrounds,inspeciallyallottedplaceshavingfirmcovering.Collectedwasteandreplacedoilsaresenttofurtherregeneration.
5.Roadconstructionmachinesmustbeparkonlyonspeciallyallottedplaces.
6.Allthedestructivelandsshouldberestoredbeforecompletionoftheworks.Performanceoftechnicalandbiologicalstagesofthedamagedlandsreclamation.
7.Clearanceoftheterritoriesofdustandrecyclingofwaste.Fortheworkingperiodcontainersforseparatecollectionofwastemustbeprovidedatthesite.
8.Toconcludecontractsofthewasteremoval.
9.ThequalityofsoilshouldbeinspectedaccordingtotheecologicalmonitoringschemeatthelaboratoryspecifiedintheContract.
10.TheContractshouldbesignedwitheligiblelaboratory,andthesoilqualitymonitoringshouldbeconductedbythelaboratoryaccordingtotheplan.
Inthecourseofconstructionworks
Atconstructionsites
SinohydroCorporationKazakhstanBranch
EnvironmentEngineer
LiuMingJian
TEL:
007-7713074437
Atmosphereair
Materialswillbetakenrespectibelyfromfourquarrieslocatingat
1000мcrossПК632+000,
7000мcrossПК645+200,
3000мcrossПК647+200,
1кмcrossПК663+100,
300мcrossПК669+100.ThelivingcampwillbeplacedatКм660+500,50mapartfromthenewroad,andtheproductioncampwillbesetupatКм660+500,50mapartfromthenewroad.Concretemixingplantandlaboratorywillbebuiltattheproductioncamp.
Topsoilclearedwillbestockpiledrespectibelyat20mapartfromthenewroad.
Materialsusedforthefillingofroadbed,subbaseandbasecoursewillbedepositedat50mapartfromthenewroad;
Warehouse,asthestoragelocationfortheothermaterials,willbesetupat100mapartfromthenewroad.
TherehabilitationoftheroadwillpassthroughtheMASHAGvillage.
Pollutantemissionsintheatmosphere:
СО,NO2,SO2,hydrocarbons,non-organicdust.
Noisenuisanceandvibration
Periodofperformanceofconstructionworks
1.ToreceivepermissionforenvironmentalemissionsofalltheworkingzonesinaccordancewithPage69undertheEcologyLawinKazakhstan.
2.AccordingtotheEcologyMonitoringPlan,environmentalqualityinspectionshouldbeconductedwiththespecifiedlaboratory,includingconfirmationofbasicdataforenvironment,noisyandvibration,andtechnicalnoteп106.
Toperformsystematicdedustingusingwaterwithconsumption1-2l/m.
3.Transportationofbulkmaterialmustbeperformedinavehiclecoveredbycanvashood.Besidesitisforbiddentoloadthematerialabovethelevelofthelateralandbackramp.
4.Unloadingofasphalt-concretemixesmustbedoneonlytoreceivinghoppersofasphaltspreaders.Unloadingofasphalt-concretemixesonthesoilisprohibited.Whenlayingasphalt-concretemixes,containingtoxichydrocarbons,it’snecessarytoprovideasteadyoperatingtempoofmachineryandtransportintheoperatingarea.
5.Tocarryoutmonitoringofpollutingemissionsintheatmosphereunderthecontractwithlocalqualifiedlaboratory
6.Installationofsignslimitingtrafficspeedandregulatingroadtraffic.Usageofhighqualityfuel.
7.Followingthescheduleofmotorvehiclesrepair.
8.Duringadversemeteorologicalconditionstheworksmustbeperformedinaccordancewiththeapprovedworkscheduleat
IMU.
9.Unloadingofdust-producingmaterialsisfulfilledinamechanizedway.
1.Controloftheroadconditionsfulfill«
Requirementstotheatmosphericairofthepopulatedareas»
Sanitaryregulationsandstandards
«
Maintenanceofmaximumpermissibleconcentration(MPC)intheairoftheoperatingarea№841asof03.2004г.»
2.WithintheareaofsettlementsEklendilocation,atthedistanceoflessthan200mfromtheoperatingareaworksshouldbeperformedonlyduringthedaytime(8-18o’clock).
3.Installationsplacementmustbedoneonlyinsound-absorbingareasorintents(compressor),andwithroad-constructionequipmentprotectivecasesandjacketsmustbeappliedwithmulti-layercoverings(rubber,foamrubberetc.)
4.Workingpersonnelisprovidedwithnoise-protectivemeans.
5.Speedrestrictionoffreighttransporttrafficinpopulationcenters.
6.Controlovertheoptimumoperatingmodeofconstructionmachinery.
7.Noisemanagement(shouldn’texceedthelevelofsanitarystandardsdB,establishedforpopulationcentersandoperatingareasbyMinistryofHealthKR,Order№139asof24.03.2005)
8.Areaswithsoundlevelexceeding85dbmustbemarkedwithsafetysigns.
Priortocommencementoftheroadconstruction