COMPARISONOFAWINDTURBINEFARM.docx
《COMPARISONOFAWINDTURBINEFARM.docx》由会员分享,可在线阅读,更多相关《COMPARISONOFAWINDTURBINEFARM.docx(22页珍藏版)》请在冰豆网上搜索。
COMPARISONOFAWINDTURBINEFARM
COMPARISONOFAWINDTURBINEFARM
INEASTERNMEDITERRANEANTURKEY
WITHTHEPROPOSEDAKKUYUNUCLEARPOWERPLANT
INTERMSOFEFFICIENCY,COSTSANDTOURISMIMPACTS
VeliKıvançTemel,SerhatYeşilyurt
Abstract
ThispapercomparesawindturbinefarminEasternMediterraneanRegionofTurkeywiththeproposedAkkuyuNuclearPowerPlantinthesameregion.Inthispaper,GE2.5MW-103windturbinewasexaminedintheaspectsofefficiency,power,costsandenvironmentalandsafetyimpacts.Thebestwaytoobtainthemaximumpowerfromawindfarmistobuildthewindfarmonahillormountainratherthanoffshoreorurbanareas,sincethemaximumwindspeedcanbeobtainedinthemountainsintheEasternMediterraneanRegion.AGE2.5MW-103windturbineonthemountainswillbeexpectedtoproducearound1.6MWpower,thoughcomparingwithanuclearpowerplant,theelectricitygeneratedfromawindturbineisrelativelylow.Awindfarmcapableofgeneratingthesameelectricitywithanuclearpowerplantshouldcontain9000windturbinesandcover23.5%oftheMediterraneanRegionofTurkey.Buildingawindfarmofthatsizewillrequire40billionEurosfor25yearsofoperationwhilethenuclearpowerplantwillrequirethesameamountfor60yearsofoperation.Oneofthebiggestconcernsofusingnuclearenergyisitsimpactsontourists,sincetourismisanimportantsourceofincomeforTurkey.Althoughmajordisastersseemtoaffecttourismandtheregionvastly,thereareonlyfewdisastersandchancesforanotheronetohappenareveryunlikelyifeverythingisdonecorrectly.Theminorincidentsontheotherhandhavenoknowneffectsontourism.
Keywords:
windenergy,nuclearenergy,efficiencyanalysis,impactsontourism
1.Introduction
Duetodevelopingcountriescontinuetheirgrowth,theirdemandforenergyconstantlyincreases.Turkey,aswell,canbeconsideredasdevelopingcountrywithforthcomingproblemsingeneratingelectricity.Ongoingindustrialization,increasingpopulationandinvestmentstocompetewithdevelopedcountriescausedTurkey’senergydemandtoburst.However,thisburstinenergydemandmaycauseTurkey’sdependencetoforeigncountriesforelectricitygenerationtoincreaseevenfurther.Asof2011,Turkey’smainelectricitysourceisnaturalgaspowerplantswith45.9percentshare[1].However,sinceTurkeylackstherequiredresourcesfornaturalgas,theenergyismostlydependentonforeigncountries.Therefore,Turkeyimmediatelyneedstodiversifyitsenergysourcesandincreaseitsfocusonotherenergysources.Currently,twoofthemostpopulardebatesaboutenergysourcesinTurkeyarerelatedtowindenergyandnuclearenergy.
GeneratingelectricityfromwindpowerisadevelopingconceptinTurkey.AsofJanuary2012,windturbinesinTurkeygenerateatotalof1792.7MW[2],andTurkeyplanstogenerateatleast20000MWfromwindturbinesby2023[3].Inthelastcoupleofyears,theresearchondeterminationofwindenergypotentialofseveralregionsinTurkeyincreasedvastly[4-6].However,evenifTurkeyuseditsallwindpotential,itisimpossibleforwindpowertocoverallofTurkey’senergydemandsinlongterm.Therefore,nuclearenergyisanotheroptionforTurkeyinordertodecreasetheimportedenergysources.OneoftheongoingprojectsistheAkkuyuNuclearPowerPlant,whichisintheMediterraneanRegionofTurkey.TheAkkuyuNuclearPowerPlantwillbeTurkey’sfirstandonlynuclearpowerplant,withacapacityofgenerating4800MW[7-8].Thenuclearpowerplantisplannedtostartitsfirstoperationin2019anditwillcovereightpercentofTurkey’senergydemandin2020[9].
ThemainobjectiveofthisstudyistocompareawindfarmintheMediterraneanRegionofTurkeywiththeproposedAkkuyuNuclearPowerPlant.Inthecourseoftheresearch,therequiredcapacityofawindfarmtosupplytheelectricityneedsofanindustrialareawillbecalculated.Additionally,thepaperwillexaminewhetherawindturbinefarmmightbeconsideredasanalternativetoproposedAkkuyuNuclearPowerPlant.Whilecomparingboth,thepaperwillalsocalculatethesizeofawindfarmtomatchthegeneratedelectricityofanuclearpowerplant,andlookatthetouristicimpactsofanuclearpowerplantontheregionthatitisbeingbuilt,sincetheareaoftheproposedAkkuyuNuclearPowerPlantisclosetolocationswithtouristicvalue.
2.FeasibilityoftheWindFarm
2.1.EfficiencyAnalysis
Energyofthewindcannotbeconvertedcompletelytomechanicalenergy,whichisexplainedbyBetz’Law[10].Duetothelossescausedbydriftcomponents,itisimpossibletoobtainthisamountofpower.Also,itisimpossibletostopthewindandconvertallofitsenergyintoanotherkindofenergy,sincewindwillcontinuetoflow.Thetheoreticalavailablepowertouseforenergyconversionis59.3%ofthemaximumpowerofthewind,whichisalsoknownastheBetz’Limit.Additionaltothedriftcomponentsofthewind,theefficiencyofawindturbinedecreasesduetotheeffectsofinternalcomponentsofthewindturbine.Awindturbinehasthreemainconstructedcomponents:
blades,nacelleandthetower.Bladesareconnectedtonacellethroughahubandnacellecontainsallthepowergenerationpartssuchasmainshaft,gearbox,diskbrake,generatorandcontrolsystems(Fig.1),whereallofthemcontributetothelossesinefficiency[10].
Fig.1.Theviewofinnercomponentsofthenacelleofawindturbine(AccionaAW-3000)[11].
ThewindturbinefarminBahçe,Osmaniye–acityinEasternMediterraneanTurkey,contains54GE2.5MW-100windturbines[12].Therefore,forefficiencyanalysis,GE2.5MW-103willbeusedsinceitispossibletohaveahubheightof100metersinGE2.5MW-103seriesanditissimilartothe2.5MW-100series.PowercurveofthewindturbineisshowninFigure2.2.
Figure2.PowercurveofGE2.5MW-103[13]
Thetheoreticalvalueofthepowerthatawindturbinecangeneratecanbefoundbyusing;
(1)
where
isthedensityofair,
istheareathatiscoveredbytherotor,
isthewindspeedand
istheBetzLimit.GE2.5MW-103hasarotordiameterof103meters,withcutinspeedat3m/sandcut-offspeedat25m/s.For10m/swindspeed,theoreticallyaturbinewith103meterrotordiametercangenerate5.12MWatmaximum.WhenBetzLimitisappliedtothisvalue,themaximumavailablepowerthattheturbinewillbeabletoconvertwillbeequalto3.04MW.However,accordingtothepowercurveofGE2.5-103(Figure2.2)whichisgivenintheproductbrochure,theratedoutputelectricalpowerat10m/sisaround2MW.ThisshowsthattheefficiencyagainsttheBetzLimitis65.9%,whereastheoverallefficiencyofthewindturbineat10m/sis39%(Table1).
Table1.EfficiencyandgeneratedpowervaluesofGE2.5-103fordifferentwindspeeds(left)
WindSpeed(m/s)
MaximumPower(MW)
AfterBetzLimit(MW)
MeasuredPower(MW)
EfficencyvsBetzLimit(%)
OverallEfficiency(%)
5
0,64
0,38
0,20
52,7
31,2
6
1,11
0,66
0,40
61,0
36,2
7
1,76
1,04
0,70
67,2
39,8
7,5
2,16
1,28
0,90
70,3
41,7
8
2,62
1,55
1,10
70,8
41,9
8,5
3,15
1,86
1,35
72,4
42,9
9
3,73
2,21
1,60
72,3
42,9
9,5
4,39
2,60
1,80
69,2
41,0
10
5,12
3,04
2,00
65,9
39,0
11
6,82
4,04
2,35
58,2
34,5
12
8,85
5,24
2,50
47,7
28,2
13
11,25
6,67
2,50
37,5
22,2
14
14,05
8,33
2,50
30,0
17,8
15
17,29
10,24
2,50
24,4
14,5
Figure3.Totalefficiencyvsthewindspeed(right)
2.2.Power
Powergeneratedfromawindturbineisdirectlyaffectedwiththreedifferentvariables:
theairdensity,theareathatwindgoesthroughandthespeedofthewind.Togetthemaximumpowerfromthewindturbines,thewindfarmshouldbeplantedtotheareawiththehighestaveragewindspeed,whichmightbeahill,amountainoroff-shore.AccordingtothewindmapofTurkey,awindturbineplantedoff-shoreinEasternMediterraneanRegionofTurkeywillhavebetween7.5and8m/swindspeedonaverage.Also,awindturbineplantedonamountainorahillintheEasternMediterraneanRegionofTurkeywillhavebetween8.5and10m/swindspeedonaverage.Usingthesevalues,wecancalculatethemaximumwindpowerdensityandtheavailablepower.Tocomputethetotalavailablepower,therotordiameterisrequiredsincethewindwillpassthroughtheareathatrotorcovers.
ThewindenergymapofTurkeyisshowninFig.4,inwhichEasternMediterraneanRegionofTurkeyiscoloredwithyellowindicatingthatthewindspeedathillsandmountainsismeasuredbetween8.5and10m/s.AdetailedwindspeedmapofMediterraneanRegionat100meterscanbeseeninFig.5.
Figure4.Turkeywindmap[15].
Figure5.MediterraneanRegionwindmap[16].
Usingthesevalues,itissimpletocalculatethetotalavailablepowerofthewindandtheestimatedgeneratedpower.
ThewindspeedonahillinEasternMediterraneanRegionwillbebetween7and9.5m/s.Assumingthatthewindspeedfortheregionwherewindfarmisinstalledis9m/s,theavailablepowerwillbe3.74MWandthegeneratedmaximumpowerfromthewindturbinewillbe1.60MW,duetothelossesstated.ThismeansthatasingleGE2.5MW-103windturbineonthehillswillbeexpectedtogenerate1.60MW.
AlthoughGE2.5MW-103onahillisideallyexpectedtoproduce1.60MW,thatisnottherealcase.Inreality,thecapacityfactorofthewindfarmshouldalsobeconsidered.Thecapacityfactorofapowerplantisdefinedastheratiobetweentherealgeneratedoutputpowerandthecalculatedoutputpowerofapowerplant.ThecapacityfactormapofTurkeyfor50metersheightwasmodeledbytheTurkishWindEnerg