Method statament of pipe culvert works.docx
《Method statament of pipe culvert works.docx》由会员分享,可在线阅读,更多相关《Method statament of pipe culvert works.docx(9页珍藏版)》请在冰豆网上搜索。
Methodstatamentofpipeculvertworks
MethodStatementof
PipeCulvertWorks
ENGINEER&CONTRACTORDOCUMENTATIONREVIEW:
□
STATUS1
Approvedassubmitted
□
STATUS2
ApprovedsubjecttoimplementationofEngineer’sand/orEmployer’scomments/notationwithoutre-submission
□
STATUS3
Rejectedandbeingsubjecttofullre-submissioninresponsetotheEngineer’sand/orEmployer’scomments/notation
NOTE:
ApprovedbytheEngineer’sand/orEmployershallnotrelievetheContractorofanydutyandresponsibilityundertheContract.
Name&Signature
Position
Date
PreparedBy:
ReviewedBy:
ApprovedBy:
Section
CONTENTS
Page
1.0
Purposeofmethodstatement
1
2.0
ScopeofWorks
1
3.0
Documentstobereferredinthismethodstatement
1
4.0
Responsibilitiesforactivitiesdescribedwithinmethodstatement
1
5.0
ResourcestobeusedfortheWorks
2
5.1Manpower
2
5.2Plant&Equipments
2
6.0
Detailedmethodofcarryingoutthismethodstatement
3
7.0
Inspectionplan
5
8.0
Health&SafetyConsiderations
5
8.1Generalsafetyissues
5
8.2EmergencyArrangement
5
9.0
EnvironmentalConsiderations
6
10.0
Recorddocumentationand/oroutput(s)whichconfirmcompletionofmethodstatement.
6
11.0
Training
6
12.0
Appendices
7
AppendixA
-
RiskAssessment
AppendixB
-
ToolBoxTalk
AppendixC
-
InspectionPlan
AppendixD
-
RICF
1.0Purposeofmethodstatement
Thismethodstatementismadeinordertocontrolthetechnologyandmanagementeffectively,andservesasaguidelineforthepipeculvertworksthatfromGerehuto9mileroad.
2.0ScopeofWorks
ThismethodstatementisapplicabletothepipeculvertprefabricationandinstallationofGerehuto9mileroadengineering.
Pipeculvertsshallbemadeintheprecastyardandtransportedtothesiteforinstallation.
3.0Documentstobereferencedwiththemethodstatement
1)MRS004
2)MRS51
3)AS1289
4)Specificationsforroadandbridgeworks—August1995
5)ProposedGerehuCasiocircleto9-mileroadgeotechnicalinvestigationreport
6)Contractspecification
7)Constructiondrawing
8)ProjectQualityPlan(PQP)
9)ProjectSafetyPlan(PSP)
10)ProjectEnvironmentalPlan(PEP)
11)InspectionPlan(IP)
4.0Responsibilitiesforactivitiesdescribedwithinmethodstatement
4.1TheresponsibilitiesoftheConstructionManager
TheConstructionManagerwillberesponsibleforthecoordinationworkin-betweentherelatedparties,machinerydeployment,andtoensuretheconstructionquality,safetyandenvironmentalstandardtoachievetherequirementsofthemethodstatementandthetechnicalspecifications.
4.2TheresponsibilitiesoftheSiteEngineer
TheSiteEngineer’sresponsibilityistomakedetailedtechnicalclarificationandgivetechnicalguidancetothepersonnelwhomareonthesiteoftheconstruction.
4.3TheresponsibilitiesoftheSurveyor
Intheprocessofinstallingthepipeculvert,theSurveyorshouldberesponsiblefortheculverts’centrelinelayout,andtocontroltheelevationofpipeculvert.
4.4TheresponsibilitiesoftheMaterialEngineer
TheMaterialEngineerwillberesponsibleforthecompliancetestonthebackfillingmaterialsandthedesignofconcreteforreinforcedconcretepipeculvert.
4.5TheresponsibilitiesoftheSupervisor
TheSupervisorwillberesponsibleforthepreparationworkonthesite,andcarryoutthemanagementworkaccordingtotheconstructionschedulesandplans.
5.0Resourcestobeusedfortheworks
5.1Materials/TechnicalInformation
NO.
MATERIALDESIGNATION
QUANTITY
1
Concrete
1057m3³
2
Steel
42t
3
Sandcushion
300m3³
5.2ManPower
NO.
POSITION
NATIONALITY
AMOUNT
1
Supervisor
China
1
2
Excavatoroperator
China
1
3
Dumptruckdriver
PNG
1
4
Rolleroperator
PNG
1
5
Craneoperator
China
1
6
Concretemixertruckdriver
PNG
1
7
Labour
PNG
5
5.3Plant&Equipments
NO.
MACHINERY
MODEL
FUNCTION
1
Excavator
EC300
1
3
Dumptruck
15t
1
4
Crane
25T
1
5
Concretemixertruck
8m2
1
6
Roller
XL180J
1
7
Flatvibrationrammer
HZD115
2
8
Thefrogvibrationrammer
HW40
2
6.0Detailedmethodofcarryingoutthismethodstatement
6.1Sequenceofworks
6.1.1Sequenceofprecastreinforcedconcretepipeculvert
6.1.2Sequenceofprecastreinforcedpipeculvertinstallation
6.2Detailedmethodofprecastconcretepipeculvert
6.2.1Thepreparationofprecast
Priortoprecast,theworkershallcleanuptheareathathasbeingusedtoprecasttheconcretepipeculvert.Watershallbeaddedasrequiredtoavoidmoistureloss.Andweneedfabricatethecolumncageswithφ6cold-rolledribbedmildsteelbarsasperthedesign.Forpipeculvertunderφ600mmorbetweenφ600mm-φ1000mm,columncagesshallbefabricatedwithsinglelayerofsteelbarmesh,anddoublelayersteelbarmeshshallbeengagedandwellfixedforpipeculvertoverφ1000mm.Beforethecageisputtedintheformwork,weshouldmakesurethattheformworkhasbeencleanedandtheformworkhasbeencoveredbyreleaseagent.Thenweputthespacerblockinthecage,andmakesurethatthesteelbarhasenoughthicknessprotectivelayers.
6.2.2Precastpipeculvert
Afterweputtedthecageintheformwork,usedgantrycranemadethemintheposition.Andthenaddharshconcretetothesteelformwork.Asthemachinerevolves,harshconcreteiscontinuouslyaddeduntilthewallsofthetubereachtherequiredthickness.Thewallsofthetubearetobefullycompactedbeforethespeedofthemachineisgraduallytransferredto1200revolutionsp/min.Themachineshallbeathighrevolutionfor5mins-7minsuntilthewallofthetubeisinacompactedstate.Oncethepipeculvertiscompleted,itwillbehungintoasteampool.
6.2.3Curing
Beforetheremovaloftheformwork,thepipeculvertshallbeinasteamcuringprocessforfourhours.
6.2.4Test
Finishedalltheprecastworksweneeddosometesttocheckthequalityoftheculvert,thesetestswillbecarriedoutaccordingwiththeAS/NZS4058:
2007orasdirectedbytheengineer.
6.3Detailedmethodofpipeculvertinstallation
6.3.1Settingout
Thesiteshallbesurveyedtosetthelimitsofexcavationandculvertcentrelineasperthedrawings.Thetemporarybenchmarkshallbesetuptocontroltheelevationofpipeculvert.
6.3.2Drainage
Afterthefieldinvestigation,partofculvertsshallbedrainedoffwatertoreducetheinfluenceofwaterflowingthroughtheconstructedpipeculvert.
6.3.3Excavation
Theexcavationofthefoundationforpipeculvertsshallbedoneaccordingtothelimitsofthesettingout.WhenMechanicalexcavationtothedesignelevationabove10~20cm,artificialexcavationshallbecarriedouttoavoidoverexcavation.Thewidthofthefoundationshallbejustsufficienttopermitsatisfactoryjointingofthepipeandtheminimumwidthofthetrenchtobeconstructedforapipeculvertshallnotbelessthantheexternalpipediameterplus600mm.Duringtheprocessofexcavation,thesurveyshalluselevelstocontroltheelevationofthepipeculvert.Ifconstructionislaunchedduringtherainyseason,oneormoresumpsshallbedugwithinthefoundationpit,usingwaterpumptodrainwateroutfromthescopeofthefoundationpit.
Digtodesignelevation,Basalbearingcapacityshallbecarriedout.Ifbasalbearingcapacitycannotmeetthedesigndemand,lessthan150kpa,quotesupervisionengineeranddisposeasdirectivebytheengineer.
6.3.4Basetrimming
75mmthickofsandshallbelaidatthebottomofthefoundationbeforethelayingoftheculvert.Andatrenchneedstobedugmanuallyinthefoundationbedtolayaculvert.Theconstructionofthetrenchshallbeconstructedaccordingtothelengthandwidthoftheculvert.
6.3.5Layingofpipeculvert
Thelayingofthepipesshallbeginattheoutletendofthebarrelwiththesocketendsupstreamandspigotendsdownstream.Theendsofeachlengthofpipeshallbecarefullybuttedtogethertoprovideacontinuouslystraightbarrel.
Wherethereismorethanonepipethatformstheculvert,thepipesshallbespacedasperthedrawings.
6.3.6Pipejointing
Whenjointing,thetrenchshallbedryandthejointsshallbecleanedandwettedbeforesealingwithmortar.ThemortarshallbekeptdampuntiltheEngineerapprovesbackfillingtoproceed.Internaljointsofpipesmorethanlmetreindiametershallnotbemortareduntilafterbackfillingiscomplete.Wherethereislessthan1meterofpipe,thejointshallbesealedwithmortarbeforebackfillingiscompleted.Allexcessmortarshallberemovedfrominsidethepipe.
6.3.7Headwallsandwingwalls
Theexcavationoftheheadwallsorwindwallsshallbesetoutasperthedrawing.Thefoundationshallbeexcavatedandormanuallydugfollowedbyconcreteplacement.Theconcreteplacementiscarriedoutuponthecompletionofexcavationtothebottomofthefoundationaccordingtothedesignelevation.
Theconcreteshallbedoneinlayeredcastingduetheheightoftheheadwallandwindwall.Iftheformworkisabove2m,scaffoldingshallbeinstalledonbothsidesofthefoundationtoensurethesafetyoftheconstruction.
6.3.8Backfilling
Thebackfillingofthebasetopandbothsidewallsoftheculverttrenchshallbebackfilledwithsand,withlayerslaidsymmetricallyaccordingtothedesignandspecificationrequirements.Eachlayershallnotexceed150mmwiththecompactiondegreeoftheembankmentontheplatformnotlessthan90%.Thebackfillingmaterialshallbethoroughlyrammedandtamped.
Thesub-gradetopshallbebackfill