土方工程施工方案05ExcavationEmbankment611
DEMOCRATICSOCIALISTREPUBLICOFSRILANKA
MINISTRYOFHIGHEREDUCATION&HIGHWAYS
EXTENSIONOFSOUTHERNESPRESSWAYPROJECT
SECTION-3
FROMWETIYATOANDARAWEWA
MethodStatementforExcavation&Embankment
CHINARAILWAYFIRSTSURVEY&
DESIGNINSTITUTEGROUPCO.,LTD.(FSDI)
CONSULTANT
CONTRACTOR
CHINASTATECONSTRUCTIONENGINEERING
CORPORATIONLTD.
SubmittalNumber.S3-CSC-EW-CS1-3005-02
ProjectCode
FromXXX
Section
No
Project
Phase
Type
ProfessionalType
DocumentTe
DocumentNo
Revision
#
E
S
E
P
━
C
S
C
━
S
3
━
W
D
━
T
E
C
━
E
W
━
C
S
1
━
3
0
0
5
0
2
02
2016.6.11
RenPeng
JiJianhui
CaiLei
Forconstruction施工
02
2016.4.27
RenPeng
JiJianhui
CaiLei
Thirdmodificationandsubmission第三修改和提交
01
2016.4.1
RenPeng
JiJianhui
CaiLei
Secondmodificationandsubmission第二修改和提交
00
2016.2.16
RenPeng
JiJianhui
CaiLei
FirstSubmission第一次提交
Revision#
Date
preparedby
Audited
QualityManager
Validation
ChiefEngineer
Description
RepliesaboutcommentsoftheMSforExcavation&Embankment(S3-CSC-EW-CS1-3005-01)
No
CommentsofConsultant
RepliesofContractor
1
Thetechnologyofstrippingtop-soilshouldbeexpatiatedaccordingtoclause651,TechnicalSpecificationoftheContract.
Clause651inspecificationisabout.furnishingandplacingtopsoil.Wehavementionedthemethodofstockpilinginchapter4.1.3.
2
Thelastsentenceofpageno05says“Itisenvisagedthatthesame8groupsusedforthoseexcavationactivitieswillbeusedfortheseworks”.Youhavenotmentionedregardingany08groupsthatareusedforexcavationactivity.Pleaseclarify.
Wehaverevisethesentence..
3
Youhavereferredanaddenduminthelastparaofpageno06.Wecouldnotfoundsuchaddenduminavailablerecordswithus.HoweverthecontentoflastparaisnotrelevantsinceyouareresponsibleforthedesignworkandPlanandProfiledrawingaremadeaccordingtoresultsofyouinvestigations.
Thisparagraphisnotrelevant,sowedeleteit.
关于开挖、路堤的MS评论回复(s3-csc-ew-cs1-3005-01)
No
Commentsof顾问
回复承包商
1
应根据第651条的规定,对剥顶土壤技术进行详细的阐述,并对合同的技术条件。
第651条在规范中是关于。
我们已经提到在第4.1.3堆存的方法。
2
页的最后一句没有05说:
“它是设想,相同的8组用于这些挖掘活动将用于这些作品”,你没有提到关于任何08组用于挖掘活动,请澄清。
我们已经修改了句子。
3
3你已经在最后一页的第06页提到了一个附录,我们找不到这样的附录可以用我们的记录。
然而,最后一段的内容是不相关的,因为你是负责设计工作,并计划和轮廓图是根据你的调查结果。
这一段是不相关的,所以我们删除它。
这段是不相关的,所以我们删除它
Section
CONTENTS
Page
1.0
IntroductionandGeneralInformation介绍和一般信息
1
2.0
Materials材料
1
3.0
Equipment设备
1
4.0
MethodandProcedure方法和程序
2-7
5.0
SafetyManagementandControl安全管理与控制
7-9
6.0
QualityControl质量控制
9
7.0
MeasurementControl测量控制
10
1.IntroductionandGeneralInformation介绍和一般信息
Thismethodstatementprovidesthedetailsofthematerials,theequipment,theprocedureandrelevantdocumentsrelatedtotheexcavationandembankmentactivities,includingthequalitycontrolandthesafetyprecautions.
1.1.LocationofWorks作品的位置
ThelocationoftheexcavationandembankmentworkswillbelimitedtoselectedareaswithintheRightofWay(ROW),asinstructedbytheEngineer.Alternatively,asrequired,theseworksmaybeapplicabletolocationsoutsidetheROW(ie.borrowpits,disposalareasetc.)
2.Materials材料
Themajormaterialsusedfortheexcavationandembankmentworksinclude,butarenotlimitedtothefollowing.
∙Suitablesoil
∙Granularmaterial
∙Weatheredrock
∙Hardrock
∙Unclassifiedorborrowmaterial
∙Water
3.Equipment设备
Themajorequipmentusedfortheexcavationandembankmentworksinclude,butarenotlimitedtothefollowing.
∙JCB
∙Backhoes
∙Dozers
∙DumpTrucks
∙MotorGrader
∙RockDrills
∙RockHammers
∙Rollers
∙Rammers/PlateCompactors
∙WaterBrowsers
∙Sampling&TestingEquipment
∙Otherminortools
4.MethodandProcedures方法和程序
Themethodandproceduresfortheexcavationandembankmentworksfollowthestepsbelow.TheFlowchartisalsoprovidedinAppendixA
Beforethecommencementoftheworkandafterthecompletionoftherelatedclearing&grubbingoperation,theEngineerwillbenotifiedoftheareastobeexcavated.Accordingly,theEngineerwillinspecttheareaforapprovalbeforecommencementoftheworks.
Soilclassificationwillbecarriedoutonsamplestakenalongtheroadconstructionarea.Theintervalofsamplingwillbedeterminedbythechangingnatureofthesoilencountered.Teststoclassifythesoiltypesencounteredwillinclude,oneormoreofthefollowing,asrequired(ie.CBR(DCP),PI,Gradation,OMC/MDDetc.)
4.1.ExcavationofTopsoilMaterials挖掘表层土材料
4.1.1AftergettingtheEngineer’sapproval,thetopsoil(toplayerin-situmaterialcontainingvegetation,rootsandseeds)willbestrippedoffbymeansofearthmovingequipmentinthedayshift.
DuringtheEngineer’sinspectionofthegeneralareaofwork,theEngineerwillconfirmthethicknessoftopsoiltoremoveandrecordhisinstructioninwritingatthefield.
4.1.2Thetopsoilmaterialsexcavatedwillbestockpiledwithinand/oroutsidethesiteinareasapprovedbytheEngineer.
4.1.3Afterthecompletionofstrippingandstockpilingoftopsoilwithinaparticulararea,arequestwillbemadetotheEngineertocarryoutaninspectiontoconsistofavisualinspectionfollowedbyajointsurvey.Iffollowingtheinitialvisualinspection,theEngineerdeterminesthatcertainareasrequirefurtherstripping,hewillissuehisfurtherinstructionsinwritingatthispointandCSCECwillcarryouttheadditionalworkaccordingly.Oncetheinitialvisualinspectionissatisfied,thesecondpartoftheinspectionwillbecompletedwithajointsurveyoftheareabeforecommencementofworkstofollow.
4.2.ExcavationofUnclassifiedMaterials公开的材料开挖
4.2.1EarthmaterialwhichwillbeclassifiedasunclassifiedsoilandconformingtospecificationrequirementswillbeexcavatedusingExcavators.
4.2.2Theexcavatedunclassifiedmaterialwillbetransporteddirectlytoareasforuseinformingembankmentsfortheroadways,connectingroads,rampsandapproaches;inconstructingsubgradeandshoulders;inbackfillingaroundstructuresorforanyotherpurposenecessaryforthecompletionoftheprojectinaccordancewiththedrawings.
4.2.3Inareaswherethesituationarises,excessmaterialwillbestockpiledtemporarilywithintheROWoralternativelyinselectedareasadjacenttothesite,approvedbytheEngineer.
4.2.4Excavationwillbeundertakendowntotheapprovedlinesandlevels.
4.2.5Ifthesubgradelevelisreachedwithintheunclassifiedmaterialstrata,thebottomlayerwillbecompactedtothedensityspecified.IfmaterialatthebottomisfoundtobesoftandweareunabletocompacttotherequireddensityandCBRvalues,thenwewillrequiretheinstructionoftheEngineertofurtherexcavatetoaspecifieddepthandreplacewithSelectedMaterial,orasotherwiseinstructed.Detailofsuchadditionalworkswillberecordedjointly.
Ifhardrockisreachedandexcavationneedstocontinueinthenewstrata,unclassifiedexcavationwillbehaltedinthoseareas.
4.2.6ArequestwillbemadetotheEngineertocarryoutajointsurveyoftheareawhereexcavationiscompleted,forthepurposeofmeasurements.
4.2.7Excavationworkincuttingareaswillbedoneseparatedinlayersandwidthtoensurethevehiclestraveling.Fortheshallowexcavationportion,bulldozersandloaderswillbeused,forthedeepexcavationportion,excavatorwillbeused..Soilexcavationandsoftrockcuttingexcavation,thereservedsoilatthebottomorslopeshouldbeatleast20cmforthesecondaryexcavation.Meanwhile,thecatchwatermustbebuildbeforeexcavation.
4.2.8Accordingtothedesignrequirements,theslopeofsoilcuttingareais1:
2andtheslopeofrockcuttingareais1:
0.5,whentheexcavationdepthismorethan7m,twolevelsofslopewillbeused.
4.3.HardRockExcavation硬岩开挖
Thischapterwillbedescribedinmethodstatementforrockblasting.
4.4.ExcavationofUnsuitableMaterials不合格材料的挖掘
4.4.1EarthmaterialwhichwillbeidentifiedbytheEngineerasunsuitableforembankmentwillbeexcavatedusingexcavators/dozers.
4.4.2SuchmaterialswillbetransporteddirectlytodisposalareasapprovedbytheEngineer,withoutdoublehandling.
Beforethedisposalofwastematerialsorselectedvegetation,arequestwillbemadetotheEngineerforapprovalofalocationfordisposalwhensuchalocationisintheROW.Alternatively,ifanareaoutsidethesiteisconsidered,thenecessarystepswillbetakentoobtainapprovalfromlandownersandoftheCEA.
Disposalofallwasteincludingwood,trash,debris,stumps,andotherforeignmatterwillberemovedtotheapprovedlocationswiththehelpofdumptrucks,JCB,tractorandmanpowerorother.
Eachlocationforthenecessaryapprovalsisshowedasfollow.
No
Name
Address
1
A.L.Peeter
No4562,WeniwalAra,Sooriyawewa
2
K.A.Leelawathi
Watawana,Bediganthota
3
NimalRuwanPatirana
No162,WatawanaRoad,Bediganthota
4
R.K.kusumawathi
Bediganthota,Sooriyawewa
Figure4.4-1Locationofdisposalarea处置区位置
4.4.3Thevolumeofexcavatedmaterialtobespoiledissubstantialinvolumeandproperdisposalareashavetobedeterminedoutsidethesite.
Ifanyborrowareasarerequired,unsuitablematerialwillbedisposedofintheresultantexcavations.Theunsuitablematerialwillbetransportedandstockpiledontheedgeofborrowareaforlaterbackfilling.Onceexcavationoftheborrowpitiscompleted,thestockpiledspoilmaterialwillbedozedtothepitandtopsoilwillbesp