盾构机组装调试拆机方案Word文档格式.docx
《盾构机组装调试拆机方案Word文档格式.docx》由会员分享,可在线阅读,更多相关《盾构机组装调试拆机方案Word文档格式.docx(41页珍藏版)》请在冰豆网上搜索。
九、资源配置.............................................................................................................................................15
9.1设备...............................................................................................................................................15
9.2工具...............................................................................................................................................15
9.3耗材...............................................................................................................................................16
Ⅱ、盾构机拆机方案.........................................................................................................................................19
一、概述.....................................................................................................................................................19
二、拆机的准备工作.................................................................................................................................19
2.1前期准备工作...............................................................................................................................19
2.2现场准备工作..............................................................................................................................19
2.3出洞后的准备..............................................................................................................................20
三、主机的拆卸.........................................................................................................................................21
3.1刀盘的拆卸...................................................................................................................................21
3.2螺旋输送机的拆卸.......................................................................................................................22
3.3管片安装机的拆卸.......................................................................................................................23
3.4盾尾的拆卸...................................................................................................................................23
3.5前盾与中盾的拆卸.......................................................................................................................23
四、后配套的拆卸.....................................................................................................................................24
4.1各连接杆件的拆卸.......................................................................................................................24
4.2连接桥的拆卸...............................................................................................................................24
4.3一号拖车.......................................................................................................................................24
4.4二、三、四、五、六号拖车......................................................................................................25
五、液压管件拆卸顺序.............................................................................................................................25
六、电气控制线路的拆卸顺序.................................................................................................................26
七、盾构机拆机人员组织机构.................................................................................................................26
八、拆机整体工序...................................................................................................................................26
九、资源配置.............................................................................................................................................27
盾构机拆机所用机具、工具表.................................................................................................................27
Ⅲ安全文明施工...............................................................................................................................................29
一、危险源辨识及应急措施.....................................................................................................................29
二、安全保证措施.....................................................................................................................................29
2.1技术保证措施...............................................................................................................................29
南宁市轨道交通2号线5标盾构组装调试拆机方案
2.2劳动保护安全措施.......................................................................................................................30
2.3施工现场的安全措施...................................................................................................................30
2.4施工机械安全保证措施...............................................................................................................31
2.5高空作业安全保证措施...............................................................................................................32
2.6吊装作业安全保证措施...............................................................................................................33
2.7安全技术交底...............................................................................................................................34
三、文明施工.............................................................................................................................................38
Ⅰ、盾构工地组装调试方案
一、工程概况及概述
本标段共包含3站7区间,五象大道站、江南客运站、白沙大道站,五象大道站~江南
客运站~白沙大道站~石柱岭站~福建园站~体育馆站区间,友爱站~友爱北站~秀厢站区间。
见1.1-1盾构施工筹划图。
图1.1-1盾构施工筹划图
区间为单线双洞隧道,采用盾构法施工,单线总长11000米。
隧道掘进专用设备盾构机是工程能否顺利完成的关键环节。
为了保证盾构机进入现场
后,能够顺利完成组装、调试、始发、掘进,特编制盾构组装调试方案,合理进行工作和
人员安排,明确质量控制要点,优化作业次序,在确保盾构组装质量的前提下,保证按期
完成盾构组装调试工作。
每次组装开始时,预先到场地勘察,制定车辆的进场顺序,与项目部商谈组装的工具
准备清单,组装场地的照明等先期工作。
现场盾构组装的下井顺序以拖车由后至前,主机下井次序以刀盘为节点。
组装原则为
附属设备尽量地面安装。
管线安装与设备安装同步进行。
组装以液压电气安装为控制要点,
以大件吊装为重点。
1
南宁市轨道交通2号线5标盾构组装调试拆机方案二、人员组织
为保证组装质量和组装进度,需要配备足够的技术人员和技术工人,在确保人员和设
备的安全的前提下,盾构组装过程中,人员组织安排如下表:
组织结构:
三、盾构组装总体方案
总体步骤:
6#拖车—→5#拖车—→4#拖车—→3#拖车—→2#拖车—→1#拖车—→设备桥支撑架下
井—→设备桥(含皮带机)—→螺旋输送机支撑架下井—→螺旋输送机下井—→拆除前端
轨道—→始发台定位—→前盾—→中盾(含人员仓)—→刀盘—→主机前移—→管片安装
机—→盾尾—→铺设轨道至盾尾—→螺旋输送机安装—→底部反力架—→设备桥与主机连
接—→左右侧,顶部反力架安装—→空载调试—→安装负环管片
2
组装流程图
四、吊装设备
1、主要设备外形尺寸重量表
3
2、吊车的选择260吨履带吊。
五、拖车组装
5.1拖车进场
进场顺序6#、5#、4#、3#、2#、1#,设备桥。
进场后停放在竖井端头区。
5.2拖车组装准备
竖井内拖车及后配套轨道铺设变频机车(充电)、管片小车下井。
6#拖车吊装
将6#拖车在地面上安装轮对,附属风管吊机及其支架并紧固螺栓,然后将6#拖车
吊装下井,用变频机车拖拉6#拖车到明挖区靠后的位置。
5#拖车下井吊装
将5#拖车在地面上安装轮对,皮带机后部滚筒及其支架。
将5#拖车吊装下井,用变频
机车拖拉5#拖车到明挖区靠后位置,与6#拖车连接。
4
4#拖车下井
将4#拖车在地面上安装轮对,顶部皮带机支架,将风筒放到皮带机支架上,并用铁丝
绑扎。
将4#拖车吊装下井,用变频机车拖拉4#拖车到明挖区靠后位置,与5#拖车连接。
3#拖车下井
将3#拖车在地面上安装轮对,顶部皮带机支架,将风筒放到皮带机支架上,并用铁丝
将3#拖车吊装下井,用变频机车拖拉3#拖车到明挖区靠后位置,与4#拖车连接。
5
2#拖车下井
将2#拖车在地面上安装轮对,顶部皮带机支架,将风筒放到皮带机支架上,并用铁丝
将2#拖车吊装下井,用变频机车拖拉2#拖车到明挖区靠后位置,与3#拖车连接。
1#拖车下井
将1#拖车在地面上安装轮对,顶部皮带机支架,将风筒放到皮带机支架上,并用铁丝
将1#拖车吊装下井,用变频机车拖拉1#拖车到明挖区位置,与2#拖车连接。
6
南宁市轨道交通2号线5标盾构组装调试拆机方案设备桥支撑架下井,设备桥支撑架的制作应在盾构组装前开始,在拖车下井前完
成。
设备桥下井
设备桥下井,安放到设备桥支撑架上后,用直流焊机将两者搭接位置焊接,并在两侧
增加加强筋板。
焊接完成后,用变频机车将设备桥拖拉到洞内明挖区,前端距离洞口约14
米。
7
螺旋输送机支架下井
螺旋输送机支架的焊接制作工作应在拖车下井前完成。
螺旋输送机下井
螺旋输送机安放到管片小车后,均与支架进行焊接加固,支架的制作可根据实际情况
8
南宁市轨道交通2号线5标盾构组装调试拆机方案进行调整。
但应注意重心选取的影响。
在焊接工作完成后,将螺旋输送机推到隧道明挖处。
拆除前端轨道,始发台下井,定位,加固。
并在始发台正中用红色油漆标明隧道中心
线。
在这期间,部分人员可开展拖车液压,电气,机械部件的连接工作。
注意:
液压管路的连接,不得戴手套,且拆开后连接面均需用化油清洗剂清洗。
电气线路的连接,遵循对号入座的方式,并注意走线的美观,且线路均需绑扎。
机械部件的连接,需调整螺栓孔,紧固螺栓,检查是否有漏紧,漏装的位置。
六、主机组装
?
主机组装准备
盾体下井前清洁结合面,割除盾尾临时支撑,制作盾体前移反力座。
前盾组装
前盾翻身前在地面上清洁中前盾结合面,并安装中前盾密封条。
采用260吨履带吊主、
副钩配合地面翻转,翻转后取掉副钩、使用主钩吊装下井。
保证前盾与连续墙之间留2500mm的距离。
中盾安装(含人仓)
吊装下井方法同前盾。
前盾与中盾贴近前安装人仓密封,及中前盾密封条。
并在吊装
状态安装中盾与前盾连接螺栓。
并用风动扳手紧固4个角后吊车松钩。
最后利用千斤顶调
整人仓安并装螺栓。
9
螺栓涂抹螺纹紧固剂。
螺栓按规定力拒紧固。
刀盘安装
中前