DesignedBy
MacaoCabralGreensightDesigner/AssociateArchitect
Structure&
Model
316LStainlessSteel&
S275CarbonSteelStructuresCoveredwithPoint-SupportedGlass&
AluminumPlateCurtainWall
2.SteelStructures&
CurtainWallsProjectBrief
MacaoAMARALMetalStructures&
CorridorsRebuildingisalarge-scaleglass&
metalstructureprojectfeaturedofuniquemodeling,specialmaterialsandstricttechnicalrequirements.Itmainlyconsistsoftwoportions.Thefirstportionisapetallikemodelingconstructedby316Lstainlesssteelwiththeinner&
outersurfacescoveredwithtoughenedPVB-interlayerglasswhichconsistof2patchesofTIP01,TIP02andTIP03respectively,4patchesofTIP04,1patchofTIP05,8patchesofTIP06totaling19patches.Plusthesupporttrussesinthemiddle,themetalstructureweighedabout300tonsandthetotalglassareareachesabout5,100M2.Thesecondportionisthecorridorsrebuildingthatconsistsof1,030tonsofS275SteelStructures,4,000m2aluminumCurtainWalls,4,250m2glassCurtainWallsand1,720m2glassstage.
3.FeaturesofSteelStructures&
CurtainWallsProject
CurtainWallsprojectiscontractedbytheGeneralContractorwiththemainmaterialsattheOwner(theinvestor)’schoice.ThedesignistobeverifiedbyMacaodesigners.Thecomplicateddesignofthemetalstructureandtheperiodrequirementofthefieldoperationrequirestrictplantpreparations.TheexaminationperiodoftheCustomsmustbetakenintoaccountinintroducingfieldoperators,equipmentandmaterials.Thelocalstandardsreferencedinthedesigning&
operatingofthisprojecthavegrinding-inperiodwithChinaNationalStandards.
4.MainFoundationsofthisplanning
1.TheguidelinesoftheOwner.
2.TheblueprintsfurnishedbytheOwner.
3.Thelatestfieldoperationregulations&
specificationissuedbytheState(China)andtheIndustry.
4.TheRegulationsofConstructionFieldManagementissuedbytheMinistryofConstruction(China).
5.TheimprovedDesignofShenzhenJinYueCurtainWallsDecorationEngineeringCo.,Ltd.
6.ShenzhenJinyue’scapabilityinthefieldsofdesign,manufacture,installationandcapital.
Section2ConstructionGoals
I.QualityGoal
1.One-offacceptanceoftheprojectquality.
2.2yearswarrantyfortheoutsidedecorationsofthisproject,whichcountsfromthedateofacceptance&
signature.Alltheexpensesarisingfromthereworkduetotheprojectqualitywithinthewarrantyperiodwillbeatourcost.
II.PeriodGoal
WewillcoordinateandcooperatewiththeGeneralContractorandotherconstructionunitstomaketheouterdecorationperiodmeettheoveralltimelimit,ofwhichtheinstallationperiodofmetalstructureandCurtainWallsis120days.
ThescheduledstartingdateisOct.5,2005withthespecificstartingdateasnotifiedbytheOwnerinwritten.
III.Safety&
CivilizationGoal
InobediencetotheGeneralContractor’smanagementsoastoensurethesmoothfinishofthisproject.Toputanendtoseriouscasualtyaccidentsandtolowertheinjuryratepermonthtobelow0.1%soastoensurethecivilizedfieldconstruction.
IV.ContractingCommitments
ToabidebytheAgreementandtoprovidetheOwnerwithqualityservices.ToconstructqualityprojecttofulfillthecommitmentstotheOwner.
Chapter2OrganizationChartofProjectManagement
Section1ManagementStaff
此处请重新嵌入翻译的表格
Annex3:
TableofMainProjectManagingPersonnelofFieldOperations
Position
Name
Title
TechnicalTitle
MainExperiences
1.ProjectDirector
邓建球
DeputyGeneralManager
SeniorEngineer
10yearsexperiencesofSteel-Structure&
CurtainWallsoperations
2.SiteManager
张文健
ChiefEngineer
20yearsexperiencesofSteel-Structure&
3.TechnicalDirector
窦铁波
DeputyChiefEngineer
Engineer
15yearsexperiencesofSteel-Structure&
4.SiteManager
曾达超
ManagerofContractEnforcementDept.
5.Designer
吴光琼
ChiefDesigner
10yearsdesignexperiencesofSteel-Structure&
CurtainWalls
4.FieldChief
张洪振
FieldChief
SeniorTechnician
20yearsenginneringexperiencesinfieldoperations
6.QualityInspector
陈远程
QualityInspector
12yearsenginneringexperiencesinfieldoperations
7.MaterialsInspector
尤明秋
MaterialsInspector
7yearsenginneringexperiencesinfieldoperations
8.PlanningAgent
马坚伟
PlanningAgent
8yearsenginneringexperiencesinfieldoperations
9.SafetyInspector
罗新运
SafetyInspector
SafetyDirector
10yearsenginneringexperiencesinfieldoperations
Section2ResponsibilitiesofManagementStaff
1.ProjectCommanderinChief:
ZhangWenjian
Inchargeoftheoverallprojectandtotakecontrolofthewholeandgrasptheoverallsituation.TomakeknowledgeofprojectprogressatanymomentandtohearthereportsofSiteManager,GeneralTechnicalDirectorandotherrelevantpersonnelperiodically(theIntervalnomorethan5days).Beresponsibleforthedispositionofgreatamountofcapitalandtoactivelydealwithorprovideassistancetothespecialissues.
2.SiteManager:
ZengDachao
2.1Tocompileplantandfieldconstructionschedulecombinedwiththegeneralconstructionschedule.
2.2TocoordinatewiththeOwnerandgetpreparedfortheconstruction.
2.3Toattendfieldmeetingsandtotakerecordsandresolveproblems.
2.4Toestablishfieldinstallationplanwiththefieldengineers.
2.5ToreportthefieldsituationtotheGeneralCommanderinchiefinwrittenformperiodically.
3.TechnicalDirector:
DouTiebo
3.1Beresponsibleforalltechnicalissuesandtocontrolthedesignprogressanddesignquality.
3.2Tocoordinatewiththeproductiondept.toresolvethepotentialconflictsindesign&
productionsoastoensuretheprecisemanufacture.
3.4TocoordinatewiththeSiteManagertostudyactualfieldsituationsoastoensurethefieldconstructiontomeetwiththeblueprints.
3.5Beresponsibleforguidingresolvinganypotentialtechnicalproblemsinthewholeprojectandconstructionprocess.
4.Designer:
WuGuangqiong,etc
4.1Toimprovedesignaccordingtothebiddingdocuments.
4.2Todiscussdrawingsdetailsandanypotentialdesignrevisionwiththearchitectsandberesponsiblefortheaudit&
approvalofconstructionblueprints.
4.3Todesigncomponentsmanufactureblueprintsandcompilematerialsorders.
4.4Toadjustmaterialsordersandmanufacturedimensionsinaccordancewiththeactualfieldmeasurements.
4.5TocoordinatewiththeProductionDept.withanypotentialconflictssoastoensurethecompleteaccuratedesign.
4.6Beresponsibleforresolvinganypotentialtechnicalproblemsinconstruction.
5.FieldChief:
ZhangHongzhen
5.1Toresolvealltechnicalproblemsinconstructionandbringforwardsuitableconstructiontechnology.
5.2ToanalyzethefieldmeasurementsandfeedbackalldeviationsagainsttheconstructionblueprintstotheDesignDept.Inordertoensuretheprojectprogressandquality,toworkwithSiteManagertoholdmeetingsperiodicallyandinvitetherepresentativesofOwner,installationheadandetc.tocoordinateanddiscussallaspectsoftheprojectandafterthattofeedbackthemeetingsummariestothecompanytofacilitatetheoverallarrangement.
6.MaterialAgent:
YouMingqiu
6.1Tocompileoverallsuppliessupply,customsdeclarationanduseplaninaccordancewiththetimelimitoftheproject.
6.2Tobringforwardmaterialsrationandberesponsibleformaterialspurchase.
6.3Beresponsibleforsupervisingmaterialsqualityandcheckingmaterialquantities.
6.4BeresponsiblefortheCustomsClearanceandtransportationofmaterials.
7.QualityController:
ChenYuancheng
7.1Toconductfieldinspectioninaccordancewiththegoverningtechnicaldocuments,drawingsandindustryandenterprisestandards.
7.2Toinspectallincomingproductsandsemi-finishedproductsandrejectallNGproducts.
7.3Toinspecttheprotectionmeasuresofproductsandsemi-finishedproducts.
7.4BeentitledtomakereworkdecisiononNGportionswhileininstallationandtoreporttothecompanyforrecord.
7.5ToconductthepositionqualificationoverallnewemployeesandrejectallNGones.
7.6ToworkwiththeSiteManagerandtheCounselorEnterprisetofinishthequalityacceptanceoftheprocessesandthewholeproject.
8.SafetyInspector:
LuoXinyun
Toeducatecivilizedoperationconceptoverfieldoperatorsandresolveanywildoperations.ExternallytobeinobediencetotheunifiedcommandandarrangementoftheOwner,theCounselorandtheGeneralContractorsoastoachievemutualunderstandingandcooperation.
Tokeepcleanofthebuildingfieldandexterminatepollution.Toreasonablyarrangeoperatorsandfacilitiesaccordingtositesituationandpreventthedisturbanceovernormallivesofneighbourhood.
9.CoordinationAgent:
MaJianwei
9.1BeresponsibleforthecontactswithallpartiesandtocoordinatetherelationshipwiththeOwner,theGeneralContractorandtheDesignertoensurethetimelycommunication.
9.2Tocoordinatepaymentissues.
9.3Tocoordinateprojectacceptanceandwarranty.
10.OperationTeam
Multi-operationteam