1、Designed ByMacao Cabral Greensight Designer/Associate ArchitectStructure & Model316L Stainless Steel & S275 Carbon Steel Structures Covered with Point-Supported Glass & Aluminum Plate Curtain Wall2. Steel Structures & Curtain Walls Project BriefMacao AMARAL Metal Structures & Corridors Rebuilding is
2、 a large-scale glass & metal structure project featured of unique modeling, special materials and strict technical requirements. It mainly consists of two portions. The first portion is a petallike modeling constructed by 316L stainless steel with the inner & outer surfaces covered with toughened PV
3、B-interlayer glass which consist of 2 patches of TIP01, TIP02 and TIP03 respectively, 4 patches of TIP04, 1 patch of TIP05, 8 patches of TIP06 totaling 19 patches. Plus the support trusses in the middle, the metal structure weighed about 300 tons and the total glass area reaches about 5,100M2. The s
4、econd portion is the corridors rebuilding that consists of 1,030 tons of S275 Steel Structures, 4,000m2 aluminum Curtain Walls, 4,250m2 glass Curtain Walls and 1,720m2 glass stage.3. Features of Steel Structures & Curtain Walls ProjectCurtain Walls project is contracted by the General Contractor wit
5、h the main materials at the Owner (the investor)s choice. The design is to be verified by Macao designers. The complicated design of the metal structure and the period requirement of the field operation require strict plant preparations. The examination period of the Customs must be taken into accou
6、nt in introducing field operators, equipment and materials. The local standards referenced in the designing & operating of this project have grinding-in period with China National Standards.4. Main Foundations of this planning1. The guidelines of the Owner.2. The blueprints furnished by the Owner. 3
7、. The latest field operation regulations & specification issued by the State(China) and the Industry. 4. The Regulations of Construction Field Management issued by the Ministry of Construction (China). 5. The improved Design of Shenzhen JinYue Curtain Walls Decoration Engineering Co., Ltd.6. Shenzhe
8、n Jinyues capability in the fields of design, manufacture, installation and capital. Section 2 Construction GoalsI. Quality Goal1. One-off acceptance of the project quality. 2. 2 years warranty for the outside decorations of this project, which counts from the date of acceptance & signature. All the
9、 expenses arising from the rework due to the project quality within the warranty period will be at our cost. II. Period GoalWe will coordinate and cooperate with the General Contractor and other construction units to make the outer decoration period meet the overall time limit, of which the installa
10、tion period of metal structure and Curtain Walls is 120 days.The scheduled starting date is Oct. 5, 2005 with the specific starting date as notified by the Owner in written.III. Safety & Civilization Goal In obedience to the General Contractors management so as to ensure the smooth finish of this pr
11、oject. To put an end to serious casualty accidents and to lower the injury rate per month to below 0.1% so as to ensure the civilized field construction.IV. Contracting Commitments To abide by the Agreement and to provide the Owner with quality services. To construct quality project to fulfill the c
12、ommitments to the Owner. Chapter 2 Organization Chart of Project ManagementSection 1 Management Staff此处请重新嵌入翻译的表格Annex 3: Table of Main Project Managing Personnel of Field OperationsPositionNameTitleTechnical TitleMain Experiences1. Project Director邓建球Deputy General ManagerSenior Engineer10 years ex
13、periences of Steel-Structure & Curtain Walls operations2. Site Manager张文健Chief Engineer20 years experiences of Steel-Structure &3. Technical Director窦铁波Deputy Chief EngineerEngineer15 years experiences of Steel-Structure &4. Site Manager曾达超Manager of Contract Enforcement Dept.5. Designer吴光琼Chief Des
14、igner10 years design experiences of Steel-Structure & Curtain Walls 4. Field Chief张洪振Field ChiefSenior Technician20 years enginnering experiences in field operations6. Quality Inspector陈远程Quality Inspector12 years enginnering experiences in field operations7. Materials Inspector尤明秋Materials Inspecto
15、r7 years enginnering experiences in field operations8. Planning Agent马坚伟Planning Agent8 years enginnering experiences in field operations9. Safety Inspector罗新运Safety InspectorSafety Director10 years enginnering experiences in field operationsSection 2 Responsibilities of Management Staff1. Project C
16、ommander in Chief: Zhang WenjianIn charge of the overall project and to take control of the whole and grasp the overall situation. To make knowledge of project progress at any moment and to hear the reports of Site Manager, General Technical Director and other relevant personnel periodically (the In
17、terval no more than 5 days). Be responsible for the disposition of great amount of capital and to actively deal with or provide assistance to the special issues.2. Site Manager: Zeng Dachao2.1 To compile plant and field construction schedule combined with the general construction schedule. 2.2 To co
18、ordinate with the Owner and get prepared for the construction.2.3 To attend field meetings and to take records and resolve problems. 2.4 To establish field installation plan with the field engineers. 2.5 To report the field situation to the General Commander in chief in written form periodically. 3.
19、 Technical Director: Dou Tiebo 3.1 Be responsible for all technical issues and to control the design progress and design quality. 3.2 To coordinate with the production dept. to resolve the potential conflicts in design & production so as to ensure the precise manufacture. 3.4 To coordinate with the
20、Site Manager to study actual field situation so as to ensure the field construction to meet with the blueprints. 3.5 Be responsible for guiding resolving any potential technical problems in the whole project and construction process. 4. Designer: Wu Guangqiong, etc 4.1 To improve design according to
21、 the bidding documents. 4.2 To discuss drawings details and any potential design revision with the architects and be responsible for the audit & approval of construction blueprints. 4.3 To design components manufacture blueprints and compile materials orders. 4.4 To adjust materials orders and manuf
22、acture dimensions in accordance with the actual field measurements. 4.5 To coordinate with the Production Dept. with any potential conflicts so as to ensure the complete accurate design.4.6 Be responsible for resolving any potential technical problems in construction. 5Field Chief: Zhang Hongzhen5.1
23、 To resolve all technical problems in construction and bring forward suitable construction technology. 5.2 To analyze the field measurements and feed back all deviations against the construction blueprints to the Design Dept. In order to ensure the project progress and quality, to work with Site Man
24、ager to hold meetings periodically and invite the representatives of Owner, installation head and etc. to coordinate and discuss all aspects of the project and after that to feed back the meeting summaries to the company to facilitate the overall arrangement. 6. Material Agent: You Mingqiu 6.1 To co
25、mpile overall supplies supply, customs declaration and use plan in accordance with the time limit of the project. 6.2 To bring forward materials ration and be responsible for materials purchase. 6.3 Be responsible for supervising materials quality and checking material quantities. 6.4 Be responsible
26、 for the Customs Clearance and transportation of materials. 7. Quality Controller: Chen Yuancheng 7.1 To conduct field inspection in accordance with the governing technical documents, drawings and industry and enterprise standards. 7.2 To inspect all incoming products and semi-finished products and
27、reject all NG products. 7.3 To inspect the protection measures of products and semi-finished products.7.4 Be entitled to make rework decision on NG portions while in installation and to report to the company for record. 7.5 To conduct the position qualification over all new employees and reject all
28、NG ones. 7.6 To work with the Site Manager and the Counselor Enterprise to finish the quality acceptance of the processes and the whole project. 8. Safety Inspector: Luo XinyunTo educate civilized operation concept over field operators and resolve any wild operations. Externally to be in obedience t
29、o the unified command and arrangement of the Owner, the Counselor and the General Contractor so as to achieve mutual understanding and cooperation. To keep clean of the building field and exterminate pollution. To reasonably arrange operators and facilities according to site situation and prevent th
30、e disturbance over normal lives of neighbourhood. 9. Coordination Agent: Ma Jianwei 9.1 Be responsible for the contacts with all parties and to coordinate the relationship with the Owner, the General Contractor and the Designer to ensure the timely communication. 9.2 To coordinate payment issues. 9.3 To coordinate project acceptance and warranty. 10. Operation TeamMulti-operation team
copyright@ 2008-2022 冰豆网网站版权所有
经营许可证编号:鄂ICP备2022015515号-1