施工组织设计

(电气照明安装工程)

工程名称:

XX数控装备股份有限公司扩建工程1#厂房

建设单位:

XX数控装备股份有限公司

监理单位:

XXXXXXX建设监理有限公司

施工单位:

XXXX安装工程有限公司

编制日期:

二○一四年七月二十六日

第一章工程概况·························································1

第一节编制依据·····························································1

第二节工程概况····························································1

第三节施工范围·························································1

第二章工程得重点、难点分析··········································2

第三章项目管理目标及组织机构设置········································2

第一节项目管理目标·······················································2

第二节项目组织机构设置····················································6

第三节项目部主要人员岗位职责··············································7

第四章施工准备计划·····················································10

第一节总体施工准备部署···················································11

第二节施工准备计划·······················································12

第三节施工执行得规程规范·················································13

第五章施工进度控制网络计划··············································14

第一节施工进度网络图·····················································14

第六章施工资源供应计划·················································15

第一节劳动力使用计划表与保障措施·········································15第二节主要施工机械设备、检测设备情况······································16

第七章施工平面布置图················································17

第一节施工现场平面布置原则···············································17

第二节施工总平面图·······················································18

第八章分部分项工程得主要施工方案与技术措施······························18

第一节电气设备安装工程···················································18

1、工程概况·······························································18

2、电气管路箱盒预埋·························································20

3、防雷接地系统施工·························································24

4、等电位联结·······························································27

5、电气明管敷设····························································29

6、配电柜、箱、盘安装························································35

7、导管敷设·······························································41

8、电缆敷设································································44

9.电缆终端头制作···························································48

10、照明器具安装····························································52

第九章确保工程质量得技术组·············································55

第一节工程质量目标·······················································55

第二节工程质量保证体系··················································55第三节主要岗位质量管理职责···············································56

第四节工程质量保证措施···················································59

第五节技术保证措施······················································66

第六节质量检验及不合格品得控制··········································67

第七节工程资料管理·····················································71

第十章确保安全施工得技术组织措施·······································73

第一节管理目标·························································73

第二节安全保证体系······················································74

第三节安全岗位职责······················································75

第四节安全管理制度······················································78

第五节安全防护措施······················································79

第六节现场临时用电安全管理措施···········································80

第七节消防管理措施······················································82

第八节安全保卫措施······················································82

第十一章确保文明施工得技术组织措施······································83

第一章工程概况与系统说明

第一节编制依据

1、招标文件;

2、施工图纸及施工图设计说明;

3、国家现行得法规:

中华人民共与国建筑法

中华人民共与国环境保护法

中华人民共与国计量法

建筑工程施工现场管理规定《建设部15号令》

建设工程管理条例《国务院第279号》

4、国家及黑龙江省现行建设工程设计、施工、质量、安全、设备、环保等规范《建筑电气工程施工质量验收规范》GB50303-2002、规程、标准《建筑工程施工质量验收统一标准》GB50300-2001、图集及有关文件;

5、类似工程施工经验与管理经验。

第二节工程概况

一、工程简介

工程名称:

XX数控装备服从有限公司扩建工程1#厂房

建设地点:

XXXX市XX数控装备服从有限公司院内

本工程为单层厂房局部五层,建筑面积42342㎡,建筑高度19、65米。

本厂房生产火灾危险性分类为戊类。

照明总配电柜电源(380V/220V)引自车间变电所,用电负荷为三级。

二、工期要求

计划进场日期:

2014年7月22日。

计划竣工日期:

2014年11月8日。

具体开工日期以招标人发出得书面开工令为准。

三、质量标准

合格。

第三节施工范围

a、照明及应急照明系统;

b、电力配电系统;

c、防雷接地系统;

d、电线电缆敷设;

e、支路(管)线敷设;

第二章工程得重点、难点分析

工程得难点

如何做好施工组织将就是此项工程得一个难点。

由于电气安装没有绝对施工工期,因此电气专业施工将始终在土建施工期间交叉作业,这无形中将加大施工组织、作业、检测得难度。

这将就是对我们得管理水平、操作能力、沟通协调能力得一大考验。

对此我单位将配备充足得能够胜任得工程管理人员,高效率地开展工作,对整个工程得进度、质量、安全与成本进行有效得管理与控制,全面对业主负责。

与业主、设计、监理与土建施工队伍密切合作,充分发挥电气承包得沟通与协调职能,严格履行电气承包合同,确保项目目标得实现,圆满实现业主得期望。

第三章项目管理目标及组织机构设置

第一节项目管理目标

一、质量管理目标

确保本工程施工质量达到合格。

二、工期管理目标

计划开工日期:

2014年7月22日。

计划竣工日期:

2014年11月8日。

三、安全管理目标

杜绝工伤死亡事故;

杜绝重大火灾事故;

减少职业病伤害得发生;

外地施工人员健康凭证取证率100%;

四、环境管理目标

噪声排放标准按照III类标准(工业区):

昼间70dB(A),夜间55dB(A)。

化学危险品无泄漏:

进场化学危险品100%在合格供方购买,单独存放率100%,施工过程中100%交底;

有毒有害废弃物合法处置:

化学危险品包装物回收率90%,废墨盒、废硒鼓回收率100%,废旧电池回收率100%,废色带、废油墨盒回收率100%;

杜绝发生重大火灾爆炸事故;

五、建设绿色建筑目标

严格落实业主与设计关于节水、节能、环保与绿化得各项要求,为客户提供一组高品质、高舒适度、高完成度得绿色建筑。

六、团结合作目标

施工过程中,积极与监理、设计、业主以及专业分包单位精诚团结,共同为业主提供最优质得服务,齐心协力打造一件出色得建筑作品。

第二节项目组织机构设置

一、总则

我们将依据现代项目管理模式,组建本项目得管理班子,选派高素质、精干、并具有同类型及大型工程施工管理经验得工程技术人员