水平定向钻施工组织方案
目录1、工程概况.....................................................................................................12、组织机构.....................................................................................................12.1项目管理...............................................................................................12.2施工班组...............................................................................................13、施工组织.....................................................................................................14、技术措施.....................................................................................................84.1施工方法...............................................................................................84.2施工流程.............................................................................................104.3机械准备.............................................................................................104.4路径复测.............................................................................................114.5水平导向钻进施工..............................................................................124.6施工控制措施.....................................................................................165、质量措施...................................................................................................175.1原材料及器材检验..............................................................................175.2质量缺陷处理.....................................................................................186、安全措施...................................................................................................186.1安全施工大纲.....................................................................................186.2施工现场管理规定..............................................................................206.3工具器及设备使用..............................................................................20广州电力建筑安装工程有限公司6.4水平导向钻进施工危险点辩识...........................................................217、文明施工及环保措施................................................................................227.1文明施工措施.....................................................................................227.2环境因素辨识表.................................................................................227.3环境保护措施.....................................................................................227.4施工事故及应急措施..........................................................................238、施工进度计划表.......................................................................................239、应急措施...................................................................................................249.1人员触电.............................................................................................249.2现场火灾.............................................................................................249.3中毒....................................................................................................249.4中暑....................................................................................................259.5灼伤....................................................................................................259.6医院位置...............................................................错误!
未定义书签。
10.工程回访、保修服务及承诺....................................................................2513.1回访、保修服务的依据......................................................................2513.2工程回访.............................................................................................2513.3保修服务.............................................................................................2513.4保修服务承诺.....................................................................................252广州电力建筑安装工程有限公司1、工程概况①2010业扩配套电力顶管工程,位于广州市南洲路。
新顶2孔Φ160HDPE电力护套管103米(附电缆设计走向图)。
工程施工需作好安全防护,穿越深度以现场路面正负零起算确定为-10.0m。
本工程拟采用美国先进技术水平的水平定向钻进行顶管施工。
②计划施工时间:
2011年5月21-2010年5月31日2、组织机构2.1项目管理总负责:
叶祖彦项目经理:
何旭焜安全专责:
李本桓质检专责:
李本桓材料专责:
赵树新理赔专责:
何旭焜资料专责:
任景丽2.2施工班组班长:
陈海洋现场负责:
龙盛波质检员:
官小威安全员:
黄定3、施工组织1广州电力建筑安装工程有限公司工程项目管理组织图3.1项目班子配备和职责分工3.1.1项目班子人员配置施工项目经理部主要管理人员表2广州电力建筑安装工程有限公司3.1.2项目班子成员职责分工3.2.2.1项目经理职责项目经理是公司法定代表人在本项目上的全权委托代理人,具体履行、实施该项目的工程合同,对工程项目全面负责。
(1)贯彻执行国家、行业和项目所在地有关工程质量、环境保护和职业健康法律法规、规范、规定,贯彻执行集团公司管理方针、目标与方案。
(2)组织制定项目经理部各类人员的职责权限和各项规章制度,搞好与上级各管理职能部门的业务联系和经济往来,定期报告工作。
(3)负责组织本项目施工全过程的一切管理活动,执行公司颁布实施《管理手册分手册》和有关程序文件,并将各项管理职责分工落实到人。
①参与公司组织本项目的合同评审和接收评审后的合同交底,负责组织编制项目质量计划或实施性施工组织设计并组织实施;②负责组织对本项目的环境因素识别、危险源辩识,编制项目环境,职业健康安全管理方案、应急响应方案并负责运行管理。
建立应急指挥机构并进行管理,定期组织应急演练。
③负责按合格物资分供方(中间商)名录中采购物资,负责评定、审批B类物资分供方,负责按合格劳务/工程分承包选择外协队伍;④负责组织对施工现场产品标识和可追溯性施工过程(特殊/关键工序)的控制、管理,执行公司颁布的设备使用、管理制度、安全操作规程,确保施工设备经常处于良好状3广州电力建筑安装工程有限公司态,负责项目工地安全生产与文明施工;⑤负责组织物资验证、复试,分项/分部工程和竣工工程的检验和试验工作的实施和管理;⑥负责组织项目检验、测量和试验设备的使用、维护和管理工作,组织实施分项分部工程检验、试验状态标识,实施不合格品的整修方案,