1.PURPOSE
ThisDocumentexplainsthedetailedprocedureforErectionofBatchingPlantusingHydraulicMobilecrane50T/60T.
2.;
3.SCOPE
Thismethodstatementdetailstheerectionandcommissioningof:
BatchingplantwithSilosandAssembly.
4.REFERENCESDOCUMENTS/SPECIFICATION/STANDARD
BatchingSchwingStetterM-1T
SHEconditionsofcontract.
SHEmanualofcontract.
ProjectEHSplan.
!
ProjectQualityPlan.
5.RESPONSIBILITIES:
Followingaretheresponsibilitiesandreportingstructureofpersonnelinvolvedinthescopeoftheprocedure:
Position
Reporting/Responsibilities
【
ProjectManager
Shallberesponsibleforsafeandtimelyerectionofbatchingplantinhissupervision.
Shallberesponsibleforassuringqualitytobemaintained.
DeputyProjectManager
Shallberesponsibleforcontrol,supervisionanddirectionforimplementationandexecutionofconstructionplansinregardoferectionofbatchingplant.
Manager(CastingYard)
Shallalsoberesponsibleforsupervisionoferectionofbatchingplantandotherassemblies.Ensuringofconstructionactivitiesandpreparationofrecords,proceduresrequiredtobecompletedinregardofbatchingplanterection.
Sr.Engineer(Execution)
!
Shallreporttomanagercastingyard
Shallberesponsibleforday-to-dayplanningandprogressofsite.
Gettingthefoundationreadyasperrequireddrawingsforsafeandearlyplanterection.
Responsibletofinalizethelocationofbatchingplantandgetitapprovedbymanager(castingyard).
Surveyor
ShallreporttoManager(Castingyard)
…
ShallberesponsibletocoordinatewithManager(Castingyard),understandthedrawing,planning&
carryingoutofsurveyactivitiesatsitealongwiththepreparationofsurveyrecordsbasedontheapproveddrawing.
QA/QCIncharge
ShallreporttoProjectManager.
ShallberesponsibleforoverallcontrolofQCactivitiesandsub-contractor’sQCactivitiesasperapprovedITPandimplementationofProjectQualityPlan.
ShallberesponsibleforcarryingoutInspectionasperspecification.
;
ChiefSHEManager
ShallberesponsibleforoverallcontrolofSHEActivityasperapprovedSafetyMethodology.
EnsuringtheapprovalofMethodstatementbytheclient.
ResponsibletoEnsuretoprovideRiskAssessmentinvolvedinerectionofBatchingPlant.
Monitoringofsafetyrequirementanditscompliancesfromtimetotime.
SHEEngineer
—
ResponsibleforcompletingallthedocumentsneededforerectionofBatchingPlant.
Responsibleforprovisionofriskassessment.
Responsibleforensuringcranedocuments.
Responsibleformakingliftingplanandcommencementofallsafetymeasuresrequiredbeforeliftingoperationsstarts.
SHESteward
ShallreporttoSHEEngineer/SHEManager.
MonitoringofToolBox(TBT)atsitebeforeerectionofplantstarts.
'
ToprovideandensurethecorrectuseofPPE'
s&
safetydevicesaspertheworkingcondition.
Ensuresafeworkaterectionlocation.
ResponsibletomakesurenoworkmenshallbeallowedtositewithoutPPEsandSafetyInduction.
P&
MIncharge
ShallreporttoProjectManager
Responsibleforsafeandtimelyerectionofbatchingplant.
ResponsibletoensurealltheequipmentsshallbeTPIbyapprovedTPIvendor.
】
Responsiblefortheselectionofcranetobedeployedforsafeerectionofbatchingplant.
Monitorstheerectionofbatchingplantatsite.
CoordinateswiththeProjectManagerforallplantandequipmentrequirements.Tomeetthedeadlineofrsafeandtimelyerectionofbatchingplant.
Electrical/MechanicalIncharge
ShallreporttoP&
MIncharge.
Responsibleforsafeelectricalpowersupplyanddistributionatsiteduringliftingoperation.
Responsibletoprovideoptimumworkinglightaterectionlocation.
Responsibleforensuringnocableshallgetpuncturedorpassthroughtheliftingarea.
ResponsibletoCo-ordinatewithElectricalContractorforElectrification,Execution,Erection&
Commissioning.
Ensuringpropercableroutingofbatchingplantaftererectionandcommissioning,throughtrench.
Responsiblefortoensurealldocumentsrelatedtoerectionofplanthasbeensubmitted.
Responsibleforensuringliftingplanofbatchingplant
Responsibletousetaglinewhileliftingofheavyequipmentofbatchingplant.
Responsibletoensuretheliftingisbeingcarriedoutwithincranelimits.
Toensurethegroundconditionbeforefinalizingthecranelocation.
\
ToensureforavailabilityofTPIapprovalforcraneandliftingequipmentstobeusedforerectionofbatchingplant.
SiteSupervisor
ShallReporttoEngineer.
EnsureallworkiscompletedaspertheresponsibilitiesofEngineer.
DirectandsupervisetheWorkman,operatorsandriggersforthedesiredworktobedone.
`
6.MACHINERY,TOOLS,EQUIPMENTSANDMATERIALS
Srno
Equipment
Nos.
Remarks
1
"
HydraCraneIIndGeneration(F-15)
01
Asperrequirement
2
HydraulicCrane(77Tat75%dinrated)
02
4
~
WeldingMachine
5
Gascuttingset
6
[
Grinder
7
Handtools,Jack
8
《
Wireropeslings&
ChainSlings(10T,6T,2T)
04Set
9
DShackles(17T,
06+02
10
@
Nylonrope,28mmdiaturnbuckles
15mtr
11
Webslings5T
4No
》
7.MATERIALS
MajormaterialstobeusedintheErectionofBatchingPlant
StructuralSteelasperIS2062shallbeused
SuitableElectrodesofgrade–6013orothergradeasrecommendedbyDesigner/Designdrawingshallbeused.
Concreteofspecifiedgradeshallbeusedasperapproveddesign&
drawings.
Boltswithwashersaspertheapproveddesign&
'
Suitablegroutmaterials.
MACHINERY,TOOLS,EQUIPMENTSANDMATERIALS
Silo3200dia.Weight6T-04nos.,(100Toncapacity)
BatchingPlant(Mainstructure)weightapprox.17Ton.
Aggregatehopperandbeltconveyor.
OperationCabin.
}
CementScrew.
DustControllerSystem.
8.WORKMETHODOLOGY
Whethertheliftingoperationsarerepetitiveoriftheyareaoneoff,asafesystemofworkmustbeestablishedandfollowedfortheoperationtobebothsafeandsuccessful.
Inordertoprovideasafesystemofworkthefollowingitemsaretobeincludedintheliftplan/Assessment
Thesequentialactivityandcorrespondingmethodsaredetailbelow
-
Erectionofbatchingplantwith04no.silosandAssembly,Make-SchwingStetter,Model-M-1T,Capacity-54Cum/Hr.
SELECTIONOFCRANE:
Theselectionofsuitablecraneandworkequipmentmustbecarriedout.
Acraneteamhastobedeployedatsiteforpreinspectionofsoilconditionandmakethemawareoftheirresponsibilitiesbeforethecommencementofthejob.
Allcertifications,reportsofthoroughexaminationandotherdocumentsincludingmanufacturersmanualaretoberetainedandavailable.
7.3CRANEOPERATIONS
*
Onlyauthorized&
experiencedOperatorshallbepermittedtooperatethecrane.
Assembling,maintenanceanddisassemblingontheequipmentshallbedoneasperthemanufacturer’smanualandThird-partycertifiedcraneshallonlybedeployedforthejob
Overloadingshallneverbeallowedatsite.Weightofloadbeingliftedandtheliftingradiusofallmajorcomponentsareprovidedinthemethodstatement.SamewillbeincorporatedinthedailyerectionpermitalsoandCraneshallbestationedonafirmlevelground.
Theoperatorshallensuretheareaisgoodenoughforthecranebeforemarchingorparkingit.
Properboomangleandradiusshallbefollowedtolifttheload.Refertheloadchartgiveninthecranemanualorfixedinsidethecranecabin.Cranesshallnotbeparkedneartheedgesofpitorexcavations.
Limitswitchofcranesshallbetestedfrequentlyforensuringitsproperfunctioning.
Theswingingareaofthecraneshallbecordoned.TheCranehelpershallensurenotrespassersenterinthisvicinityandatrainedsignalmanshallgivethesignalforcraneoperation.
Theoperatorshallhaveaclearviewoftheoperationthroughoutthehoistingperiod.
Thebanksmanshallbealwaysatthevisibilityofthecraneoperator.Iftheoperationissuchthatthebanksmanmuststandatanobscurelocationthenmorebanksmanshallbepostedtohaveaneffectivecommunication.Acompetentrigginggangshalldomaterialhandling
Clearpassagesshallbeleftforeasyhandlingandtransportationstructures.
Allpersonsshallstandclearwhenacraneissortingorshiftingmaterials.
Belowstaffshouldbeavailableatthetimeoferection-
KECP&
Mincharge/P&
Mincharge(ForSupervision).
KECElectrical/MechanicalEngineer.
、
SchwingStetter(OEM)serviceengineer(Erectionactivity).
SkilledRiggerforerectionwork.
Unskilledworkmen.
Electrician
Mechanic.
Welder
7.5}
7.6GENERALSAFETYMEASURES
Onlyskilled&
experiencedgang(specialised)willbedeployed.
Onlytested&
certifiedtools&
tacklesshouldbeused.
Cranesbeingusedforerectionactivitiesshouldhavevalid3rdpartyinspectioncertificate.
Alltheworkmenhavetowearfullbodyharnessandfallarrestoratthetimeofworkingatabove3metersheight
SoftbarricationtheareaofbatchingPlantduringerection,nounauthorisedworkmenwillbeallowedintheerectionarea.
Ensurepropercommunic