深井降水方案Word格式文档下载.docx
《深井降水方案Word格式文档下载.docx》由会员分享,可在线阅读,更多相关《深井降水方案Word格式文档下载.docx(20页珍藏版)》请在冰豆网上搜索。
1.1、基本概况........................................................................................................................-3-
1.2、基坑概况........................................................................................................................-3-
1.3、基坑围护结构概况..........................................................................................................-3-二、工程地质及水文地质条件........................................................................................................-4-
2.1、工程地质条件.................................................................................................................-4-
2.2、水文地质条件.................................................................................................................-4-三、基坑降水方案.........................................................................................................................-5-
3.1、编制依据........................................................................................................................-5-
3.2、降水目的及方案选择......................................................................................................-5-
3.3基坑降水方案...................................................................................................................-6-
3.3.1、深井降水有关计算...............................................................................................-6-
3.3.2、深井平面布置......................................................................................................-8-
3.3.3、深井井身结构......................................................................................................-8-四、施工组织..............................................................................................................................-10-
4.1、施工管理机构设置........................................................................................................-10-
4.2、管理人员配置及劳动力组织..........................................................................................-10-
4.3、施工机械、设备配备....................................................................................................-11-六、施工方法..............................................................................................................................-13-
6.1、深井施工......................................................................................................................-13-七、降水运行管理.......................................................................................................................-18-
八、降水注意事项.......................................................................................................................-19-
九、质量、安全及文明施工保证措施...........................................................................................-20-
9.1、质量保证措施...............................................................................................................-20-
9.2、安全措施......................................................................................................................-21-
9.3、文明施工措施...............................................................................................................-21-十、基坑开挖应急措施................................................................................................................-22-十一、施工配合...........................................................................................................................-23-
十二、季节性施工措施................................................................................................................-24-
12.1、雨季施工技术措施......................................................................................................-24-十三、技术资料整理汇总.............................................................................................................-25-附件:
基坑降水布置附图3张
江苏中兴建设有限公司-2-
一、工程概况
1.1、基本概况
1)、工程名称:
上海市北高新技术服务区7#地块项目基坑降水
2)、建设单位:
上海远运投资管理有限公司
3)、施工总承包单位:
4)、基坑围护设计单位:
上海岩土工程勘察设计研究院有限公司
5)、监理单位:
6)、地理位置:
上海市闸北区寿阳路以东、平型关路以西、江场路以南。
27)、基坑规模:
本项目基坑开挖面积约为49305?
(其中东区23649m,西区24656
2m)。
8)、编制范围:
本工程分两个区,东区先行施工,再施工西区,东区施工到?
0.00时方可开始施工西区。
1.2、基坑概况
1)、本工程结构概况
“上海市北高新技术服务区7#地块项目”工程的拟建物由2幢23层大型甲拟建
级标准办公楼,1幢10层大型办公楼,2栋8层办公楼、2栋6层办公楼、2栋1,33层商业用房及其它的附属建筑,拟建建筑下为统一大型地下室,均为地下2层。
2)、基坑规模及开挖深度:
坑降水面积及开挖深度详见下表:
名称面积基坑底标高最大挖深地下层数
东区23649?
-11.1m10.45m二层
东区局部落深-13.1m12.45m二层
西区25656-11.1m10.45m二层
1.3、基坑围护结构概况
2本基坑为一级基坑,基坑开挖面积为总计约49305m,地下室开挖深度为
江苏中兴建设有限公司-3-
上海市北高新技术服务区7#地块项目——降水施工方案10.45m/12.45m;
基坑开挖面积大,开挖深度深,施工影响范围广。
基坑围护设计采用三轴搅拌+灌注桩+两道内支撑的围护形式。
二、工程地质及水文地质条件
2.