钢筋混凝土圆管涵施工组织设计方案Word文档下载推荐.docx
《钢筋混凝土圆管涵施工组织设计方案Word文档下载推荐.docx》由会员分享,可在线阅读,更多相关《钢筋混凝土圆管涵施工组织设计方案Word文档下载推荐.docx(16页珍藏版)》请在冰豆网上搜索。
![钢筋混凝土圆管涵施工组织设计方案Word文档下载推荐.docx](https://file1.bdocx.com/fileroot1/2022-10/9/9468001c-58d4-400d-886c-4aa01d442844/9468001c-58d4-400d-886c-4aa01d4428441.gif)
3施工组织、资源配置.....................................................................................................5
3.1现场管理机构设置................................................................................................5
3.2资源配置..............................................................................................................5
3.3工期安排..............................................................................................................6
3.4材料供应..............................................................................................................6
4施工方案........................................................................................................................6
4.1基坑开挖...............................................................................................................6
4.2砂砾垫层施工.......................................................................................................7
4.3浇筑基础混凝土...................................................................................................7
4.4管节安装...............................................................................................................7
4.5浇筑管座混凝土...................................................................................................8
4.6接缝、沉降缝处理................................................................................................8
4.7护管......................................................................................................................8
4.8进出口工程施工(端墙、八字翼墙等)..............................................................8
4.9浆砌片石洞口铺砌施工........................................................................................8
0
4.10填土.....................................................................................................................9
5管理和质量控制的组织保证措施...................................................................................9
5.1质量管理...............................................................................................................9
5.2质量控制要点.......................................................................................................9
5.3质量控制的具体措施...........................................................................................10
5.4常见问题及防治措施...........................................................................................10
6安全组织措施................................................................................................................11
6.1建立安全保证体系................................................................................................11
6.2安全教育和训练...................................................................................................11
6.3落实安全责任制,制定安全管理的各项规章制度...............................................11
6.4各项安全技术措施................................................................................................11
7环境保护、水土保持保证体系及保证措施...................................................................12
7.1环境保护、水土保持保证体系.............................................................................12
7.2环境保护、水土保持措施...................................................................................12
8文明施工、文物保护保证体系及保证措施...................................................................13
8.1文明施工、文物保护保证体系.............................................................................13
8.2文明施工、文物保护保证措施............................................................................13
钢筋混凝土圆管涵、倒虹吸施工方案
一、编制说明
1.1编制依据
1、依据招投标文件、设计施工图纸、工程地质勘查报告及相关的文件精神;
2、当地气候、交通、资源、环境及工程地质和水文地质条件;
3、《公路桥涵施工技术规范》(JTG/TF50-2011)
4、《公路工程质量检验评定标准》JTJF80/1-2004
5、现场踏勘调查所获取的相关资料;
6、我单位施工类似工程积累的施工经验。
1.2编制原则
1、全面符合招标文件关于工程质量、工期、安全、环保、文明施工等各方面的要求。
2、按倒排工期方法确定各道工序施工进度,以此上足机械设备和劳力,并做到机械设备配套、技术工种齐全,确保按计划完工。
3、采用成熟的施工技术和工艺,以加快施工进度,降低工程成本。
4、遵循“以人为本、安全第一、质量百年大计”的原则。
严格按照施工规范、标准、安全操作规程及工程建设强制性标准,从制度、管理、方案、资源方面制定切实可行的措施,确保施工质量及安全。
5、快速施工原则,确保施工机械配套合理、先进,能满足机械化、专业化施工。
二、工程概况
本标段内共设计122.42m/4道圆管涵(Φ1.50m),66.0m/1道倒虹吸,钢筋混凝土圆管涵基础多处于黏土或粉土上,地基承载力较低,圆管涵多为跨灌溉沟渠或排水而设,圆管涵采用C25混凝土管基,C30混凝土管节,C20混凝土洞帽石,翼墙,跌水井。
M7.5浆砌片石洞口,隔水墙及铺砌。
洞身每隔4~6m设沉降缝一道,缝宽2cm,缝内填以沥青麻絮或不透水材料。
具体如下:
工程部位
细目名称
单位
工程量
滕AK0+102圆管涵
(1-1.5m)钢筋混凝土圆管涵
m
24
挖基土方
m3
874
涵管基础垫层
17