调试方案commissioning中英文双语版Word文档格式.docx
《调试方案commissioning中英文双语版Word文档格式.docx》由会员分享,可在线阅读,更多相关《调试方案commissioning中英文双语版Word文档格式.docx(31页珍藏版)》请在冰豆网上搜索。
1、调试具备条件见表3.14.1-1。
Table3.14.1-1Commissioningindispensableconditions
表3.14.1-1调试具备条件
No.序号
Nameofsystem
系统名称
Preparatoryworkbeforecommissioning
调试前的准备工作
1
Electricalsystem
电气系统
Installationofelectricalequipmentiscompleted.Layingofbridge,medium&
lowvoltagecablesandbusbariscompleted;
wiringofsecondarycontrolcablesisrightasperdrawings.Installationofpowerandlightingswitchboardiscompleted;
installationandwiringofpowerequipmentarecompleted;
appearancecheckisqualified.Wiringofvariouslampsiscompleted.Wiringofvariousswitchpanelsiscompleted.
电气设备安装完毕。
桥架及中、低压电缆、母线敷设完毕,二次控制电缆按图纸接线正确。
动力、照明配电盘安装完毕,动力设备安装、接线完毕,外观检查合格。
各种灯具接线完成,各种开关面板接线完毕。
2
HVACsystem
通风空调系统
Stablepowersupplyforairconditioningventilatingequipment,ductpurgingisqualified.Stablepowersupplyforairconditioningwatersystem,systemflushingisqualified;
hydraulicpressureofthesystemmeetsrequirements;
valveisturnedonandturnedoffnormally.
空调风系统设备供电稳定,风管吹扫合格。
空调水系统设备供电稳定,系统冲洗合格;
系统水压满足要求,阀门启闭正常。
3
Systemofplumbingaswellasfirefighting
给排水及
消防系统
Connectionofequipmentandpipelineiscorrect,itshallcheckcompletenessbeforeequipmentoperates,hydraulicpressuretestofpipesystemandcirculatingflushingworkofsystemhavebeencompleted.
设备和管道连接准确,设备运行前应进行完整性检查,管道系统水压试验与系统循环清洗工作已经完毕。
2.Organizationmeasuresofcommissioning
2、调试的组织措施
(1)Organizationchartofcommissioningisshowninthefigure3.14.1-2.
(1)调试的组织机构见图3.14.1-2。
Figure3.14.1-2Chartofcommissioningorganization
图3.14.1-2调试组织机构图
(2)Responsibilitiesofmainpersonnelforprojectcommissioningareshowninthetable3.14.1-2.
(2)项目调试主要人员职责见表3.14.1-2。
Table3.14.1-2Responsibilitiesofmainpersonnelforprojectcommissioning
表3.14.1-2项目调试主要人员职责
No.
序号
Post
职务
Actingpersonnel
担任人员
Responsibilities
职责
Teamleader
组长
Projectmanager
项目经理
Beresponsibleforestablishmentofcommissioningorganization,preparationofresourcesusedincommissioning,establishmentandimplementationofcommissioningworkingsystem,coordinationbetweenMEPandothersubcontractoratthestageofjointcommissioning.
负责调试机构的建立,调试需用资源的配备;
负责调试工作制度的建立实施,联动调试阶段机电与其他分包间的协调。
Deputyteamleader
副组长
Technicaldirectoroftheproject
项目技术
负责人
Beresponsibleforcompilationandsubmissionoforganizationcommissioningmethodstatement,coordinationandcommunicationwithrelatedpartiesaswellasmanagement,coordinationandcooperationinvariouscommissioningworkbetweentheOwnerABB,LendLeaseCompanyandrelevantdirectorofthesupervisionunitandallothersubcontractors;
analyzeandsummarizecommissioningresult.
负责组织调试方案的编制和报审,与外部相关方的协调与沟通,与业主ABB、联实公司及监理单位相关负责人和其他各分包单位各项调试工作的管理、协调与配合。
对调试结果进行分析和技术总结。
Groupleaderofalldisciplines
专业
小组长
Professionalengineerofcommissioning
调试专业
工程师
Beresponsibleforcompilationofcommissioningmethodstatementandstandardoperationproceduresforthisarea;
safetyandtechnicaldisclosureaboutcommissioningworkofthisarea;
makesolutionsfordifficultproblemsdiscoveredincommissioningintheareaofthisdiscipline;
ensuresafetyandreliabilityofinstrumentsusedinthecommissioningofthisarea;
implementthecommissioningscheduleofthearea,organizingtocollatecommissioningmaterialsandissuingcommissioningreport.
负责本区域调试方案和作业指导书的编制;
本专业本区域调试工作的安全、施工技术交底;
负责本专业本区域调试过程中发现疑难问题的解决方案;
负责本专业本区域调试所使用的仪器、仪表的安全和可靠性;
负责本专业本区域调试进度计划的落实,组织整理调试资料并出具调试报告。
4
Groupleaderofresourceguarantee
资源保障小组长
Materialguaranteepersonnel
物资保障人员
Beresponsibleforprovidingcommissioningmaterials.
负责提供调试所需物资。
5
Groupleaderofemergencyhandling
应急处理小组长
Professionalengineer
专业工程师
Beresponsibleforhandlingemergenciesoccurredintheprocessofcommissioning.
负责调试过程中出现应急情况的处理。
(3)Instrumentandequipmentusedincommissioningareshownin“5.2Guaranteemeasuresforinputofconstructionmachineryequipment”.
(3)调试所使用的仪器设备详见“7.2施工机械设备投入保证措施”。
3.Commissioningprocessisshowninthefigure3.14.1-3.
3、调试流程见图3.14.1-3。
Figure3.14.1-3Commissioningprocesschart
图3.14.1-3调试流程图
3.14.2Single-machinecommissioning
3.14.2单机调试
1.Maincontentsandrequirementsofsingle-machin