施工组织 1星.docx
《施工组织 1星.docx》由会员分享,可在线阅读,更多相关《施工组织 1星.docx(91页珍藏版)》请在冰豆网上搜索。
施工组织1星
目录
第一章工程概况···················································
(2)
第一节工程建设概况·········································
(2)
第二节工程特点·············································(4)
第二章施工质量目标与部署·········································(6)
第一节施工质量目标·········································(6)
第二节施工部署·············································(7)
第三节工程项目部署·········································(9)
第三章施工方案··················································(10)
第一节施工顺序············································(10)
第二节测量放线············································(10)
第三节降水工程方案········································(11)
第四节桩基工程············································(14)
第五节主体结构工程········································(16)
第六节屋面工程············································(24)
第七节装饰工程············································(25)
第八节门窗工程············································(26)
第九节天棚装饰及内外墙工程································(28)
第十节脚手架工程··········································(30)
第四章单位工程施工进度计划······································(32)
第五章单位工程施工平面图布置····································(33)
第一节施工现场条件··········································(33)
第二节施工临时用电布置······································(34)
第三节照明布置··············································(34)
第四节施工用水布置··········································(35)
第五节施工场地管理··········································(35)
第六章主要技术组织措施··········································(35)
第七章主要技术施工措施··········································(41)
第一节雨期施工措施··········································(41)
第二节夏季施工措施··········································(42)
第三节冬季施工措施··········································(42)
第四节工程施工进度··········································(44)
第五节文明施工管理··········································(44)
第六节质量管理制度与安全管理制度····························(44)
第八章主要经济指标及设计文件····································(47)
本施工组织设计编制依据及规范······································(54)
管理机构附图表····················································(55)
第一章工程概况
第一节工程建设概况
一、工程概况
本工程为省委党校经济适用房二期工程3号住宅楼
工程地点:
文一路浙江工程学院东侧,省委党校西南角
建筑面积:
2848.8M²工程造价:
813.26万
建筑高度:
建筑物主题最大标高为38.280M。
±0.000相当于绝对标高4.80M。
本建筑为一梯两户,电梯式公寓,共11层,22户。
由主楼和架空层两部分组成,地下设架空层(车库、机动车库、汽车库)层高为2.18M,主楼层高为2.8M,顶层为2.9M。
建筑结构:
异形柱框剪结构。
工程相对标高±0.000相当于绝对标高4.80M。
室内外高差700MM,盥洗室、卫生间、阳台、前室、阳台地面均比客厅低30MM,并向地漏找坡泛水。
建筑物形状如下图:
建设单位:
省委党校
施工单位:
浙江建工集团
设计单位:
浙江建设职业技术学院设计事务所
勘测单位:
浙江省综合勘测设计研究院
监理单位:
浙江省通利建设监理工程有限公司
质检单位:
杭州市质检站
安检单位:
杭州市安检站
二、建筑设计:
1、屋面:
a、平屋面做法:
EPS隔热砖,20厚1:
2水泥砂浆结合层,SBS防水层,30厚细石砼加浆找平,一布五涂“JS”防水层,20厚1:
2水泥砂浆找平层,膨胀珍珠岩2%找坡最薄处30厚钢筋砼屋面板。
b、斜屋面做法:
波形装饰瓦坡屋面做法详00SJ202
(一)。
2、墙体:
标高±0.000以下MU10粘土砖,M10防水砂浆砌筑;
标高±0.000以上MU10多孔砖(KP1)M5混合砂浆砌筑。
3、外立面:
地面:
20厚1:
2水泥砂浆地面,表面夯实,100厚碎石垫层,80厚C15砼;
踢脚:
150高水泥砂浆踢脚:
12厚1:
3水泥砂浆打底,8厚1:
2水泥砂浆抹面;
外墙:
面砖外墙面:
12厚1:
3水泥砂浆底,8厚1:
2水泥砂浆面粘贴面砖。
4、内装修:
卫生间:
(5厚1:
1水泥砂浆结合层,防滑地砖面)1800高10厚1:
3水泥砂浆粘贴,200×300瓷砖面;
楼面:
水磨石楼层,用10-15厚1:
3水泥砂浆打底,找平。
按设计图纸采用1:
1水泥砂浆固定分格条再采用1:
2-1:
2.5水泥石屑抹面,浇水养护一周后用磨石机磨光,再用草酸清洗,再打蜡保护;
内墙:
18厚1:
4水泥砂浆分层抹平,2厚水泥纸筋灰光面803白色涂料二度;
顶棚:
15厚1:
3水泥砂浆分层抹平,803白色涂料2度。
5、其它:
PVC雨水管详见水施,雨水口用铸铁保护,明露金属屋面:
防锈漆二度,银粉漆二度;
明露金属面为防锈漆二度,银粉漆二度;
黑色艺术铁花装饰件;
木材防腐:
水柏油二度罩面;
屋面采用有组织排水,平屋面采用建筑找坡I=2%;
阳台、雨蓬、女儿墙压顶;
凡图中门窗未注明者均逢中、柱边或距墙边120mm安装,所有落地窗内设1100高栏杆。
三、结构设计:
本工程±0.000相当于绝对标高4.800M。
本工程为乙类建筑,抗震设防烈度为6级,安全等级为2级,设计使用年限为50年,耐火等级为2级,结构抗震设防类别为丙类。
梁柱墙抗震等级为3级,采用钢筋砼框架剪力墙结构,场地土类别为3级。
1、主体:
主体为异形柱框剪结构
(1)、各标高段所用混凝土强度等级如下表:
混凝土强度等级
所用部位
C40
2.150标高以下
C35
2.150-7.750标高之间
C30
7.750-16.150标高之间
C25
16.150标高以上
(2)、钢筋采用HPB235和HRB335(分别用Φ和ø表示)
钢筋锚固长度及塔接长度见下表:
砼等级
C35
C30
C25
锚固长度
搭接长度
锚固长度
搭接长度
锚固长度
搭接长度
HPB235
30d
35d
25d
30d
25d
30d
HRB335
35d
40d
35d
40d
30d
35d
注:
不同直径的钢筋的搭接以直径最小的钢筋计算搭接长度
(3)、箍筋末端做135度的弯钩,弯钩平直长度为10d(d为箍筋直径)
(4)、接头区段内受拉钢筋接头面积的允许百分率:
当为绑扎搭接时为25%,焊接时为50%。
(5)、焊条:
E43xx型—用于HPB235级钢筋
E50xx型—用于HRB335级钢筋
(6)、砖墙:
标高±0.000以下Mu10的粘土砖
标高±0.000以上Mu10多孔砖(KP1)
(7)、砂浆:
标高±0.000以下M10防水水泥砂浆
标高±0.000以上M5混合砂浆
(8)、门窗过梁通过处,均设过梁或过梁板。
(9)、沉降观测点位置详见结施—4,沉降观测需在观测点设置后时进行,以后每上一层观测一次。
(10)、基础:
①本工程桩基说明详见桩位平面图,基础混凝土采用C40级,承台下设300厚嵌桩石,基础垫层采用50厚碎石上100厚C10素混凝土,砖胎膜用MU7.5砖,M7.5水泥砂浆砌筑;
②地下室混凝土施工要求连续浇捣,所有穿墙管都必须带止水钢板;
③基础施工时必须结合设备图预留(预埋)孔洞(埋件),严禁后凿;
④根据实际情况作好地下室围护工作,确保邻近建筑物及道路的安全和施工安全;
⑤基础底板上,下皮主筋应用短钢筋绑扎支撑,不得用预制块支撑,地梁及底板的下部钢筋在跨中搭接,上部钢筋在支座搭接;
⑥地下室外墙、基础、地梁及底板混凝土抗渗等级为S6;
⑦地下室外墙、地梁及底板混凝土水泥中渗8-10%UEA微膨胀剂。
三、设备安装设计详见《设备安装施工组织设计》
第二节工程特点
一、工程特点:
困施工场地受到一定的限制,施工工作面较狭小。
1、打桩工程:
地质情况详见地质勘测报告。
打桩前要确定桩位和打桩顺序,打桩过程中要注意打桩的流水方向,防止因打桩挤土而使桩身位移和破坏,以至出现承载力不足及断桩现象,具体详见打桩专项方案。
2、主体工程:
本工程为框架剪力墙结构,在施工过程中,特别要控制模板、混凝土施工、钢筋工程的质量,确保模板接缝密实,有足够的强度、刚度、保证不变形,不炸模。
混凝土浇捣密实、不漏振、不离析,保证混凝土施工质量。
钢筋工程要保证原材料、钢筋加工、钢筋连接、钢筋安装的质量要求,使构件的形状、尺寸不受偏差。
以确保优质结构目标实现。
3、装饰工程:
外墙装饰主要采用外墙涂料(AC—97弹性涂料),内墙面采用“803”白色涂料,装饰工程要保证墙体表面平整光洁,阴阳角垂直、不起壳、不起鼓、不开裂,要特别重视大厅、楼梯等重点部位的施工质量。
确保整个工程显得美观、大方。
4、屋面工程:
屋面防水用SBS改性沥青柔性防水,沥青铺贴采用热熔法施工中的滚铺法进行施工。
要做好SBS改性沥青接头处的质量及确保各个细部的施工工艺和质量(如檐口、泛水等等)。
5、测量方法:
本工程垂直度和轴线控制用经纬仪,标高控制采用水准仪。
二、工程土质特点:
本次完成的勘探孔最大深度56.2米.经勘察查明,该建筑场地中上部主要以第四系沉积为主,其覆盖层厚度达35.-37.0M左右,主要为全新统(Q4),上更新统(Q3)的海相沉积层;其下伏基岩为中生代侏罗系(J)紫色,浅紫色安山玢岩,根据地层的成因和工程特性划分为12个工程地质层,现将特征相似的地层归入6个地层组,自上而下为了,①杂填土,素填土;②粉质粘土;③淤泥质粉质粘土;④粉质粘土;⑤含粘性土砾石,含粘性土卵石;⑥全风化,强风化,中风化安山玢岩.具体特征分述如下:
①-1杂填土:
颜色较杂,组成物质主要有砖瓦砾,石块,腐植物等建筑垃圾和少量生活垃圾.最大砖块,石块直径大于10CM,一般在5-10CM左右,含量在20%-30%,其中充填着砂砾,粘性土等.松散,易坍塌,透水性好,很不均匀.部分地段10CM砼地坪和块石基础,全场分布,层厚0.5-1.5米左右.
①-2素填土:
灰色,黄褐色,软塑为主(部分地段为流塑状态),组成物质主要不粘性土著居民,粉性土,占80%左右.含腐植物,有机质及少量砖瓦屑,砾砂,占20%左右,土质不均匀.主要分布在3号,4号楼附近,层厚1.0米左右,Z13号孔附近深达4.3米.
②粉质粘土:
黄褐色,灰黄色,可塑,局部软塑,含氧化锰斑点,云母,夹薄层粉土,具微层理.
③-1淤泥质粉质粘土:
灰色,流塑,饱和,含有机质,腐植物根茎,云母,局部分布为淤泥质粘土,全场分布,层厚3.0-4.0米左右.
③-2淤泥质粉质粘土:
灰色,深厚感情灰色,流塑,饱和,含有机质,腐植物,云母,偶见僵结石数块,直径10-20MM,全场分布,层厚15.0M左右.
③-3淤泥质粉质粘土:
灰色,黑灰色,流塑,饱和,含大量有机质,云母,该层层底1.0米左右部分段含少量腐质植物叶片及多量碎贝壳,全场分布,层厚8.0米左右.
④粉质粘土:
黄灰,灰色,灰褐色,软塑-可塑,含有机质,云母,微层理.该层底部2.0米左右,含15%左右粉砂,中砂,全场分布,层厚6.0-7.0左右.
⑤-1含粘性土砾砂:
灰色,灰褐色,稍密-中密,含30%左右的粘性土,砾砂55%左右,卵石15%左右,直径20-40MM,部分地段缺失,层厚0.5-1.0米左右.钻进时稍有跳感,进尺较快.
⑤-2含粘性土卵石:
灰色,灰褐色,中密,含30%左右的粘性土,卵石40%左右,直径20-50MM,砾砂30%左右,厚度不大.仅见Z13,Z16,Z17号钻孔.钻进时略有跳动,进尺一般.
⑥-1全风化安山玢岩:
紫红色,紫色,局部灰褐色等,岩石已风化成土状或砂粒状,母岩结构构造已不清晰,矿物成份大部分已风化,局部夹强风化岩块.手易捏碎,遇水后即软化,钻进速度较快.层面起伏变化不大,但层厚变化较大(0-7.2M),详见剖面图.
⑥-2强风化安山玢岩:
紫红色,紫色,灰褐色等,岩石已风化成碎块状,母岩结构构造已不甚清晰,风化裂隙发育,局部含中风化夹层.锤击声响较沉闷,易击碎,用手可折断,作重型动探时钻杆有弹跳感,钻进速度一般.岩石遇水易软化,层面起伏及厚度变化较大(0.3-7.0M),详见剖面图.
⑥-3中风化安山玢岩:
紫红色,浅紫色,紫灰色等,岩石结构构造较清晰,岩芯呈短柱状,一般长度为100-150MM,场地北面岩芯较完整,中部和南面岩芯较破碎,呈块状,部分风化裂隙较发育,但岩石硬度较高,锤击不易碎,锤击声较清脆,颜色新鲜。
钻进速度稍慢,遇岩石破碎钻机跳动较大。
该层层面起伏变化特别大,层面埋深在35.70-51.0M之间.高差达15.30米.
三、现场条件:
施工现场将在2004年3月15日开工,施工用电、用水均已布置完成(由浙江工业大学校区内的供电、供水管网提供),施工用电为。
施工用水的供水口径为D,施工现场的道路铺设完毕。
材料、人员、机械均已进场,已达到施工开工条件。
四、工程工期:
本工程将于2004年3月15日开工,至2004年11月30日全部完工,为保证工期要求,在施工中各施工班组要搞好协调施工,创造足够的工作面和充分的时间,在田间允许的情况下尽可能的缩短工期。
第二章施工质量目标与部署
第一节施工质量目标
一、工期目标:
1.工期目标:
本工程总工期定为260天,其中桩基础工程占用工期40天,主体工程占用工期100天,装饰工程占用工期110天,室外工程及其它占10天。
根据招标文件要求,确保实际施工工期在国家定额工期的基础上提前20%,为如期兑现上述工期目标,我们拟采取以下措施:
准备边施工,抢开工时间;
短桩基施工时间:
拟一台桩机施工,日夜三班不停;
尽量利用塔吊综合施工的优势,加快施工进度;
尽量使用商品砼,用泵车浇灌,或用砼输送泵送浆,节约现场用工,加快施工速度。
二、工程质量目标:
质量是企业的生命,我们一贯坚持“质量第一”的原则。
在该工程上,我们将通过自身的质保体系,严格的管理措施和技术工人的精心操作,在用样板开路,严格“三检”的基础上,虚心听取建设单位、设计单位、工程监理单位,质监部门的意见,并及时整改。
确保优良工程,以答谢建设单位及各级领导对我们的信任与支持。
我们深知质量是干出来的也是管出来的。
优秀的工程必须由优秀的队伍来创造。
因此,要实现上述目标必须选好队伍,由有丰富施工经验的施工员组织施工,配技术精、作风硬、责任心强的技术工人操作,配有丰富实践经验的专业技术人员跟班检查与指导,并做好班前交底、现场监督与检查,不好就返,一定把创优工作落到实处。
三、安全目标:
在工程中要确保安全生产、文明施工,争取达到市级“安全、文明标化”工地,争创钱江杯,树立“安全第一,预防为主”的总方针,遵守“管生产必须管安全,谁主管谁负责”的原则。
四、施工组织与安排:
(1)、本工程要坚持“先地下后地上”的原则,避免施工中重复挖填土方,基础施工阶段工程图纸内设计的所有进出地下管或套管,均应配套完成,上±0.00以上工程时,地下室周边回填土与大楼周围场平土均应达到地面垫层底标高,或场外散水道路垫层底标高,余土均运出场外,并挖好建筑物四周排水沟。
主要干道及砂石堆场做好硬地,给雨天施工创造条件,并满足杭州市城市施工环保要求。
(2)、基础阶段,应先做基坑围护,围护方案拟采用土钉墙围护方案。
土钉墙围护结构强度合格及打桩完成后即可开挖。
由1轴向9轴分层按序开挖,开挖时要注意由于受力不均匀使桩位偏移等现象。
(3)、结构阶段:
主体施工为分段流水施工。
组织木工、钢筋工、砼工分段流水。
(4)、装修阶段:
同结构阶段流水施工。
第二节施工部署
一、施工准备工作:
1.调查研究,收集有关资料,如现场地质勘察报告,水文气象,收集当地给排水,供电等资料及地方性材料的供应能力,质量、价格、运输等。
2.技术资料的准备:
熟悉与会审图纸并编制施工图预算和施工组织设计。
3.现场准备:
清除障碍物,三通一平,测量放线,搭设临时设施。
4.物资准备:
根据施工组织设计的采购材料并合理安排进场,选择施工机具和模板脚手架。
5.施工现场人员准备:
组建项目管理机构,确定各施工班组。
6.作好冬雨季施工准备。
7、开工前技术员、翻样员、预算员、施工员、班组长等应熟悉图纸,组织技术交底,提出加工定货单,编出施工预算与工料分析大表。
8、放线前根据场地自然标高与建筑物室外标高的情况清平场地,清除障碍物,三通一平,测量纺线,搭设临时设施。
9、根据设计总平面图,尽量利用永久道路路床修通现场临时道路,实现场地硬化,保证下雨施工不泥泞,利于施工。
二、施工总体部署:
由于工程项目较大,项目部应配备生产、技术、质量、安全、预算、材料、财务等职能人员,在项目经理的协调下负责对施工准备、技术管理、生产组织、质量监控、文明施工、材料供应到竣工验收和工程结算等方面的全过程管理。
在实际施工中,我们为加强管理,将全方位跟踪对进度、劳力、工资、材料、资金监控,及时调整施工各要素,优化进度安排,找出主要矛盾线,确保施工进度计划的实现。
同时还要给质检人员配备先进的检测工具,使计量正确,问题找准,定把质量控制好。
我们有信心通过完整的管理体系,忠于职守的工作态度,充分完善的后勤保障,并调配技术过硬的班组,参加施工作业,采用ISO9000管理模式进行项目法施工。
在保证质量的前提下尽量缩短工期,争创“钱江杯”。
三、劳动力配备
为了保质保量地完成任务,我们决心加大劳力、机具的投入量,配1台塔吊,1台客货梯,全套钢筋、木工加工机械,挑选作风扎实,技术过硬,能吃大苦耐大劳,并有丰富施工经验的自有施工队伍施工,除打桩、基坑围护、机械挖土、运土需找专业队伍协助或租借他们的机械外,其他一律由公司内部调剂解决,到时由项目部按照施工进度计划,依照流水施工,交叉作业的要求编出用工计划,公司即按计划调配。
根据该工程的具体情况,其劳力安排大体如下:
1、结构施工期间的劳动力计划
序号
工种
计划人数
进场时间
备注
1
普工
100
2004-3
劳动力根据工程量大小及施工进度具体安排进场
2
钢筋工
40
2004-3
3
木工
50
2004-3
4
混凝土工
20
2004-4
5
架子工
15
2004-4
6
防水工
10
2004-3
7
塔吊司机
2
2004-4
8
信号工
2
2004-3
9
瓦工
40
2004-3
10
电气焊工
3
2004-4
11
水暖工
10
2004-4
12
电工
8
2004-3
2、装饰装修施工期间劳动力计划
序号
工种
计划人数
进场时间
备注
1
抹灰工
50
2004-8
劳动力根据工程量大小及施工进度具体安排进场
2
油漆工
30
2004-8
3
木工
10
2004-8
4
防水工
10
2004-8
5
电工
20
2004-8
6
水暖工
35
2004-8
7
电梯工
5
2004-10
四、临时设施规划:
临时设施
面积(m2)
结构形式
办公用房+会议室
15×5+75=110
一层活动用房
职工宿舍
500×2=1000
二层活动用房
工具间、仓库
80
一层活动用房
食堂
120
一层砌筑
浴室、厕所
50
一层砌筑
传达室
10
一层砌筑
临时设施
面积(m2)
结构形式
钢筋加工棚
120
工棚
木工加工棚
80
工棚
五、施工机械配备:
因该项目用商品砼,现场只设砂浆搅拌机和备用砼拌合机,用塔吊客货梯井架运灰,砖,吊钢筋、模板等,砼用泵车,或砼输送泵浇筑,钢筋、模板集中配制。
设备配置详见附表。
序号
名称
规格
单位
数量
电容量
1
塔吊
STMMAGTI187C2.5
台
1
116.2KW
2
振动棒
Φ50
台
8
2.2KW×8
3
振动棒
Φ30
台
3
2.2KW×3
4
平板振捣器
BL11
台
2
1.5KW×2
5
混凝土泵
HBT-60
台
1
55KW
6
电焊机
BX1-50-7
台
4
38.6KVA×4
7
钢筋切割机
CQ-50
台
1
7.OKW
8
弯曲机
CN-50
台
1
5.5KW
9
电锯
MJ500
台
1
7.5KW
10
螺纹机
台
1
45KW
11
电刨
MB-104C
台
1
4.5KW
12
冷挤压机
台
1
5KW
13
蛙式打夯机
H400
台
2
2.8KW×2
14
钢筋调直机
GT4-8
台
1
5.5KW
15
潜水