1、施工现场协调管理英文V. Construction Site Coordination Management1.Construction General Layout Plan CoordinationBased on construction deployment and milestone delivery requirements in various phases, General Contractor is in charge of formulating overall plan for general layout plan and deliver technical discl
2、osure to subcontractors for carrying out dynamic management.General contractor is responsible for dispatching road, temporary storage yard, fixed storage yard within construction site unitedly。The subcontractor shall submit “temporary access road or storage yard application sheet to General contract
3、or as per production requirements at each stage for approval by procedures。The subcontractor shall submit “Use of existing fixed storage yard application sheet” (Sheet 72) to General Contractor Production Coordination Department as per production requirements at each stage for approval。The subcontra
4、ctors are responsible for standardized management and maintenance of public facilities, surrounding roads within fixed storage yard or temporary site they used, as well as to cater for General Contractors standardized management requirements.2.Temporary Water and Power Supply CoordinationGeneral Con
5、tractor is in charge of overall planning and implementation for temporary water and power supply deployment and deliver technical disclosure to subcontractors.The subcontractors are in charge of configuring full-time temporary water and power supply managerial personnel, who should submit to General
6、 Contractor “Subcontracting use power general schedule within stipulated period, as well as to sign “ Temporary water and power use management agreement” with General Contractor within one week。The subcontractor shall submit “Use of temporary power supply application” to General Contractor Productio
7、n Coordination Department as per production requirements at each stage for approval.The subcontractors are in charge of safety management of temporary water and power use and accept daily inspection from General Contractor, as well as rectify the discovered problems during inspection and make reply
8、immediately.3.Temporary Facilities CoordinationGeneral Contractor is in charge of overall planning and implementation for temporary facilities, formulating usage allocation scheme and deliver technical disclosure to subcontractors。The subcontractor shall submit “Use of temporary facilities (office,
9、living) application sheet” to General Contractor Production Coordination Department as per production requirements at each stage for approval。The subcontractors are in charge of maintain and manage temporary facilities use and accept daily inspection from General Contractor, as well as rectify the d
10、iscovered problems during inspection and make reply immediately。The subcontractors are in charge of applying overall acceptance and handover to General Contractor after temporary facilities usage completed.4.Material and Equipment Mobilization and Demobilization Coordination The subcontractors shall
11、 submit detailed material, equipment mobilization application schedule in accordance with General Contractors construction progress to confirm material, equipment name, specification, model and mobilization time。The subcontractors are in charge of material mobilization and demobilization, who shall
12、prepare documents which include, but not limited to, material type, transportation mode, quality assurance, etc. as well as submit “Material/equipment mobilization and demobilization application sheet” to General Contractor Production Coordination Department for approval.The subcontractors are in ch
13、arge of abide by General Contractors site material and equipment management system, pile up mobilized material and equipment in good order, accept daily inspection from General Contractor, as well as rectify the discovered problems during inspection and make reply immediately.5.Vertical Transportati
14、on CoordinationGeneral Contractor is in charge of overall planning and implementation for vertical transportation equipment, formulating project vertical transportation scheme and deliver technical disclosure to subcontractors。The subcontractors shall submit “ Subcontract vertical transportation equ
15、ipment use schedule sheet to General Contractor for approval.The subcontractor shall submit “Use of vertical transportation application sheet” to General Contractor Production Coordination Department every day as per daily construction demand for approval.General Contractor is in charge of planning
16、all subcontractors vertical transportation equipment use situation as a whole and formulating and public “Daily use distribution sheet of vertical transportation equipment” , as well as coordinate and resolve emergent problems among subcontractors for using vertical transportation equipment.The subc
17、ontractors are in charge of configure full-time staff to manage vertical transportation within subcontractors and cooperate General Contractor to coordinate and resolve emergent problems among subcontractors for using vertical transportation equipment。General Contractor is in charge of arranging ver
18、tical transportation equipments keep and maintenance, attachment, jacking time reasonably and give to publicity timely。6.Public Operation Platform CoordinationGeneral Contractor is in charge of formulating overall plan for public operation platform and deliver technical disclosure to subcontractors
19、in accordance with contract organization or entrust subcontractors to erect, dismantle and maintain public operation platform。The subcontractor shall submit “Dismantle of public operation platform application sheet” to General Contractor Production Coordination Department for approval due to the nee
20、d of altering, dismantling platform, dismantle shall be conducted only after obtained the approval, which could be used only after inspection and acceptance of dismantling and alteration。General Contractor is in charge of supervising public operation platforms use condition, handling misuse timely.7
21、.Public Security Protection CoordinationGeneral Contractor is in charge of unifying public security standard in accordance with contract organization or entrust subcontractors to fit with public security protection facilities, as well as deliver technical disclosure to subcontractors。General Contrac
22、tor is in charge of public security protection and supervision within public area, the subcontractors are responsible for security protection and supervision within working face。The subcontractor shall submit “Dismantle of public security protection application sheet” to General Contractor Productio
23、n Coordination Department for approval due to the need of altering, dismantling safety protection, dismantle shall be conducted only after obtained the approval, which could be used only after inspection and acceptance of dismantling and alteration.General Contractor is in charge of managing securit
24、y protection in construction site as a whole, as well as execute supervision and acceptance works for safety protection dismantling and alteration.8.Site Elevation Axis CoordinationGeneral Contractor is responsible for preparing overall survey control scheme, establishing Level 1 plane and vertical
25、control network, main axis, elevation control networks within site area, as well as make identification and carry out daily maintenance, meanwhile deliver control point and control axis disclosure to subcontractors, finish handover works。The subcontractors are in charge of configuring qualified surv
26、eyors, surveying instrument, calibrate survey instrument periodically and submit to General Contractor for register.The subcontractors are in charge of measuring pass, setting out, measurement testing, deformation monitoring, etc。9.Site Construction Interfaces CoordinationGeneral Contractor is in ch
27、arge of organize subcontractors to identify all interfaces, form “Interface matrix table, “Interface division schematic diagram。The subcontractors are in charge of familiarizing with construction contract, in case of requiring other subcontractors cooperation matters, draft a list and submit General
28、 Contractor for register.General Contractor is in charge of formulating subcontractors working face transfer plan as per progress programme, as well as organize related parties to transfer working faces as scheduled。As receiver of working faces, the subcontractors are in charge of preparing critical
29、 areas transfer list, under General Contractors management, make three tier transfer check and form check record.As receiver of working faces, the subcontractors are in charge of completing the remained works and rectifying the defected works to achieve transfer requirements as scheduled pursuant to
30、 “Key areas working face transfer list” requirements provided by the receiver。VI。 Public Resources Management10.Management Key Points at Each StageManagement ProcessManagement Key PointsPlane management(1) Layout planning and deployment(2) Site and road approval(3) Daily management of traffic organi
31、zation and civilized construction Temporary water, power supply management(1) Planning and total quantity control for temporary water and power supply(2) Management agreement signing for temporary water and power supply(3) Temporary water and power supply approval(4) Management responsibility divisi
32、on and daily maintenanceTemporary facilities management(1) Implementation of temporary facilities planning and deployment pursuant to contract type(2) Approval and acceptance of temporarily used land and facilities(3) Daily supervision of temporary facilities(4) Transfer and counter transfer of temporary facilitiesVertical transportation equipment management(1) Planning and daily maintenance of vertical transportation equipment(2) Supervision of subcontractors vertical transportation equipment usage plan(3) Daily approval and display to p