V.ConstructionSiteCoordinationManagement
1.ConstructionGeneralLayoutPlanCoordination
Basedonconstructiondeploymentandmilestonedeliveryrequirementsinvariousphases,GeneralContractorisinchargeofformulatingoverallplanforgenerallayoutplananddelivertechnicaldisclosuretosubcontractorsforcarryingoutdynamicmanagement.
Generalcontractorisresponsiblefordispatchingroad,temporarystorageyard,fixedstorageyardwithinconstructionsiteunitedly。
Thesubcontractorshallsubmit“temporaryaccessroadorstorageyardapplicationsheet’toGeneralcontractorasperproductionrequirementsateachstageforapprovalbyprocedures。
Thesubcontractorshallsubmit“Useofexistingfixedstorageyardapplicationsheet”(Sheet7—2)toGeneralContractorProductionCoordinationDepartmentasperproductionrequirementsateachstageforapproval。
Thesubcontractorsareresponsibleforstandardizedmanagementandmaintenanceofpublicfacilities,surroundingroadswithinfixedstorageyardortemporarysitetheyused,aswellastocaterforGeneralContractor’sstandardizedmanagementrequirements.
2.TemporaryWaterandPowerSupplyCoordination
GeneralContractorisinchargeofoverallplanningandimplementationfortemporarywaterandpowersupplydeploymentanddelivertechnicaldisclosuretosubcontractors.
Thesubcontractorsareinchargeofconfiguringfull-timetemporarywaterandpowersupplymanagerialpersonnel,whoshouldsubmittoGeneralContractor“Subcontractingusepowergeneralschedule"withinstipulatedperiod,aswellastosign“Temporarywaterandpowerusemanagementagreement”withGeneralContractorwithinoneweek。
Thesubcontractorshallsubmit“Useoftemporarypowersupplyapplication”toGeneralContractorProductionCoordinationDepartmentasperproductionrequirementsateachstageforapproval.
ThesubcontractorsareinchargeofsafetymanagementoftemporarywaterandpoweruseandacceptdailyinspectionfromGeneralContractor,aswellasrectifythediscoveredproblemsduringinspectionandmakereplyimmediately.
3.TemporaryFacilitiesCoordination
GeneralContractorisinchargeofoverallplanningandimplementationfortemporaryfacilities,formulatingusageallocationschemeanddelivertechnicaldisclosuretosubcontractors。
Thesubcontractorshallsubmit“Useoftemporaryfacilities(office,living)applicationsheet”toGeneralContractorProductionCoordinationDepartmentasperproductionrequirementsateachstageforapproval。
ThesubcontractorsareinchargeofmaintainandmanagetemporaryfacilitiesuseandacceptdailyinspectionfromGeneralContractor,aswellasrectifythediscoveredproblemsduringinspectionandmakereplyimmediately。
ThesubcontractorsareinchargeofapplyingoverallacceptanceandhandovertoGeneralContractoraftertemporaryfacilitiesusagecompleted.
4.MaterialandEquipmentMobilizationandDemobilizationCoordination
Thesubcontractorsshallsubmitdetailedmaterial,equipmentmobilizationapplicationscheduleinaccordancewithGeneralContractor’sconstructionprogresstoconfirmmaterial,equipmentname,specification,modelandmobilizationtime。
Thesubcontractorsareinchargeofmaterialmobilizationanddemobilization,whoshallpreparedocumentswhichinclude,butnotlimitedto,materialtype,transportationmode,qualityassurance,etc.aswellassubmit“Material/equipmentmobilizationanddemobilizationapplicationsheet”toGeneralContractorProductionCoordinationDepartmentforapproval.
ThesubcontractorsareinchargeofabidebyGeneralContractor'ssitematerialandequipmentmanagementsystem,pileupmobilizedmaterialandequipmentingoodorder,acceptdailyinspectionfromGeneralContractor,aswellasrectifythediscoveredproblemsduringinspectionandmakereplyimmediately.
5.VerticalTransportationCoordination
GeneralContractorisinchargeofoverallplanningandimplementationforverticaltransportationequipment,formulatingprojectverticaltransportationschemeanddelivertechnicaldisclosuretosubcontractors。
Thesubcontractorsshallsubmit“Subcontractverticaltransportationequipmentuseschedulesheet"toGeneralContractorforapproval.
Thesubcontractorshallsubmit“Useofverticaltransportationapplicationsheet”toGeneralContractorProductionCoordinationDepartmenteverydayasperdailyconstructiondemandforapproval.
GeneralContractorisinchargeofplanningallsubcontractors’verticaltransportationequipmentusesituationasawholeandformulatingandpublic“Dailyusedistributionsheetofverticaltransportationequipment”,aswellascoordinateandresolveemergentproblemsamongsubcontractorsforusingverticaltransportationequipment.
Thesubcontractorsareinchargeofconfigurefull-timestafftomanageverticaltransportationwithinsubcontractorsandcooperateGeneralContractortocoordinateandresolveemergentproblemsamongsubcontractorsforusingverticaltransportationequipment。
GeneralContractorisinchargeofarrangingverticaltransportationequipment’skeepandmaintenance,attachment,jackingtimereasonablyandgivetopublicitytimely。
6.PublicOperationPlatformCoordination
GeneralContractorisinchargeofformulatingoverallplanforpublicoperationplatformanddelivertechnicaldisclosuretosubcontractorsinaccordancewithcontractorganizationorentrustsubcontractorstoerect,dismantleandmaintainpublicoperationplatform。
Thesubcontractorshallsubmit“Dismantleofpublicoperationplatformapplicationsheet”toGeneralContractorProductionCoordinationDepartmentforapprovalduetotheneedofaltering,dismantlingplatform,dismantleshallbeconductedonlyafterobtainedtheapproval,whichcouldbeusedonlyafterinspectionandacceptanceofdismantlingandalteration。
GeneralContractorisinchargeofsupervisingpublicoperationplatform’susecondition,handlingmisusetimely.
7.PublicSecurityProtectionCoordination
GeneralContractorisinchargeofunifyingpublicsecuritystandardinaccordancewithcontractorganizationorentrustsubcontractorstofitwithpublicsecurityprotectionfacilities,aswellasdelivertechnicaldisclosuretosubcontractors。
GeneralContractorisinchargeofpublicsecurityprotectionandsupervisionwithinpublicarea,thesubcontractorsareresponsibleforsecurityprotectionandsupervisionwithinworkingface。
Thesubcontractorshallsubmit“Dismantleofpublicsecurityprotectionapplicationsheet”toGeneralContractorProductionCoordinationDepartmentforapprovalduetotheneedofaltering,dismantlingsafetyprotection,dismantleshallbeconductedonlyafterobtainedtheapproval,whichcouldbeusedonlyafterinspectionandacceptanceofdismantlingandalteration.
GeneralContractorisinchargeofmanagingsecurityprotectioninconstructionsiteasawhole,aswellasexecutesupervisionandacceptanceworksforsafetyprotectiondismantlingandalteration.
8.SiteElevationAxisCoordination
GeneralContractorisresponsibleforpreparingoverallsurveycontrolscheme,establishingLevel1planeandverticalcontrolnetwork,mainaxis,elevationcontrolnetworkswithinsitearea,aswellasmakeidentificationandcarryoutdailymaintenance,meanwhiledelivercontrolpointandcontrolaxisdisclosuretosubcontractors,finishhandoverworks。
Thesubcontractorsareinchargeofconfiguringqualifiedsurveyors,surveyinginstrument,calibratesurveyinstrumentperiodicallyandsubmittoGeneralContractorforregister.
Thesubcontractorsareinchargeofmeasuringpass,settingout,measurementtesting,deformationmonitoring,etc。
9.SiteConstructionInterfacesCoordination
GeneralContractorisinchargeoforganizesubcontractorstoidentifyallinterfaces,form“Interfacematrixtable",“Interfacedivisionschematicdiagram"。
Thesubcontractorsareinchargeoffamiliarizingwithconstructioncontract,incaseofrequiringothersubcontractors’cooperationmatters,draftalistandsubmitGeneralContractorforregister.
GeneralContractorisinchargeofformulatingsubcontractors’workingfacetransferplanasperprogressprogramme,aswellasorganizerelatedpartiestotransferworkingfacesasscheduled。
Asreceiverofworkingfaces,thesubcontractorsareinchargeofpreparingcriticalarea'stransferlist,underGeneralContractor’smanagement,makethreetiertransfercheckandformcheckrecord.
Asreceiverofworkingfaces,thesubcontractorsareinchargeofcompletingtheremainedworksandrectifyingthedefectedworkstoachievetransferrequirementsasscheduledpursuantto“Keyarea’sworkingfacetransferlist”requirementsprovidedbythereceiver。
VI。
PublicResourcesManagement
10.ManagementKeyPointsatEachStage
ManagementProcess
ManagementKeyPoints
Planemanagement
(1)Layoutplanninganddeployment
(2)Siteandroadapproval
(3)Dailymanagementoftrafficorganizationandcivilizedconstruction
Temporarywater,powersupplymanagement
(1)Planningandtotalquantitycontrolfortemporarywaterandpowersupply
(2)Managementagreementsigningfortemporarywaterandpowersupply
(3)Temporarywaterandpowersupplyapproval
(4)Managementresponsibilitydivisionanddailymaintenance
Temporaryfacilitiesmanagement
(1)Implementationoftemporaryfacilitiesplanninganddeploymentpursuanttocontracttype
(2)Approvalandacceptanceoftemporarilyusedlandandfacilities
(3)Dailysupervisionoftemporaryfacilities
(4)Transferandcountertransferoftemporaryfacilities
Verticaltransportationequipmentmanagement
(1)Planninganddailymaintenanceofverticaltransportationequipment
(2)Supervisionofsubcontractors’verticaltransportationequipmentusageplan
(3)Dailyapprovalanddisplaytop