户外断路器负荷开关安装作业指导书
第8部分:
配网工程
户外断路器、负荷开关安装作业指导书
编码:
HWDQSB-01
目次
1适用范围······················································································································································213
2编写依据······················································································································································213
3作业流程图··················································································································································213
4安全风险辨析与预控··································································································································213
5作业准备························································································································································13
6作业方法··························································································································································6
7质量控制措施及检验标准······························································································································9
1适用范围
1.1电压等级
35kV及以下配网工程。
1.2电气类别
配网工程中户外SF6断路器和真空断路器及负荷开关的安装。
2编写依据
表2编写依据
序号
引用资料名称
1
GB50173—1992《电气装置安装工程35kV及以下架空电力线路施工及验收规范》
2
Q/CSG11105—2008《南方电网工程施工工艺控制规范》
3
《中国南方电网有限责任公司基建工程质量控制作业标准(WHS)》
3作业流程图
4安全风险辨析与预控
图3作业流程图
4.1户外断路器、负荷开关安装作业前,施工项目部根据该项目作业任务、施工条件,参照《电网建设
施工安全基准风险指南》(下简称《指南》)开展针对性安全风险评估工作,形成该任务的风险分析表。
4.2按《指南》中与户外断路器、负荷开关安装作业相关联的《电网建设安全施工作业票》(编码:
HWDQSB-01-01/01),结合现场实际情况进行差异化分析,确定风险等级,现场技术员填写安全施工作业票,安全员审核,施工负责人签发。
4.3施工负责人核对风险控制措施,并在日站班会上对全体作业人员进行安全交底,接受交底的作业人员负责将安全措施落实到各作业任务和步骤中。
4.4安全施工作业票由施工负责人现场持有,工作内容、地点不变时可连续使用10天,超过10天须
重新办理作业票,在工作完成后上交项目部保存备查。
表4.1作业任务安全基准风险指南
序号
危害名称
风险种类
风险等级
风险控制措施
1
隔离开关、闸刀型开关处在断开位置时即开始搬运
打击
低风险
隔离开关、闸刀型开关应处在合闸位置才可以开始搬运
2
不按规定使用或选用不合格登高工具
坠落
特高的风险
按规定使用安全、合格的登高用具
3
高空作业不按规定佩戴安全带
坠落
特高的风险
使用双保险安全带
4
不用绳索传递工具、物料及不使用工具袋
打击
中等风险
用绳索传递工器具、材料,现场人员必须戴安全帽
5
用瓷套管作为受力点搬动开关
设备破损
中等风险
使用开关固定金属受力点搬运
6
线缆出入口封堵措施不足
设备停运
高风险
线缆敷设进入设备后及时对线缆进出口进行封堵,并检查其可靠性
5作业准备
5.1作业前施工条件
表5.1作业前施工条件
序号
项目
内容
确认人
说明
1
任务单
根据本单位实际设置内容(包含本项工作)
本工序施工负责人
经审批
2
图纸
设备变更单、设计图纸
本工序施工负责人
经审批
3
预算材料表
含主、辅材
本工序施工负责人
经审批
4
施工方案
施工措施、安全技术交底(项目部级)
本工序施工负责人
经审批
5
相关证照
根据需要办理涉及进入工作场所的手续、证件
本工序施工负责人
有效
6
确认上一道工序检查合格
(1)户外SF6断路器和真空断路器及负荷开关的各项电气试验合格,试验结果必须符合电气设备交接试验标准要求。
如需调整继电保护整定值按验收单位的要求调整好。
(2)接地电阻符合设计要求
本工序施工负责人
合格
5.2人员、主要工器具及仪器仪表配置
表5.2人员、主要工器具及仪器仪表配置
序号
项目
内容
说明
1
人员配置
施工阶段
建议工作
人数
现场施工负责
人
现场施工
质安员
技术岗位必须持有与作业工种相应、有效的上岗证,辅助工不得从事电气设备安装等专业工作
支架安装
技术工人3
1
1
断路器或负荷开关安装
技术工人3
接线及附件安装
技术工人3
2
施工内容相对应的设备材料
户外断路器或负荷开关、导线、热镀锌螺钉、热镀锌角铁、绝缘护套、瓷担等
(1)核对设备、材料的到位及数量;核对户外断路器或负荷开关的技术参数,各项参数符合设计要求。
(2)检查确认户外断路器或负荷开关的瓷件、套管良好,干净,气压指示正常。
进行分、合试验时操动机构灵活,经分、合操作3次以上正常,分、合位置指示正确可靠。
(3)收集户外断路器或负荷开关的出厂合格证明文件及技术资料
3
施工内容相对应的器具、机械及工器具仪表
工器具:
水平仪、焊接工具、压接钳、绳索、扳手、尺子、梯子等。
机械:
根据户外断路器或负荷开关的型号、规格,准备车
辆、起重机具及吊装机具等
(1)根据现场情况使用的工器具符合相关要求。
(2)钢丝绳荷重,须保证其安
全系数,根据起重机具臂角度确
定荷载,不得超载使用
4
完成开工程序
工作负责人向项目负责人报开工,并由项目负责人完成向监理单位开工报审手续
施工准备完成可报开工,当施工准备不足时,上报该项目负责人协调解决
6作业方法
表6作业方法
序号
项目
内容
说明
1
作业前工作
(1)现场施工负责人向进入本施工范围的所有工作人员明确交待本次施工设备状态、作业内容、作业范围、进度要求、特殊项目施工要求、作业标准、安全注意事项、危险点及控制措施、危害环境的相应预防控制措施、人员分工,并签署
(班组级)安全技术交底表。
(2)工作负责人负责办理相关的工作许可手续,开工前做好现场施工防护围蔽警示措施,夜间施工的,须有足够的照
明。
(3)现场施工负责人组织检查确认进入本施工范围的所有
工作人员正确使用劳保用品和着装,并带领施工作业人员进入作业现场
按安规规定佩戴统一的安全帽、统一佩戴有个人照片的作业证(或胸卡证),穿着统一的工作服
2
开始主要作业
现场施工负责人发出许可开工命令
3
支架安装作业程序
(1)支架应采用热镀锌材料,如需对热镀锌材料进行加工,必须进行防腐处理。
(2)双杆式户外断路器或负荷开关支架宜采用槽钢,并经热镀锌处理,其强度应满足断路器或负荷开关荷载的要求。
(3)支架安装牢固、平整,水平面倾斜不应>1%
现场施工负责人正确、安全地组织作业,现场施工质安员负责现场作业全过程的安全、质量监控
4
断路器或负荷开关安装作业程序
(1)户外断路器或负荷开关吊装时参照厂家的“设备安装指导手册”。
(2)禁止用操作手柄或瓷套管搬动开关。
(3)户外断路器或负荷开关在装卸、就位的过程中,设专人负责统一指挥,指挥人员发出的指挥信号必须清晰、准确。
(4)采用起重机具装卸时,起重机具的支撑腿必须稳固,
受力均匀。
起吊时必须试吊。
起吊过程中,在吊臂及吊物下
方严禁任何人员通过或逗留,吊起的设备不得在空中长时间停留。
(5)户外断路器或负荷开关就位移动时,应缓慢移动,不
得发生碰撞及不应有严重的冲击和震荡,以免损坏绝缘构件。
(6)将户外断路器或负荷开关安装在支架上,并用热镀锌螺栓固定牢固。
(7)户外断路器或负荷开关安装后,套管表面应光洁,不
应有裂纹、破损等现象;套管压线螺栓等部件应齐全,且安
装牢固,气压不低于规定值,外壳干净
现场施工负责人正确、安全地组织作业,现场施工质安员负责现场作业全过程的安全、质量监控
5
接线及附件安装作业程序
(1)户外互感器安装按照HWDQSB—03户外互感器安装作业指导书相关要求进行施工。
(2)根据设计图纸及验收单位的要求,将辅助开关用固定金具固定在电线杆或铁塔上。
(3)选择的导线其截面应满足设计要求,导线在施工前应先用尺实际测量各跨安装点的准确长度,根据施工需要进行切割。
(4)导线压接后不应使管口附近导线有隆起和松股,管表面应光滑,无裂纹。
金具压接后,均应倒棱,去毛刺。
(5)两端遇有铜铝连接时,应设有过渡措施。
(6)引线应安装牢固、排列整齐美观。
引线相间距离及对
地距离应符合规定要求。
(7)接线端子与引线的连接应采用线夹,接触面清洁无氧
化膜,并涂以中性导电脂。
(8)户外断路器或负荷开关本体外壳及支架接地应可靠,
紧固件及防松零件齐全。
(9)户外一次接线应采用热镀锌螺栓连接,所用螺栓应有
平垫圈和弹簧垫片,螺栓紧固后,螺栓宜露出2~3丝扣。
(10)裸露带电部分宜进行绝缘处理。
(11)导线相色标识正确清晰、对应。
(12)户外断路器或负荷开关操动机构的二次电缆口应进行
封堵。
(13)同杆上装设二台及以上断路器或负荷开关时,每台应
有各自标识。
悬挂标志、警告牌等参照设计图纸及上级单位验收相关标准及文件的要求设置
现场施工负责人正确、安全地组织作业,现场施工质安员负责现场作业全过程的安全、质量监控
7质量控制措施及检验标准
7.1质量控制措施
7.1.1现场负责人应根据现场情况安排技术人员负责质量监控。
7.1.2作业人员必须熟悉工程作业流程和质量检验标准;技术岗位人员必须持有与作业相应、有效的上岗证。
7.1.3现场负责人在进行安全技术交底时必须详细介绍本作业质量控制要点、常见的质量通病及其防治措
施。
7.1.4作业现场必须有经审核批准的设计图纸和施工方案,作业人员必须按图施工。
7.1.5施工质量检验一般按以下方式进行。
质量检验一般采用三级检验制,施工队(组)对所施工的分项
工程应进行100%的质量自检;项目部对所负责施工的分部工程和单位工程组织质量检查,复检比例不宜低于50%;公司对单位工程组织检查,抽检比例不宜低于20%。
7.1.6隐蔽工程施工完成以及全部工序作业完成(转序)时,必须提前24小时通知监理现场验收。
7.2质量控制点
表7.2质量控制点表单
控制点
控制方式
W
H
S
户外电气设备安装
●
7.3检验标准
质量检验按《10kV~500kV输变电及配电工程质量验收与评定标准第8册:
配网工程》中的Q/CSG表
8-7.9要求执行。
●附件1安全施工作业票
编码:
HWDQSB-01-01/01
工作时间
工作地点
技术员
现场安全员
现场负责人
安全风险分析及控制措施
序号
危害名称
风险种类
风险等级
风险控制措施
1
隔离开关、闸刀型开关处在断开位置时即开始搬运
打击
□低风险
现场作业应严格执行相关安全规程及安全技术措施,并重点关注但不限于以下措施:
□隔离开关、闸刀型开关应处在合闸位置才可以开始搬运。
□按规定使用安全、合格的登高用具。
□使用双保险安全带。
□用绳索传递工器具、材料,现场人员必须戴安全帽。
□使用开关固定金属受力点搬运。
□线缆敷设进入设备后及时对线缆进出口进行封堵,并检查其可靠性
2
不按规定使用或选用不合格登高工具
坠落
□特高风险
3
高空作业不按规定穿戴安全带
坠落
□特高风险
4
不用绳索传递工具、物料及不使用工具袋
打击
□中等风险
5
用瓷套管作为受力点搬动开关
设备破损
□中等风险
6
线缆出入口封堵措施不足
设备停运
□高风险
安全补充事项/平面布置图
现场接受交底人员签名
备注
说明:
(一)本票由现场技术员填写,现场安全员审核,现场负责人签发生效。
现场负责人开工前核对风险控制措施
并宣读。
(二)工作内容、地点、安全措施不变时本票最长可使用十天,否则应重新办票,用后上交备查;当人员发生变
更时,应在备注栏记录变更情况。
对新增人员进行交底,并签名确认。
(三)应根据现场条件、范围和环境,补充安全事项或平面布置图。
(四)当风险等级与基准风险等级不一致时,项目部应组织相关人员重新进行风险评估并制定措施。
(五)基准风险等级与风险控制措施在开工前现场打“√”。
(六)签名不齐全(含代签名的)均作废票处理。