Part1

1.AppendixtoTender投标书附件2.BillofQuantities工程量表3.Discharge结清证明

4.InterimpaymentCertificate中期付款证书5.PerformanceSecurity履约担保

6.ProvisionalSum备用金额暂列金额

7.ReleasefromperformanceundertheLaw依照法律解除履合同

8.SuspensionandTerminationbyContractor由承包商暂停和终止

9.Thejointinsured共同被保险人10.UnitPriceContract单价合同

11.ValueEngineering价值工程

3.FinalPaymentCertificate最终支付证书

5.RetentionMoney保留金6.Statement报表

9.Variation变更10.AdvancePayment预付款

1.ForceMajeure不可抗力3.Indemnities赔款

4.theinsuringParty保险方

5.InsuranceagainstinjurytoPersonsandDamagetoProperty人身伤害和财产损失险

8.jointandseveralliability共同以及个别的法律责任

9.Erection/contractorAllRisksInsurance安装/建筑工程一切险

10.infringementsofintellectualpropertyright知识产权侵权

1.Basedate基准日期2.CommencementDate开工日期3.PerformanceSecurity履约担保

4.LetterofAcceptance中标函6.DefectsNotificationPeriod缺陷通知期限

Thethirdpartyliabilityinsurance第三者责任险thepersonaccidentinjuryinsurance人身意外伤害险

 

12.TheContractPriceshallbeadjustedtotakeaccountofanyincreaseordecreaseinCostresultingfromachangeintheLawsoftheCountry(includingtheintroductionofnewLawsandtherepealormodificationofexistingLaws)orinthejudicialorofficialgovernmentalinterpretationofsuchLaws,madeaftertheBaseDate,whichaffecttheContractorintheperformanceofobligationsundertheContract.

对于基准日期后工程所在国法律有改变(包括实施新的法律,废除法律或修改现有法律)或对此类法律的司法或政府解释有变,影响承包商履行合同规定的义务的,合同价格应考虑上述改变导致的费用增减进行调整。

 

13.IftheContractorfailstogivenoticeofaclaimwithinsuchperiodof28days,theTimeforCompletionshallnotbeextended,theContractorshallnotbeentitledtoadditionalpayment,andtheEmployershallbedischargedfromallliabilityinconnectionwiththeclaim.

如果承包商未能在上述28天期限内发出索赔通知,则竣工时间不得延长,承包商则无权获得追加付款,而雇主则应免除有关该索赔的全部责任。

14.TheContractorshallbeentitledsubjecttoSub-Clause20.1[Contractor’sClaims]to:

承包商有权依据20.1款的规定要求(承包商的索赔):

(a)anextensionoftimeforanysuchdelay,ifcompletionisorwillbedelayed,underSub-Clause8.4[ExtensionofTimeforCompletion]and

依照8.4款(延长竣工时间)的规定

(b)paymentofanysuchCost,whichshallbeincludedintheContractPrice.”

任何此类费用应计入合同价格,给予支付,

 

RepublicofLebanon

ElectriciteDuLiban

(EDL)

Engineering,ProcurementandConstructionofTwoAirInsulated

Substations(AIS)220KVinSaida赛达andBaalbeck巴尔贝克

-ElectriciteDuLiban(EDL),thepublicelectricpowerutility(公共事业公司)inLebanon,isinterestedinrequestingthebidsforEngineering,Procurement采购andconstruction建设ofTwoAirinsulatedSubstations(AIS)220kvinSaidaandBaalbackundertheInternationalCompetitiveBiddingProcedures(ICB)国际竞争性招标.EDLwillfinancethisContract.

-Thefirmswillbeexaminedforeligibility资格basedonPost-qualificationcriteriaincludedinthebiddingdocuments.ThefirmswhopassthePost-qualificationcriteriawillhavetheirofferssubjecttodetailedTechnicalEvaluationand,thereafter,toFinancialEvaluation.

-Allprospectivebidderswillbeinvitedtoattendapre-bidconference.AnychangestotheBiddingDocumentswillbecirculated,andissuedasamendmenttothebiddingdocumentstoallthebidders.Thepre-bidconferencewillbeheldattheofficesofEDL-floorTJonNovember1st,2010at11:

00a.m.

-InterestedBiddersmayobtainfurtherinformationfromtheofficesofEDL(Addressbelow),purchasethebiddingdocumentsuponpaymentofanon-refundablefeeof1,000,000L.L.(OneMillionLebanesePound)+10%VAT,payableincashorbyaBanker’sdraftinthenameofEDL,orinspecttheBiddingDocumentsasofthedateofthisNoticeduringthenormalworkinghours.

-AllbidsshallbeaccompaniedbyaBidSecurityoftheamountof1,000,000,000L.L.(OneBillionLebanesePounds)accordingtoEDLapprovedspecimenandmustbedeliveredattheaddressgivenbelowbeforeDecember14,2010at11:

00a.m

.

-Bidswillbeopenedthereafterinthepresenceofthebidder’srepresentativeswhochoosetoattend.

ELECTICITEDULIBAN

22,RUEDUFLEUVE,12THFlooroffice1223

P.O.BOX131,BEIRUT,LEBANON

PHONE:

961-1-442720-to444729

FAX:

961-1-583084

 

Part2

15.WhyisBaseDateneededtobespecifiedinthetenderingdocuments?

Itcanbeserveasacriterionforassessingtherelevantinformationinthetender.Ifgreatchangesoccurduringtheexecutionoftheworksthecontractpriceshallbeaccordinglyadjusted.

16.Whatcanbeconstruedasavariation(变更)?

P86

1)Shallchangestoquantitiesofanitemofworkbedeemedtoavariation?

Changestoquantitiesofanitemofworkdoesnotnecessarilyconstitueavariation

2)CantheEngineerissueaninstructionofvariationaftertheissuingoftaking-overcertificate?

Theengineershallnothavetheauthoritytodothatinaccordancewithsub-clause13.1

3)CanthechangeofthelawsinthecountrynecessarilygiverisetotheadjustmentofContractprice?

No,onlyontheconditionthatsuchchangeadverselyaffecttheperformanceofcontractor’sobligationsunderthecontract.

17.What’stheprerequisitefortheEmployertomakeanadvancepaymenttotheContractor?

Undertheconditionthattheemployerreceivestheinterimpaymentcertificateforthefirstinstallmentandperformancesecurityandadvancepaymentguaranteeaswell.

WhenshalltheEmployermaketheadvancepayment?

OntheconditionthattheEmployerreceivesstatementandperformancesecurityaswellastheadvancepaymentguaranteeinaccordancewithsub-clause14.2.

18.IfaneventoracircumstancecanbeconstruedasForceMajeure,whatconditionsshallbesatisfied?

Thefollowingconditionsshallbemet:

(a)whichisbeyondaparty’scontrol,

(b)whichsuchpartycouldnotreasonablyhaveprovidedagainstbeforeenteringintothecontract,

(c)which,havingarisen,suchpartycouldnotreasonablyhaveavoidedorovercome,and

(d)whichisnotsubstantiallyattributabletotheotherparty.

19.PleasereadthefollowingSub-Clause,andanswerthequestion:

ShalltheContractorbeboundbyanoralinstruction?

3.3InstructionsoftheEngineer

IftheEngineeroradelegatedassistant:

•(a)givesanoralinstruction,

•(b)receivesawrittenconfirmationoftheinstruction,from(oronbehalfof)theContractor,withintwoworkingdaysaftergivingtheinstruction,and

•(c)doesnotreplybyissuingawrittenrejectionand/orinstructionwithintwoworkingdaysafterreceivingtheconfirmation,thentheconfirmationshallconstitutethewritteninstructionoftheEngineerordelegatedassistant(asthecasemaybe).

20.Canadisputebereferreddirectlytoarbitration?

Why?

Inmostcases,adisputeshallbereferredtoADABundersub-clause20.4.However,ifthereisnoDABinplaceundersub-clause20.8,itcanbedirectlyreferredtoarbitrationundersub-clause20.6.

 

21.WhatdoestheContractortypicallyclaimfor?

Pleaselist3Sub-ClausesthattheContractorcanapplytomakeaclaimsagainsttheEmployer.

 

1.Whatisthemajordifferencebetweentheacceptedcontractamountandthecontractprice?

Inaccordancewithsub-clause14.1,thecontractpricecanbeadjusted.

2.Ifthepaymentsaredelayed,whataretheremediestheContractorcanresortto?

Takeaccountofsth

Takeintoconsiderationofsth

Submit,tosb,sth

 

1.CantheEmployerreplacetheEngineerwithouttheconsentoftheContractor?

Why?

No,because3.4(p35)

2.CantheEngineeramendtheContract?

Why?

Absolutelynot,sub-clause3.1providesthattheengineershallhavenoauthoritytoamendthecontract,asamatteroffact,theprimaryreasonliesinthefactthattheengineerisnotoneofthepartiestothecontract.

3.IftheSpecificationisinconsistentwiththeContractAgreement,whohastheauthoritytoissuenecessaryclarification?

Whichofthetwodocumentshastheprioritytobeapplied?

P251.5

4.CanoneofthepartiestotheContractassignthewholeoranypartoftheContractoranybenefitorinterestinorundertheContract?

P40

6.WhohastheauthoritytonominateaSubcontractor?

IstheContractorunderobligationtoemployanominatedSubcontractor?

P555.15.2

2.HowdoestheAcceptedContractAmountdifferfromtheContractPrice?

Thelatercanbeadjustedinaccordancewiththeagreementbetweenthepartiestothecontractortheconditionsofcontract.

3.DoesachangeoflawnecessarilyresultinadjustmentsoftheContractPrice?

Why?

Yes,p9113.7

5.WhyisawrittendischargebothnecessaryfortheContractorandtheEmployer?

P10214.12

 

1.Underwhatconditionsthecontractorshallbeentitledtosuspensionoftheworkorreductionoftherateofwork?

Twoconditionsshallbemet:

firstofall,theEngineerfailstocertifyinaccordancewithsub-clause14.6[issueofinterimpaymentcertificates]ortheemployerfailstocomplywithsub-clause2.4[employer’sfinancialarrangements]orsub-clause14.7[payment],andthecontractorshallgivenotlessthan21days’noticetotheEmployer.

2.Accordingtosub-paragraph(d)ofSub-Clause15.2,theEmployershallbeentitledtoterminatetheContractiftheContractorsubcontractsthewholeoftheWorksorassigntheContractwithoutrequiredagreement.Whyisitprovidedinthisway?

Pleasejustifytheprovision.

ItisevidentthatthecontractualagreementsignedbythecontractorandtheEmployerisbasedontheparties’mutualtrust.ThereforetheprovisioncanserveasadeterrenttoensurethattheinterestsoftheEmployershallbeprotected.

 

4.WhichPartyshallbetheinsuringPartyforinsuranceagainstinjurytopersonsandDamagetoPropertyandforinsuranceforWorks?

Unlessotherwisestatedintheparticularconditions,thecontractorshallbetheinsuringparty.

5.WhydoestheSub-Clause4.17providethat“The