五柱模板及支撑体系计算
一工程概况.................................................................................................................3
二模板支撑设计.........................................................................................................3
三梁模板与支撑架计算.............................................................................................3
1上部框架梁模板基本参数.....................................................................................4
2梁模板荷载标准值计算.........................................................................................4
3梁底模板木楞计算.................................................................................................5
4梁模板侧模计算.....................................................................................................5
5穿梁螺栓计算.........................................................................................................6
6梁模板支撑脚手架的计算.....................................................................................7
四6.5M 高楼板模板钢管扣件支架计算 ...................................................................7
1模板面板计算.........................................................................................................8
2模板支撑方木的计算.............................................................................................9
3板底支撑钢管计算 ..............................................................................................10
4扣件抗滑移的计算 ..............................................................................................11
5模板支架荷载标准值(立杆轴力) .......................................................................12
6立杆的稳定性计算 ..............................................................................................12
五柱模板及支撑体系计算 ......................................................................................13
1柱模板计算基本参数 ..........................................................................................13
2柱模板荷载标准值计算 ......................................................................................14
3柱模板面板的计算 ..............................................................................................15
4竖楞木方的计算 ..................................................................................................16
5B 方向柱箍的计算 ..............................................................................................17
6B 方向对拉螺栓的计算 ......................................................................................18
7H 方向柱箍的计算 ..............................................................................................19
8H 方向对拉螺栓的计算 ......................................................................................20
1
六楼梯模板 ..............................................................................................................20
七模板安装质量要求 ..............................................................................................21
1模板制作 ..............................................................................................................21
2墙模板安装 ..........................................................................................................21
3柱模板安装 ..........................................................................................................21
4梁、板模安装 .......................................................................................................21
5楼梯模板安装要求 ..............................................................................................23
6后浇带模板及支撑架安装要求 ..........................................................................23
7模板支设的质量要求 ..........................................................................................23
8板模支设的质量控制措施 ..................................................................................24
9模板拆除 ..............................................................................................................24
10成品保护 ..............................................................................................................25
11安全技术要求 ......................................................................................................25
12文明施工要求 ......................................................................................................26
2
一工程概况
1.1工程名称:
3M 中国有限公司新桥生产用房扩建工程
1.2工程地点:
中国上海松江区新桥镇民益路 38 号 3M 新桥工厂内
1.3结构类型:
桩基独立承台,现浇钢筋砼框架结构,整体二层(局部三层)。
1.4建筑面积:
13194 平方米
一模板支撑设计
1.1设计原则
✍实用性:
该工程结构质量要求高,接缝要严密,不漏浆。
保证构件的形状尺寸和
相互位置的正确,模板构造合理,便于支拆;
✍安全性:
在施工过程中,不变形,不破坏,不倒塌;
✍经济性:
合理配备模板,减少一次性投入,增加模板周转次数,减少支拆用工,
实施文明施工;
1.2独立柱基础承台及底板基础梁模板:
结构地坪部位梁采用 240mm 厚 MU10 混
凝土砌块砖胎模、M7.5 水泥砂浆砌筑,内侧抹 20mm 厚 1:
2 水泥砂浆。
砖模板
砌筑好后,四周用土回填密。
1.3基础剪力墙模板及其支撑体系:
模板采用优质层板,层板厚 18mm,背楞采用
50×100×4000mm 木枋,龙骨采用 Φ48×3.5mm 厚标准钢管。
1.4框架梁、板模板及其支撑体系:
模板采用优质木层板,层板厚 18mm,背楞采用
50×100×4000mm 木枋,龙骨采用 Φ48×3.5mm 厚钢管。
1.5梁、墙拉接体系:
采用 Φ12mm 圆钢作为对拉螺杆。
一梁模板与支撑架计算
1上部框架梁模板基本参数
1.1本工程梁截面形式众多,现以最大截面 700×1400mm 的梁为例进行计算。
1.2梁截面宽度B=700mm,高度H=140