Constructionofkeyproblemsofprojectprogresscontrol
Abstract
Constructionprogresswasoneofthethreeobjectivesoftheprojectwhichisanimportantcomponentofprojectmanagement.Reasonable,scientific,efficiencyofprojectconstructionscheduleisthekeytoachievetheprojectobjectivescontrol.Onlyduringthepreparationstage,stageofprogressoftheprogrammerdesignstage,plansandimplementationofconstructionandotherlinks,takingfullaccountofthefavorablefactors,rationalcoordinationoflimitedresources,caneventuallyachievetheprogressrequiredbythetarget,tocreateadvaneed,civilizationandconstructionprocessandlayasolidmaterialfoundation.
Keywords:
Constructionprojects;Progresscontrol;Keyissues
Progress,investment,qualityisthethreeobjectivesoftheproject;thereisarelationshipofmutualdependenceandmutualrestrictionbetweenthem.Projectschedulecontrolisanimportantcomponentofprojectmanagementandistoensurethatprojectobjectivescontroliscompletetheprerequisitefortherealizationof,toensuretheprojectduration,therationaluseofresources,andlowercosts,topreventplanchangestoobigandimportantguaranteeforimprovingtheefficiencyofproject.Managementshouldfocusonthefollowingaspects:
1.Attachesgreatimportancetoprojectconstructionpreparation
Projectpreparationisanimportantcomponentofconstructionproduction,anditisintendedtoprojectgoals,resourcesupplyandselectionofconstructionplan,spatiallayoutandthevariousaspectsoftimeandmanpowerarrangement.Italsoisthefundamentalguaranteeforthesmoothconductofcivilengineeringconstructionandequipmentinstallation.Therefore,preparingcarefullyfortechnicalbeforeconstruction,materials,labororganizationspreparationandover-the-counterpreparationsforconstructionsitepreparation,hasanimportanteffectonrationalsupplyingresourcestospeeduptheconstructionspeed,improvingprojectqualityensuringconstructionsafetyandwinningsocialreputation.To
strengthentheprojectprogresscontrol,youmustattachgreatimportaneetotheprojectpreparation,preparationbeforeconstruction.
2.Deploymentandconstructionofconstructionprogramming
Constructionsofcomprehensivearrangementsforthedeploymentprojectasawholeis,andmakesdecisionsonmajorstrategicissuesinconstruction.Prefectofconstructiondeploymentiseffectivecontrolengineeringprogress,guaranteesengineeringquality,andsavesengineeringinvestmentofprimaryprotection,anditspreparationshouldreflectreasonableoforganizationarrangementsandtaskdivision,andestablishprovenof,andreasonablerunningofProjectManagersector;personnelofsetandthedivisionshoulddofullmobilizationitsenthusiasm,andmakeofprofessionalplay;establishedofspecializationconstructionorganizationsystemandforengineeringminpackage;divisionconstructionstage,determinesstagingbatchconstruction,andcommissioningofarrangementsandmainprojectandinterspersedproject.
Inadditiontothedeploymentconsistsofperfectconstruction,preparationofreasonableconstructionplan,toensuretheeffectiveprogressoftheproject,constructionreadinessplanningshouldalsobeenincludedthedevelopmentspecification.Mainsite-widepreparations,includesmaterialsforideological,organizationalpreparation,technicalpreparation,andsoon.Majoritemsofworksorthemainunitofengineeringandspecialprojectsshouldbedevelopedintheconstructionorganizationtodesignitsconstructionprogrammed.Theaimisthepreparationoftechnicalandalsofortheconstructionofwellunderwayandprovidesabasisforrationalarrangementoftheprojectsite.Therefore,youshouldcalculatethequantitytodeterminetheprocess,selectthecommandmentsandmainconstructionmethodoflargeconstructionmachine.
Engineeringdeterminationoftheorder,needtobeconstructedbystagesandingroups.Itshouldbethefirstundergroundandthentheground,afterthefirstdeep-shallow,afterthefirstline,extension,undergroundpipelineconstruction,withthesupplyofvarioustypesofmaterialandtechnicalconditionsandshouldbebalaneedandrationalutilizationoftheseresourcesbetweencoordinatedconstructionofpromotingbalaneed.
3.Inaccordancewiththecontract'sdurationrequirements,wellconstructionprogresscontrol
Accordingtothedurationofthecontracttocompleteconstruction,bothcontractrequirementsarealsoobjectstoachievebusinessgoals.Inthisconnection,theconstructionunits(owners)withtheconstructionunitoftheinterestsofbothsidesarefullyconsistent.Therefore,strengtheningconstructionprogresscontrolensuresthatthedurationofthecontractperformaneeisaprojectmanagerandmaincontentofthebasicduties.Planisaprerequisiteforcontrol,ifhasnotitwillbeoutofcontrolwhichistocompareactualandplannedvalues,identifydeviationsduring,andforfeedbackadjustment.Preparationofconstructionprogressplantocontrolthedurationvalueisdetermined,andcomeupwithaguaranteeschemeimplementationofeffectivemeasurestoguaranteethedurationplannedcompletionofthecontractperiod.
Preparationofprogressistodecidewhattowhentodo,orwhentheprogressoftheprojecttodowhatextent.Whateveristheprocessoftheprojectitself,orwithotherconstruction-relatedwork,shouldbeintegratedintothescheduleto,or,whoseprogressyouwanttomakeaschedule.Typesofprojectscheduleclassificationbasedoncontentistargetedschemesandsupportschemes.Schedulefortheprojectitselfisthemostbasicgoalplanthatdeterminesthedurationoftheprojectgoals.Inordertoachievethisgoal,youhavearangeofsupportplans,suchasplanningmaterialusage,workingcapitalplanningmaterialusage,andequipmentuseplans,laboruseplantouseplan,semi-finishedproductsandcomponents,andsoon.Controlthelengthoftimeitcamefromoverallprogressplanandphaseplan.Totalprogressschemecontrolthewholeprocessofprojectconstruction,andphasedplanincludestheprojectconstructionprogressplanandten-years,quarters,months,weeksofjobschedules,andsoon.Ithasatextplan-planwithachartfromtheexpressions.Theformeriswithatextdescriptionofeachstageofconstruction,andtheimageofprogresstoachieverequirements;thelatteriswithimageandsimplechartstoexpresstheconstructionschedule.AsfarasIknow,baristhemostcommonlyusedscheme,networkplanning,andslash-typescheme.Ithasoverallprogressplanandthepartitionplanfromthescopeofmanagement.Masterplansareproject-orientedglobalstrategyprogressoftheplan,generallycruder.WhiletheplanisforabottlegourdorProject~Professionalprogressoftheworkplan,generallymoredetailed.
4.Preparationofprojectschedule
a.Thisprojectofprojectcontract.Provisionistodeterminethedurationofthecontractdurationinplannedvaluebasis.Projectstartandcompletiondatesstipulatedinthecontract,mustbeimplementedbyschedule.Scheduleoftheultimategoalisthroughreasonableprogressdesign,toguaranteedurationcompletedontime.
b.Constructionofenterpriseproductionandmanagementofreasonableplan.Throughtheconstructionofenterpriseproductionandmanagementofrationalplanning,toensureprojectefficiency,isthemajorcomponentoftheplan.Obeyingthebusinessprincipleofguidaneeandmeetingtherequirementsofenterprisebalaneeachievethebestinterestsoftheenterprise.
c.Drawinginformation.Drawinginformationisthebasisandpremiseofrationaldesignofconstructionschemesforconstruction.Constructionprogressplanmustbelinkedwiththeprogressofthedesignplan,andmustbebasedonthedateofdeliverynumberagreementtoarrangetheappropriatepartoftheconstructiontime,whichisalsoagoodwayofconstructionriskpreventionandguaranteeconstructionquality.
d.Constructionorganizationdesignofthisprojectisoneofthestrongbasisforthepreparationofprojectscheduling.Thisinformationdefinesconstructioncapacitydeploymentandmethodofconstructionandreflectstheconstructioncharacteristicsoftheproject,whichformsthebasisoftargetsatvariousstagesintheprocessofdeterminingconstructionplans.
e.Materialsandequipmentsupplyplan.Ifyoualreadyhaveonthematerialandequipmentandturnovermaterialsupplyplan,theconstructionprogressplanmustbecoordinatedwiththeproject.Inadditiontotheabovefivepointsmakingprogressonaprojectplansasthebasisforthemainconsideration,youshouldbeawareofinformationaboutsiteconstructionconditions,includinghydrological,climateandenvironmentaldatainthefieldofconstructionandtransportationconditions,energysupply,auxiliaryproductioncapacity.Alsopriortothepreparationofprojectconstructionprogressplan,similartoanalreadybuiltoractualconstructionscheduleneedstobecollected,andyoushouldseriousanalysis,organize,listcontrolconstraint,cleartheinflueneeofdurationtoachievemandatorytimelimits,forthepreparationofprojectprogressaswellprepared.
5.Theprojectprogr