资源描述

某小区高层住宅施工组织设计最终版.docx

《某小区高层住宅施工组织设计最终版.docx》由会员分享,可在线阅读,更多相关《某小区高层住宅施工组织设计最终版.docx(124页珍藏版)》请在冰豆网上搜索。

某小区高层住宅施工组织设计最终版.docx

某小区高层住宅施工组织设计最终版

(此文档为word格式,下载后您可任意编辑修改!

 

****公司**花苑

住宅楼工程施工组织设计目录

第一章工程概况············································15

.1设计概况···········································15

1.2气象条件···········································15

1.3地质构造···········································15

1.4现场条件···········································16

1.5施工特点分析·······································16

第二章工程目标············································16

.1质量目标···········································16

2.2安全目标···········································16

2.3工期目标···········································17

2.4文明目标···········································17

2.5环保目标···········································17

2.6服务目标···········································17

第三章项目施工管理机构设置································17

3.1施工管理机构设置···································17

3.2组织机构管理形式···································18

3.3主要管理人员组成···································18

3.4主要管理人员职责···································19

第四章施工部署及生产准备·····························23

4.1施工部署指导思想································23

4.2施工部署原则····································24

4.3施工顺序流水段划分······························24

4.4生产准备········································25

第五章施工方案与技术措施····························29

5.1总体施工方案·································29

5.2施工测量·····································30

5.3土方工程·····································39

5.4喷锚网护坡···································45

5.5人工成孔钢筋混凝土灌注桩·····················49

5.6基础工程·····································54

5.7地下室卷材防水施工···························74

5.8主体工程·····································78

5.9砌体工程·····································96

5.10脚手架工程···································98

5.11装饰工程·····································106

5.12门窗工程·····································131

5.13安装工程施工·································134

第六章质量管理体系与措施····························142

6.1质量目标·····································142

6.2质量管理体系·································142

6.3技术保证措施·····························153

6.4组织措施·································154

第七章安全管理体系与措施························155

7.1确保安全目标,建立健全安全管理体系·······155

7.2现场安全管理规章制度·····················156

7.3安全防护设计与管理·······················157

7.4安全防火、防雷击等技术措施···············161

7.5防有毒、有害气体的安全防护···············162

7.6防高空坠落、物体打击及机具伤害的安全措施·162

7.7施工用电的安全措施·······················163

7.8易燃易爆物品管理及安全使用的技术措施·····164

7.9安全作业纪律及防盗措施···················164

第八章环境保护管理体系与措施···················164

8.1环境保护管理体系·························164

8.2环境方针·································164

8.3施工现场的环境保护措施···················165

8.4施工现场周边环境卫生保护措施·············166

8.5防止噪音措施·····························167

第九章文明施工保证体系与措施··················168

9.1建立文明施工保证体系·····················168

9.2对场区进行文明施工规划···················168

9.3现场材料·································169

9.4建立和完善各项文明施工管理制度·········169

第十章工程进度计划与措施·····················170

10.1工期安排······························170

10.2施工计划制度··························170

10.3组织交叉、流水施工作业,加快施工进度··170

10.4合理调配机械、材料、劳动力············171

10.5与各方紧密配合,加快施工进度··········171

第十一章源配备计划·····························172

11、1主要施工机械计划····················172

11、2试验、检测仪器计划··················172

11、3劳动力计划··························172

第十二章施工总平面图··························172

12.1现场平面布置图·······················172

第十三章冬雨季、农忙季节施工措施··············174

13.1冬季施工措施··························174

13.2雨季施工措施··························178

13.3农忙季节措施··························178

第十四章关键点、难点控制分析及处理措施········179

14.1施工测量及有效的测量观测··············179

14.2筏板基础大体积混凝土施工··············180

14.3附着式升降脚手架施工··················181

14.4混凝土结构裂缝的预防···················182

14.5加气混凝土砌体裂缝的预防··············185

14.6施工缝的有效处理······················186

第十五章施工管理总承包管理措施···············187

15.1管理总则·····························187

15.2对专业分包单位管理方法···············188

15.3总承包对各分包单位的协调配合·········191

15.4对空调、消防等工程管理···············192

15.5其它工程·····························192

15.6总承包人与业主的关系·················192

15.7总承包人与监理的关系·················193

15.8总承包人与设计方的关系···············193

第十六章沿线建筑物、地线管线及文物保护措施··194

16.1沿线建筑物、地下管线保护措施········194

16.2文物保护措施························194

附表一:

拟投入本工程的主要施工设备表

附表二:

拟配备本工程的试验和检测仪器设备表

附表三:

劳动力计划表

附表四:

计划开、竣工日期和施工进度网络计划图

附表五:

施工总平面图

附表六:

临时用地表

附图:

质量管理体系

安全管理体系

环保管理体系

文明管理体系

****公司**花苑

住宅楼工程施工组织设计

第一章工程概况

****公司**花苑住宅楼工程位于**市**湖公园西北角,南临**市主干道**路以北;建设规模为建筑高度为98.6米,地上部分30层。

由28层住宅楼和2层商业裙房构成;地下有1层,为地下车库及设备用房。

总建筑面积约20000平方米。

其中地上建筑面积约16000平方米,地下建筑面积约4000平方米。

本次招标范围为施工图纸包含的全部内容(不含电梯设备及安装、空调设备及安装、变压器设备及安装、全部门和窗)。

1.1设计概况

**市****公司**花苑住宅楼工程位于**市**湖公园西北角,南临**市主干道**路以北;建设规模为建筑高度为98.6米,地上部分30层。

由28层住宅楼和2层商业裙房构成;地下有1层,为地下车库及设备用房;总建筑面积约20000平方米。

建筑:

本楼建筑高度为98.6米,地上部分由30层楼,由28层住宅楼和2层商业裙房构成;地下有1层,为地下车库及设备用房。

结构:

住宅主楼为剪力墙核心筒结构,商业裙房为框架结构。

1.2气象条件

拟建场区属温暖带半湿润季风气候,冬寒夏热,四季分