西萨摩亚5MW可研报告英文版 精品.docx
《西萨摩亚5MW可研报告英文版 精品.docx》由会员分享,可在线阅读,更多相关《西萨摩亚5MW可研报告英文版 精品.docx(71页珍藏版)》请在冰豆网上搜索。
西萨摩亚5MW可研报告英文版精品
FeasibilityResearchReport
Of5MWOn-GridPVPowerSystem
ProjectinSamoa
CEEG
2009-8-4
TableofContents
1.Generalintroduction
1.1Overview
1.2Solarenergyresourcesandgeographical/meteorologicalconditions
1.3Engineeringgeology
1.4Taskandscaleofproject
1.5Projectdesign
1.6Technicaldesign
1.7Fireprotection
1.8Organizationstructuredesign
1.9Engineeringmanagementdesign
1.10Environmentalprotectionandsoil/waterconservation
1.11Laborsafetyandindustrialhygiene
1.12Engineeringbudgetaryestimate
1.13Energysavingandemissionreductionbenefits
2.TheconstructionconditionsofSamoa
2.1Solarradiationcondition
2.2LocationTerm
2.2.1SiteLocation
2.2.2Constructionsiteconditions
2.2.3Geographicallandforms
2.2.4Geologysituation
2.2.5Siteconclusion
2.3Climatecharacteristic(providedbycustomer,needten-yearmeteorologicaldata)
3.ThebasicconditionsofelectricpowersysteminSamoa
3.1Basicconditionsofpowerconstruction
3.2Supplyconditionofpowersystem
3.3Demandconditionofpowersystem(needbalancetableofelectricpower)
3.4Theproblemofpowersystem
3.5Thedevelopmentplanofpowersystem
4.Designofsolarphotovoltaicpowerstation
4.1Designofsolararrays
4.1.1SelectionofPVmodules
4.1.2Theefficiencyevaluationofon-gridPVpowersystem
4.1.3Radiationcalculationoftheinclinedsurfaceofsolararray
4.1.4Series-parallelplanofPVsystem
4.1.5LayoutofPVarray
4.1.6Civilengineeringdesign
4.2DCcombinerboxdesignwithlightingprotectionforPVarray
4.3DCpowerdistributioncabinetdesign
4.4SelectionofPVgrid-tieinverter
4.5ACpowerdistributioncabinetdesignwithlightningprotection
4.6ACstep-uptransformerdesign
4.7Blockdiagramofsystemprogram
4.8Designofinterfacetopowergrid
4.9Programimprovements
4.10Constructiondesign
4.10.1Constructioncondition
4.10.2Transportationofconstruction
4.10.3Permanentlandforconstruction
4.10.4Mainpartofconstruction
4.10.5InstallationofPVarray
4.10.6Arrangementofconstruction
5.Environmentalimpactassessmentinconstructionphaseandmeasurementofemissionreduce
6.Publicbenefits
6.1Promotetouristindustry
6.2Createjobopportunities
7.Predictionofelectricitygeneration
7.1Electricitygenerationinfirstyear
7.2Electricitygenerationin25years
8.Investmentcostandrecovery
8.1Staticinvestmentevaluation
8.1.1Projectconstructioncostbudget
8.1.2Maintenancefee
8.1.3Totalstaticinvestment
8.2Revenueofelectricitygenerated
8.3Comparisonofstaticinvestmentandrevenue
8.4Recoveryofstaticinvestment
9.IntroductionofCEEG
1.Generalintroduction
1.1Overview
Samoa’s5MWon-gridPVdemonstrationprojectislocatedinPolynesia,thesouthernequatorialregion.Itsgeographicalcoordinates:
13.82°S,172.01°W,theaveragealtitudeof63m.Thesiteisopen,flat,easilyaccessibleandconvenient.(SpecificlocationcanbefoundintheattachedmapinFig.1.1).
Fig.1ThelocationofPVpowerstation
ThePVpowerstationcoversaround100,000㎡withalengthof563mandawidthof180.5m.Accordingtotheanalysisofsolarenergyresourcespre-installedrequirementsandoptimizedlayout,17,920280Wmodules,998mm(width)×1956mm(length)foreachmodule,willbeinstalledinthe100,000㎡area.ThetotalcapacityofPVpowerstationis5.0176MWandwillgeneratearound7,752,900kWheachyear.
1.2Solarenergyresourcesandgeographical/meteorologicalconditions
Accordingtoregionalsolarradiationdataandanalysis,solarresourceintheprojectsitehasseveralfeaturesinthefollowingconclusions:
1.2.1TheprojectislocatedinrichsolarresourceareaofSamoa
AccordingtoNASAsolarradiationdatameasuredinthepast30years,theaverageamountofsolarradiationis6,908.1MJ/m2,theaveragehoursofsunshineare3,313hours.
1.2.2ChoosethebestangleofPVarraycaneffectivelyincreasetheamountofradiation
BasedontheNASAdatabaseonSamoa’sradiationwithdifferentinclinedangle,theoptimumforPVpanelinstallationis18.9°.ThenthePVpanelwillreceivemaximumradiationof7053.9MJ/m2throughouttheyear.
1.3Engineeringgeology
TheprojectSiteiscoveredbyplantbutnoriver,lakeinthearound.Thedistancetotheairportisabout400mandtheairporthighwayinthenorth.Noresidentsliveinthesurroundingarea,nordoesanyminingfactory.(Moreinformationisrequiredtobeprovidedbycustomers,focusedonthegeologyconditions,whichshouldmeettheconstructionrequirementandtheeffectonconstruction.)
1.4Taskandscaleofproject
ThelocationisidealforPVpowerplantbecauseoftherichsolarresource,convenienttransportandgridconnectioncondition.Samoa’s5MWon-gridPVdemonstrationprojectwilladheretotheprincipleofworldsustainabledevelopmentofenergy,inlinewiththenationalenergystrategywhichcallsforreducingconsumptionoffossilresourcesandharmfulemissionssuchascoal-firedpollution.Sothisprojectwillplayanimportantroleinpromotingthelocaltourismandlocaleconomicdevelopment.Therefore,thedevelopmentofthisprojectisvitalnecessary.
1.5Projectdesign
Thisprojectusesdistributedgenerationandcentralizedgridconnectionstrategy.Thewholesystemwillbedividedintofive1MWunitsandconnectstolocalgridat22kVvoltagepointthroughfive0.4/22kVtransformer.Thewholesystemhas17920280Wmono-crystallinePVpanels,theactualoutput5.0176MW.Foreach1MWsubsystem,therearefour250kWgrid-tieinverters.Each250kWinverterconsistsofoneDCpowerdistributionunit,inwhichthereis10DCcombinerboxwithlightningprotection,6inputsforeachcombinerboxandtotal56inputsfor1MWunit.Foreachinput,thereisonePVstringwith16panelsinseries.So1250kWinverterhas896PVpanelsinput,and3584PVpanelsinputfor4inverters.Attheoutputofeachinverter,thereisanACpowerdistributioncabinetwithlightingprotection,andconnectingtoa1250kVA0.4/22kVstep-uptransformer.
1.6Technicaldesign
1.6.1Mainpowersystemdesign
SiliconPVmoduleisCEEGSST280-72P,mono-crystalline,thestandardpowerof280W,thepeakvoltageof35.5V.Grid-tieinverterisSG250KTL,maximumpowertrackingvoltagerangeDC450V~880V,outputpower250kW,theoutputvoltage270V,Europeefficiency98.3%,total20grid-tieinvertersforPVpowersystem.
Five0.4/22kVdistributiontransformersconnectstoone22kVdistributionconnectingpoint,5inputand1output,thentolocal22kVclassgrid.
1.6.2Centralcontrolsystemdesign
ThedepartmentofelectricpowerinSamoawilltakechargeoftheprojectandtakefew-peopleattendedmethod.Tele-controlworkstationwillbeusedinthecontrolroomforinformationtransmissiontoandmonitoringfromdispatchingdepartment.Theautomationsystemachieves22kVline,themaintransformers,thecentralizedmonitoringanddispatchingdepartmenttele-controlmonitoringofACswitchcabinet.
20grid-tieinverterswillbeappliedintheproject.Themonitoringandprotectionofeachinverterisachievedbyitsinnerdetectingsystemandprotectiondevice.1setofenvironmentalmonitoringsystemisequippedtomonitortheenvironmentconditions.PowermeasurementofthePVpowerstationwillbeattheinterfacepointtothegrid.
1.6.3Communication
ThecommunicationofSamoa’s5MWon-gridPVpowerprojectincludessystemcommunication,administrationcommunicationandinnerstationdispatchcommunication.
1.6.4Construction
Thetotalcapacityoftheprojectis5.0176MWwith17920280Wsolarmodules,1120supportsoffixedinstallationstyle,five1250KVAtransformersandinterfacetogridthrough22KVclasspowerline.CivilengineeringofthePVpowerstationincludesbaseofPVmodules,fiveACandDCpowerdistributionrooms,comprehensivebuilding,comprehensivepumpingstation,sand-proofwall,insideroad,etc.Accordingto(GB50011-2001),theComprehensiveBuilding,AC-DCpowerdistributionroom,andcomprehensivepumpingroomsbelongtoCcategories,seismicintensityof7degrees,thebasicdesignofthegroundaccelerationvalueof0.10g.
Accordingtositeconditions,solarmodulefollowsthebasisof50m/sdesign.SinglearraytakesconcretereinforcementandgradeofC25.Thebaseis0.4mmhigherthansiteaverage,thedepth0.6m,andtheconcretepouringofonepointis0.256m3.
ThePVpowerstationinthewindyarea,thecombinationofengineeringandbiologicalmeanswillbeadoptedforwindproofatthisstage.Thatis,building2.5mheightwallaroundthePVpowerstationandplantingpoplaroutsideofthewall.What’smore,PVmodules,supportsandbasesaresand-proofdesigned.
1.7Fireprotection
A.PVpowerstationisnotequippedwithfirefightingorganization,butapart-timefirefightershouldbeemployed.Atinitialstage,firewillbehandledbypersonnelfromtheinternalstation,andmeanwhilewithnotificationofthelocalfirebrigadetofightagainstfires;
B.Thefireengineeringdesignoftheprojectadoptstheintegratedfiretechnicalmeasuresincludethefireprevention,monitoring,alarm,control,firefighting,smokeexhaustion,andescape.Theaimistoreducethepossibilityoffire.Oncehappens,itcanbeextinguishedinashorttimeandthelosscanbereducedtoaminimum,whileensuringthesafetyoffireevacuation;
C.PVpowerstationfirecontrolroomisintegrateddesignedwiththemainbuildingcontrolroom;
D.Firefacilitiesandequipmentsaresetaccordingtotheimportanceofproductionandthedegreeoffirerisk;
E.FireservicephoneisinstalledforeachimportantsiteinPVpowerstation.
1.8Organizationstru