道路绿化工程进度计划、网络图.doc
《道路绿化工程进度计划、网络图.doc》由会员分享,可在线阅读,更多相关《道路绿化工程进度计划、网络图.doc(7页珍藏版)》请在冰豆网上搜索。
迎宾路绿化工程(一标段)
技术标
目录
第一章工程概况及施工部署
一、工程概况···········································································································1
二、现场施工平面布置···························································································2
三、施工部署···········································································································4
第二章施工方案与技术措施
一、施工顺序··········································································································11
二、现场施工测量··································································································18
三、整理绿化地······································································································21
四、选苗、起苗、运输、种植··············································································22
五、养护措施··········································································································37
六、主要分部分项工程的施工工艺及施工方法··················································48
第三章质量管理体系与措施
一、质量保证体系··································································································61
二、质量保证措施··································································································63
第四章安全管理体系与措施
一、安全施工目标··································································································68
二、安全生产管理程序及体系··············································································68
三、安全生产管理措施··························································································70
第五章环境保护管理制度及措施
一、环境保护管理制度··························································································73
二、环境保护管理体系··························································································74
三、环境保护措施··································································································76
第六章施工总进度计划及保证措施
一、施工总进度计划安排的原则··········································································79
二、施工工期··········································································································79
三、施工进度计划图······························································································81
第七章资源配备计划
一、劳动力配置计划······························································································82
二、主要施工机械设备配置计划··········································································83
三、材料进场计划··································································································83
第八章主要项目管理人员
一、项目组织管机构······························································································84
二、各工作岗位职责······························································································85
第九章施工设备、试验、检测仪器设备··························································89
迎宾路绿化工程(一标段)施工进度计划横道图
序号
工作名称
持续
时间
工期(30日历天)
2
4
6
8
10
12
14
16
18
20
22
24
26
28
30
1
施工准备
2
2
种植土回填
2
3
土地整理
2
4
喷灌设施安装
3
5
树穴定位、开挖
5
6
树木种植
5
7
乔木种植
5
8
灌木种植
5
9
地被花卉种植
8
10
场地清理
2
11
养护管理(至养护期满)
20
12
竣工验收
1
迎宾路绿化工程(一标段)施工进度计划网络图
6
8
施工准备
2
种植土回填
2
喷灌设施安装
3
树森种植
5
乔木种植
5
土地
2整理
树穴定位开挖
5
灌木种植
5
地被花卉种植
8
场地清理
2
竣工
验收
1
养护管理
20
12
11
10
9
7
5
3
2
1
4