3.ConstructionArrangement
4.ControltheConstructionSchedule
5.ConstructionOrganization
SECTION-2:
CIVILWORKS
1.ScopeofWorks
2.Earthwork
3.ConcreteWork
4.GroutingWork
5.RoadandPavingWorks
SECTION-3:
UNDERGROUNDPIPING
1.General
2.InstallationofCarbonSteelPipe
3.InstallationofGalvanizedSteelPipe
4.InstallationofConcretePipe
5.InstallationofPVCPipe
SECTION-4:
BUILDINGWORKS
2.InstallationofHVACSystem
3.SteelWork
SECTION-5:
ATTACHMENTDRAWINGS
SECTION-1GENERAL第一章概述
1.GENERALINFORMATION总说明
1.1NameofProject项目名称
BASFIntermediatesTHF/Poly-THFProject,Caojing,China,CivilWorks,UndergroundPiping&
BuildingWorks.中国上海漕泾巴斯夫中间体四氢呋喃/聚四氢呋喃项目的土建、地下管道和建筑工程
1.2.NameofOwnerandContractor业主和承包商名称
Owner:
BASFChemicalsCompanyLimited
业主:
巴斯夫化学有限公司
Contractor:
TechnipTianchenChemicalEngineeringCompanyLimitted
承包商:
德希尼布-天辰化学工程有限公司
TheContractorisentrustedbyOwnertorepresentandactonbehalfofOwner,withtheengineering,procurement,andconstructionmanagementoftheproject.
业主委托承包商代表业主负责项目的设计、采购和施工管理。
1.3.ProjectInformation项目简介
BASFChemicalsCompanyLimited,China,intendstobuildanew80000t/yearTetrahydrofuran(THF)plant,a60000t/yearPolyThfplantandinfrastructureplantattheShanghaiChemicalIndustryPark(SCIP)intheCaojingArea,PeopleRepublicofChina(PRC).在中国漕泾上海化学工业区(SCIP)内,巴斯夫(中国)化学有限公司计划新建一个年产80000吨四氢呋喃和年产60000吨聚四氢呋喃装置及
TheTHF,Poly-THFandinfrastructureplantistobeastandalonefacilitybutsomeutilitiesandancillaryfacilitieswillbeconnectedwithSCIPfacilities.TheplantwillcomprisesProcessUnits,Utilities,Offsitesincludingtankfarm,roadloading/unloading,infrastructurefacilitiesincludingControlBuildingandAdministrativeBuildingsandBuildingsforotherservices.AsiteJettyistobeset-upwith600Tonunloadingcapacity.四氢呋喃/聚四氢呋喃装置是一个独立设施,但一些公用和辅助设施是和SCIP的设施相关的。
这个装置包含工艺装置、公用工程、装置外的罐区及道路装卸设施和控制室、行政管理楼等其他服务建筑。
该地方已建成了拥有600吨装卸能力的码头。
TheProjectsiteisabout56kmawayfromtheShanghaiCityand60kmfromPudongInternationalAirport.Itisabout15kmfromtheShanghaiPetrochemicalCorporation.Itsgeographiclocationis120o28’Eand30o46’N.Thesiteisareclaimedarea.项目地点距离上海市中心大约56公里,距离浦东国际机场60公里。
离上海石化公司大约15公里。
它的地理位置是东经120o28’、北纬30o46’。
场地属于填海再造地区。
2.SCOPEOFWORKS工程范围
2.1CivilWorks土建工程
Constructionofcivilworksshallincludethefollowingarea:
土建工程的施工包括如下方面:
a)GeneralArea总图
b)THFProduction四氢呋喃生产
c)CentralBoiler锅炉中心
d)FlareStack火炬
e)IsobutaneStorage异丁烷仓库
f)Poly-THF聚四氢呋喃
g)UsedFFWaterBasin/FFStorageTanks有效的消防水池/消防储罐
h)InterconnectingPiperack连接管架
i)CoolingTower冷却塔
j)Tankfarm罐区
k)RoadandParking道路和停车场
2.2UndergroundPipingWorks地下管道工程
UndergroundPipingWorksshallincludethefollowing:
地下管道工程包括如下:
a)PressurizedUndergroundPiping地下压力管道
-Firewater消防水
-Coolingwater冷却水
-Industrialwater工业水
-Potablewater生活水
b)GravityPiping
-Stormwater雨水
-Sanitarywater生活污水
-Wastewater废水
c)AssociatedEarthworksandtrenching相关土方开挖
d)Installationofgatevalve.闸阀安装
2.3BuildingWorks建筑工程
Buildingworksshallincludetothefollowingarea:
建筑工程包括如下方面:
a)ControlBuilding控制室
b)MainSubstation总变(配)电站
c)CoolingWaterSubstation冷却水变电所
d)GateHouse门卫
e)FireBrigadeHouse消防队车库
f)FirewaterPumpHouse消防水泵房
g)AnalyserHouse分析室
3.CONSTRUCTIONARRANGEMENT施工安排
3.1Preparation准备
UponsigningthecontractwiththeContractor,mobilizationshallbeproceededwithforthefollowingitemspriortotheissuancethenoticeofproceed.
a)Liaisonwiththerelevantauthorityforgrantingtemporaryusageoflandwherethesitefacilitiesshallbeinstalledassoonaspossible,suchasoffices,shops,warehousesandsoon.
b)RentandequipthelivingaccommodationsfortheConstructionContractorstaffandworkforcewithnecessaryfurnishings.
c)Organizeandarrangethemobilizationofthepioneerstaffteam,constructionplantandfacilities.
d)Installtemporarywaterandelectricalpowersupply.
e)Beforeconstructiontemporaryroadworks,obstructionsonsiteshallbedemolishedandclearedaway.
f)TakeoverfromtheEngineerthesurveydatumpointsandestablishandtransfersurveycontrolnetworkwithdulyprotectionmeasures.
g)Builtupthesitelaboratoryandprovideitwiththefacilitiesasperthespecifiedrequirement.
h)SubmittheworkingscheduleofthefirstconstructionportionfortheEngineer’sreviewandapproval.向工程师提交首先施工部分的工作进度表,以供审核批准。
3.2SiteLayout现场布置
3.2.1LivingFacilities生活设施
Housingandcampshallbesetupclosetotheworksitewithlivingnecessities.Itshallbeabout1700m2forcaringandcateringofworkforceandstaff.
3.2.2SiteFacilities现场设施
Proposedworkingareaaround4500m2inthesitewillberemainedtoconstructnecessaryworkingfacilitiesaccordingtothedrawingoftemporaryconstructionfacilitieslayoutofferedbytheContractor.Sitefacilitiesshallincludethesiteoffice,stores,sitelaboratory,etc.
3.2.3ConcreteSupplySystem
Concreteshallbeboughtfromlocalconcretebatchingplantswithenoughcapacitytomeetthedemandofcontinuousconcretesupply.Mixertruckandconcretepumpwillbeusedforconcretedelivery.
3.2.4RebarProcessingShop
Arebarprocessingshopwithtwoprocesslineswillbelocatedintheworkingarea,whichiscapabletomeetthedemandofsiteconstruction.
3.2.5Pre-fabricationYardofStructuralSteelinSmallSize
Manufactureorprocessofsmallsteelcomponentsneededduringtheconstructionoftheprojectinacertainplaceshallbeprovidedwithintheworkingarea.
3.2.6SiteLaboratory
InstallingandprovidingthelaboratorywiththefacilitiesonsitefortestingandrequireditemsshallbeapprovedbytheContractorforitsconformitytospecificationpriortoputtingitintouse.
3.2.7TemporaryStore
Setupatemporarystorewiththeareaof180m2tohavethematerialandsemi-productinstockindoors.Anotheropenstorageareaabout3000m2shallbeused.
3.2.8ConstructionPowerSupply
PowersupplytositeshallbeconnectedwiththemainpowersuppliedbytheOwnerandContractor.Duringtheconstructionperiod,itshallbetheprovisionofagenerator.
3.2.9ConstructionWaterSupply
Watershallbeprovidedfromthemainwatersystemfortemporaryfacilitiescamp,workingsiterespectivelybyinstallingpipewithpumpsledtoeachconnection.Pipepressureandflowshallalsomeetthedemandsoffirefightingconsumption.
3.2.10CommunicationSystem
Eachofworkingsiteshallbeinstalledandprovidedwithtele-communicationsystemallowingformobilephonesandwalkie-talkies.
4.CONTROLTHECONSTRUCTIONSCHEDULE
4.1ManagementonProgress
Themanagementonprogressshallbesetforthandexecutedbymeansofclassifiedlevelsasfollowings:
(a)Theprogressscheduleatlevelclassone,asguidelineoffront-to-endschedule,isoftheOwner/ContractorandhisEngineer’scontrolforanddirectorytooverallworksandisofdeadlinetocompletionatfinalpoint.
(b)Theprogressscheduleatlevelclasstwo,subjecttoapprovaloftheengineer,isofmadebytheconstructioncontractorhimselfunderthatatlevelclassone.Thisprogressisusedincontrolofsub-contractorsandremainsunchangeableuponbeingconfirmed.
(c)Theprogressscheduleatlevelthree,underthatatclasstwo,isofmadebyworkteamsforcontrolinphases.Itcanbeusedforprogresscontrolatphaseuponapprovaloftheengineer.
(d)Theprogressscheduleatlevelclassfour,asbaseofconstructionresourcedemandforandexecutioninmonthlyprogressschedule,isprogrammedbyProjectManagementOffice.
(e)Theprogressscheduleatlevelclassfive,aweeklyprogressisofmadebytheengineer,whoisinchargeofprogressscheduleundermonthlyprogress.
4.2MeasuresofAssuranceforProgressFulfillment
Theprojectmanagerassignmentshallbeoffullyexperiencedinconstructionworks.Theexperiencedengineeringmanagementstaffandskilledworkersshallbeassignedorbefilledtothepostforsettinguphighefficienttositeoperation.Withadoptionofadvancednewtechnology,newequipmentandnewtechniques,theupliftefficiencycanassuretheworkprogressreachedandcompletingtheworkintermsofquality,safetyandtimeschedule.
Adequatestaffingandsufficientplant/equipmentprovisionshallbemadeasperprogressschedule.Allmeasurestotaketoguaranteetheperfectibilityandutilityofconstructionplantsandequipment.
Thematerialsrequiredbyandusedfortheprojectshallbesuppliedanddeliveredtositeontimetoscheduletosatisfytheneedoftheprogress.
Themultiplelevelprogressschedulemanagementmethodshallbeadopted.Theannual,quarter,monthlyandweeklyprogressshallbemadeaccordingly.Itistocheckdailyprogressimplementation.Thespecialmeasuresshallbemadeandtakentospeeduptheworksincasethattheprogressbeingrevisedasperactualrequirement.
Thespecialtechnicalmeasuresandplansshallbemadeforthekeyworkitemsandworkswithconsiderabledifficultiesinconstruction.
Theparticularconstructionmeasuresforrainyseasonshallbemadetominimizeconverseeffecttoexecutionoftheworks.Alldrainage,ditch,pipesshallbekeptfluentlyduringthecourseofconstructioninrainyseason.
Twoworkingshiftsdailyisrecommendedasmuchaspracticableandarrangedasthecasenecessaryduringthecourseofconstructionindraughtseasonsoastomakefullyuseofadvantageousweathercondition.Asthemeasure,it