日本造船厂协会标准造船格式合同批注版
SAJ标准造船合约格式
(Shipbuilders'AssociationofJapan,1974)
ARTICLEIDESCRIPTIONANDCLASS
1.DESCRIPTION:
TheVESSELshallhavetheBUILDER'SHullNo.............................................................andshallbeconstructed,equippedandcompletedinaccordancewiththefollowingofthiscontract,andtheSpecificationandtheGeneralArrangementPlan(hereincollectivelycalledthe"Specification")signedbyeachofthepartiesheretoforidentificationandattachedheretoandmakeanintegralparthereof.
2.DimensionsandCharacteristics
Length,overall....................................................................................................................
Length,betweenperpendiculars..............................................................................
Breadth,moulded..............................................................................
Depth,moulded..............................................................................
Designedloadeddraft,mouldedGrosstonnage..................................................................
PropellingMachinery..............................................................................
Deadweight,guaranteed..............................................................................
Trialspeed,guaranteed..............................................................................
Fuelconsumptionguaranteed..............................................................................
Thedetailsoftheaboveparticularsaswellasthedefinitionandmethodofmeasurementsandcalculationareasindicatedinthespecifications.
3.Classification,rulesandRegulations
TheVESSEL,includingitsmachinery,equipmentandoutfittings,shallbeconstructedinaccordancewiththerules(theeditionandamendmentstheretobeinginforceasofthedateofthisContract)ofandunderspecialsurveyof(船级社名字)(hereincalledthe"ClassificationSociety"),andshallbedistinguishedintheregisterbythesymbolof(船级符号)
DecisionsoftheClassificationSocietyastocomplianceornon-compliancewiththeclassificationshallbefinalandbindinguponbothpartieshereto.
TheVESSELshallalsocomplywiththerulesareregulationsandrequirementsofotherregulatorybodiesasdescribedintheSpecificationsineffectasofthedateofthisContract.
AllfeesandchargesincidentaltoClassificationandwithrespecttocompliancewiththeabovereferredrules,regulationsandrequirementsshallbeforaccountoftheBUILDER.
4.Subcontracting
TheBUILDERmay,atitssolediscretionandresponsibility,subcontractanyportionoftheconstructionworkoftheVESSEL.
5.Registration
TheVESSELshallberegisteredbytheBUYERatitsowncostandexpenseunderthelawsof...................................................withitshomeportof...................................................atthetimeofitsdeliveryandacceptancehereunder.
AETICALIIContractpriceandtermsofpayme
1.CONTRACTPRICE:
ThepurchasepriceoftheVESSELis__________,netreceivablebytheBUILDER(hereincalledthe"ContractPrice"),whichisexclusiveofthecostfortheBuyer'sSuppliesasprovidedinArticleXVIIhereof,andshallbesubjecttoupwardordownwardadjustment,ifany,ashereinaftersetforthinthisContract.
2.CURRENCY:
AnyandallpaymentsbytheBuyertotheBUILDERunderthisContractshallbemadeinnon-residentconvertiblefreeJapaneseYen(日元).
3.TERMSOFPAYMENT:
TheContractPriceshallbepaidbytheBuyertotheBUILDERininstallmentsasfollows:
(a)1stInstallment:
Thesumof________shallbepaiduponissuancebytheJapaneseGovernmentoftheExportLicensefortheVESSEL.
(b)2ndInstallment:
Thesumof________shallbepaiduponkeel-layingoftheVESSEL.
(c)3rdInstallment:
Thesumof________shallbepaiduponlaunchingoftheVESSEL.
(d)4thInstallment:
Thesumof_________plusanyincreaseorminusanydecreaseduetoadjustmentsoftheContractPricehereunder,shallbepaidupondeliveryoftheVESSEL.
4.METHODOFPAYMENT
(a)1stInstallment:
UponreceiptofacablenoticefromtheBUILDERofissuancebytheJapaneseGovernmentoftheExportLicensefortheVESSEL,theBUYERshallremittheamountofthisInstalmentbytelegraphic
(b)2ndInstallment:
UponreceiptofacablenoticefromtheBUILDERofkeel-layingoftheVESSELhavingbeenmade,theBUYERshallremittheamountofthisinstalmentbytelegraphictransferto_____________(船厂银行)fortheaccountoftheBUILDER
.
(c)3rdInstallment:
UponreceiptofacablenoticefromtheBUILDERoflaunchingoftheVESSELhavingbeenmade,theBUYERshallremittheamountofthisinstalmentbytelegraphictransferto_____________(船厂银行)fortheaccountoftheBUILDER
(d)4thInstallment:
TheBuyershall,atleastseven(7)dayspriortothesche