市次干路道路雨水污水工程施工组织设计技术标.docx
《市次干路道路雨水污水工程施工组织设计技术标.docx》由会员分享,可在线阅读,更多相关《市次干路道路雨水污水工程施工组织设计技术标.docx(78页珍藏版)》请在冰豆网上搜索。
![市次干路道路雨水污水工程施工组织设计技术标.docx](https://file1.bdocx.com/fileroot1/2022-10/23/0a823ec7-9ded-4b4a-83a2-97ac81d93c61/0a823ec7-9ded-4b4a-83a2-97ac81d93c611.gif)
市次干路道路雨水污水工程施工组织设计技术标
技
术
标
部
分
第一章总则··············································3-4
一、编制说明············································3-4
二、编制依据············································3-4
第二章工程概况··········································3-6
一、工程简介············································3-6
二、道路工程············································3-6
三、排水工程············································3-9
四、施工注意事项·········································3-10
五、工期···············································3-11
六、质量目标···········································3-11
七、安全目标···········································3-12
八、工程特点···········································3-12
第三章施工方案与技术措施·······························3-13
一、施工方案···········································3-13
(一)施工原则·······································3-13
(二)施工计划及施工方案安排·························3-13
二、施工技术措施·······································3-13
(一)污水工程·······································3-13
(二)雨水工程·······································3-19
(三)道路工程·······································3-24
第四章质量管理体系与措施·······························3-44
一、质量保证措施·······································3-44
二、施工准备阶段质量控制································3-45
三、施工阶段的质量控制··································3-46
四、竣工验收阶段质量控制·······························3-47
五、工程质量控制的实验方法·······························3-47
六、竣工资料的整理及评定·······························3-47
第五章安全管理体系与措施·······························3-49
一、建立安全生产保证体系·······························3-49
二、安全生产目标·······································3-49
三、交通疏导安全措施···································3-49
四、确保安全生产的技术组织措施·························3-50
五、应急组织及处理突发事件的措施·······················3-52
第六章文明及环保管理体系与措施·························3-55
一、文明施工管理体系与措施·······························3-55
二、环境保护管理体系与措施·····························3-57
第七章工程进度计划与措施·······························3-60
一、施工原则···········································3-60
二、工程施工计划·······································3-60
三、施工进度计划图·····································3-60
四、确保工期的技术组织措施·····························3-61
五、施工准备工作·······································3-63
第八章施工期间的保通措施································3-66
第九章配合措施·········································3-67
第十章资源配备计划·····································3-69
一、劳动力配备计划·····································3-69
二、主要施工机械及仪器配备计划··························3-70三、材料配备计划·······································3-71
第十一章项目管理班子的配备·······························3-72
一、项目管理机构组成···································3-72
二、明确项目部各职人员职责·······························3-73
第十二章施工总平面图··································3-78
第十三章质量通病的防治措施······························3-80
第十四章冬、雨季施工措施·································3-92
一、冬季施工措施·······································3-92
二、雨季施工措·施········································3-93
第十五章按报价完成工程建设的技术和管理措施·············3-97
一、确保按报价完成工程建设的技术措施···················3-97
二、确保按报价完成工程建设的管理措施···················3-97
附表一拟投入的主要施工设备表···························3-99
附表二拟配备的试验和检测仪器设备表·····················3-101
附表三劳动力计划表····································3-102
附表四施工进度表······································3-103
附表五施工总平面图····································3-104
附表六临时用地表······································3-105
施工组织设计
第一章总则
一、编制说明
1、我公司经过认真研究招标文件、设计图纸,仔细考察工程现场,对工程所处的位置进行综合研究,结合我公司多年的施工经验和目前的施工技术,组织编制了本施工组织设计。
2、在本工程组织设计编制中,充分考虑了各关键工序和重点工序及相互间的衔接与协调的可行性,及其相应的施工技术方案和工艺操作方法,本工程现场的地质条件、地上地下管线和交通情况可能对本工程产生影响,都作了充分的估计和准备。
3、如果我公司中标,我们将在施工的全过程密切配合建设及监理单位的工作,并与周边单位、村庄、社区群众协调好关系,创造良好的施工环境,确保本工程施工合同的全面履行。
4、本施工组织设计只对本次招标范围第4标段湖西路(郑上路~风茂街)污水、雨水、道路工程有效。
二、编制依据
1、郑州天一招标咨询有限公司《郑州市金桥路(桂园路~香山路)等4条道路工程施工招标文件》,编号ZZTY-2011-027;
2、郑州市金桥路(桂圆路~香山路)等4条道路工程施工招标答疑;
3、郑州市金桥路(桂圆路~香山路)等4条道路工程施工招标答疑
(二);
4、中铁第一勘察设计院集团有限公司:
郑州市湖西路(郑上路~风茂街)南段道路工程施工图设计(全一册);
5、《给水排水管道工程施工及验收规范》GB50268-2008;
6、《砌体工程施工质量验收规范》GB50203-2002;
7、《公路路面基层施工技术规范》TJ034-2000;
8、《公路沥青路面施工技术规范》JTGF40-2004;
9、《沥青路面施工及验收规范》GB5009-96;
10、《城镇道路工程施工与质量验收规范》CJJ1-2008;
11、郑州市建设委员会郑建[2007]98号文《关于促进新型墙体材料发展全面禁用粘土类墙体材料的通知》;
12、河南恒兴工程建设有限公司《程序文件》及《管理手册》。
第二章工程概况
一、工程简介
郑州市金桥路(桂圆路~香山路)等4条道路工程,包含道路、雨水、污水工程。
本施工组织设计为本次招标范围的第4标段—湖西路(郑上路~风茂街)道路、雨水、污水工程。
二、道路工程
1、郑州市湖西路(郑上路~风茂街)位于郑州市中原区西流湖以西,规划为南北向城市次干路,道路红线宽30m,路段全长1050m。
2、道路平面设计
湖西路南段共设3个曲线,最小曲线半径为200m,交叉口分别进行规范化交通控制设计。
3、道路纵断面设计
根据连接郑上路起点实测高程及规划路交叉口的规划高程进行控制。
最大坡度为2.0%,最小纵坡度0.45%。
4、道路横断面设计
湖西路南段横断面布置形式为:
6m(人行道)+18m(混行车道)+6m(人行道)。
道路设计标高为道路路面中心线标高。
5、路基、路面设计
⑴路基横断面布置
6m(人行道)+18m(混行车道)+6m(人行道)。
⑵一般路基工程
①边坡设计
局部有条件放坡的填方路段,边坡坡度为1:
1.5;挖方路段,边坡坡率为1:
1~1:
1.5。
②填料、压实度
路基填料均匀、密实,优先选用级配较好的砾类石、砂类石等粗粒土;挡土墙背优先选用渗水性良好的填料。
填方路基分层铺筑,均匀压实,并严格控制分层厚度,注意不同填料的填筑顺序。
土质路基压实度(重型)符合以下要求:
一般路堤,路面底面以下:
0~80cm不小于95%,大于80cm不小于93%。
零填方及路堑路面底面以下0~30cm的路床不小于95%。
③路基边坡防护工程
AK0+720~AK0+770段填方地段右侧边坡设扶壁式路肩挡土墙收坡,墙顶设防护栏杆。
挡土墙型采用悬臂式路肩挡土墙,挡土墙墙身、底板均采用C30混凝土现浇。
受力钢筋为Ⅱ级钢筋,分布筋为Ⅰ级钢筋,钢筋最小保护层厚度不小于3.0cm。
为控制沉降及增加承载力,挡土墙基底设1.0m碎石垫层