安全控制措施中英文Word下载.docx

《安全控制措施中英文Word下载.docx》由会员分享,可在线阅读,更多相关《安全控制措施中英文Word下载.docx(15页珍藏版)》请在冰豆网上搜索。

安全控制措施中英文Word下载.docx

8.1Generalprovisions

8.1.1Allworkerswhoareengagedinconstructionmustpasssafetyexaminationandhealthexamination,understandsafeoperationregulationsofdifferenttypesofwork.Beforeworkcanstart,techniciansmustgivesafetyinstructionsandsafetyinstructionstoworkersandspecifyworkingmethod,procedure,precautionsandpersonaldutiestoworkers.Afterthis,theworkersarerequiredtosignofftheinstructionrecordsforconfirmationandregistrationbeforetheyareallowedtostartworking.Anyworkerwhodoesnotundergoinstructionsisnotallowedtoworkonthesite.

8.1.2Itisnotallowedtodrinkalcoholduringtheworktime.Nooneisallowedtoenterthesiteintoxicated.Itisforbiddentoworkwhenaworkerisill.

8.1.3PeoplewhoenterthesitemustwearPPEcorrectly.Itisforbiddentowearslippers,highheelsorshoeswithnails;

allspecialtypeofworkerssuchaspersonwhoisengagedinhighvoltagetestmusthavecertificatesandbefamiliarwiththeirownwork.

8.1.4Testequipmentmustbestackedinordertidilybasedontheregulationssetupandcomplywithtransportationandfirefightingrequirements.

8.1.5Setupsufficientilluminationfornightshift.

8.1.6Workerswhoneedtoworkatheightmustwearharnessandhookittothesafetyropetoavoidfallingdownfromtheheight.

8.2Testinasafemanner

8.2.1Onlyelectricianisallowedtodismantleandassembleconstructionpowerconsumptionfacilities.

8.2.2Electricequipmentmustbeoperatedbasedontaginstructions.Itisforbiddentouseoneswitchforseveralpowerconnections.

8.2.3Itisnotallowedtohookthewiredirectlytotheswitchbladeordirectlyplugwireintopowersocket.Theswitchoftestdevicesshouldadoptdouble-poleswitchwithobviousbreakpointandreliableoverloadprotectiondevice.

8.2.4Whenworksinthesite,basedonthevoltageclassoftheelectrifiedbodythetestingpersonnelmustkeepasafedistanceawayfromelectrifiedbody,whichshouldnotbelessthanthedistanceregulatedinthe‘safetyregulations’.

8.2.5Themetalshellofthetesttoolsmusthavepropergrounding.Wiringbetweentestinstructionandequipmentmustbefirmandreliable.AfterinsulationresistancemeasuringandDCtestisfinished,itisnecessarydischargethetestedobjectsthoroughly.

8.2.6Thetestshouldbeconductedunderthecircumstancewhentheweatherisgood.Ifstrongwindandthunderstormtakeplace,itisnecessarytostopthetest.

8.2.7Afterthetestiscomplete,testingpersonnelmustdismantletemporarygroundingwireandinspectthetestedequipmentandcleanthetestingspot.

8.3HousekeepingMeasures

8.3.1Afterthetestiscompleted,theprincipal‘finishthework,cleanthesiteandtakeawaythematerial’shouldbeabidedby.

8.3.2Thewallandbarricadingestablishedonthesitemustbestable,tidyandnice.

8.3.3Testingpersonnelmustestablishawarenesstoprotectfinishedproducts.Itisforbiddentodismantle,takeawayandpaintthefinishedproductsarbitrarilywithoutpermission.

8.3.4Itisnotallowedtoworkafterdrinking.

8.3.5Nosmokingisallowedwithinthetestingspot.Noopenfireisallowedforkeepingwarmwithintestingspot.

8.3.6Whenleavetheworkingarea,itisnecessarytoshutdownthepowersupplyandlockthewindowtoprotecttheworkingareafromtheft.

8.4EnvironmentProtectionMeasures

8.4.1Thetagsandlabelsontheconstructionsitemustbetidy,aestheticwitheye-catchingslogans.

8.4.2Temporaryworkonthesitemustbestandardizedandproceedingoodorder.Keepcircumstanceinsideandoutsidethetoolsstorageroomcleanandsanitary.

8.4.3Testequipmentandtestdevicesmustbestacktidilyingoodorderinthedesignatedarea.Itisnecessarytoabidebytheprincipal‘finishthework,cleanthesiteandtakeawayallmaterials’

8.4.4Testequipmentmustbecleanandtidy.Powersupplypanelsmustbestandardizedwithcompletelocks.Safetyprotectionmeasuresarecompletedandreliable.

8.4.5Strictlycomplywithpublicmoralities,professionalethics,professionaldisciplines.Disposeoftheneighborrelationshipwithothercompaniesinthesiteproperly.Andtrybesttogetthesupportandunderstandingfromtherelevantcompanies.

8.4.6Thecablerackoftemporaryconstructionpowersupplymustmeetsafetyrequirements,powerpanelsmustbestandardizedandtheilluminationmustbearrangedproperly.

8.4.7Inordertopreventthetrashfromspreadingtopublicarea,roads,anditisnecessarytostoptheslagandresiduefromspilling.

8.5EmergencyPlan

8.5.1ThemanagerofHSEdepartmentisresponsibleforinitiatingtoorganizingemergencyrespondgroupandsetupclinicsbothonthesiteandnearbyofficearea.Designateconstructorsemergencymusterpointonthesite.

8.5.2Firstaidforelectricshock:

cutoffthepowersupplyimmediately,pulldowntheswitch,turnoffthepowersupplyswitchandunplugtheplug.Makesurethatthevictimhurtbyelectricshockisdisconnectedfromthepowersupplyandsendhim/hertothesiteclinicfortreatment.

8.5.3Onceemergencyaccidenttakeplaceinthesite,therelevantpersonnelmustreportittotheemergencycommandgroupimmediately.Meanwhile,itisnecessaryforhimtoinformHSEemergencytreatmentpersonnelonduty.ProjectdepartmentHSEneedstomarkoutthecautionareabasedonthesiteactualsituation.Andmakesuretheaccessforsalvageisaccessibleandunimpeded.Gathertheunauthorizedpersonneltotheemergencymusterpoint.Aftercountinguptheheadofthepersonnel,evacuatethembasedonthepreassignedevacuationroutes.

8.5.4Medicalstaffintheclinicmustrescuetheinjuredpersonorgivetheinjuredpersonfirstaidbasedontheinjuredpersonstatus.Iftheinjuredpersonneedstobesenttohospitalforsalvage,itisnecessarytodial120immediatelyfortheambulanceservice.

9.ConstructionRiskandHousekeepingForecastControlPlanTable

9.1ConstructionRiskControlPlanTable

ConstructionRiskControlPlanTable

No.:

CompilationDate:

Rev:

Project:

UnitNo.:

ConstructionItem:

synchronousgeneratortest

No.

RiskDescription

SafetyandTechniqueMeasuresProposedtoTake

RiskLevel

Control

Company/personResponsible

Method

Opportunity

Team

Department

Signature

1

Testequipmentbadgrounding

Theshellofthetestequipmentmusthavepropergrounding.Thewiringbetweentestinstrumentandequipmentmustbereliable.Thepowerswitchofthetestdeviceshouldhaveobviousbreakpointwithdouble-poleswitchblade.Further,liableoverloadprotectiondevicemustbeinplace.

G

A

T

2

Nobarricadingfortestarea

Testareamustbebarricadedandhangupwarningboardwith‘Stop!

HighVoltageDangerous!

’anddesignatededicatedpersontosupervise.Unauthorizedpersonisnotallowedtoenterthetestarea.

W

3

Nosupervisionduringvoltageboosting

Beforeteststarts,personinchargeshouldspecifythesafetymattersthatrequirecloseattentiontoalltestingpersonnel.Clarifytheworkdivisionanddesignatededicatedpersonforsupervision.

J

S

4

Notimplementingloudlyverbalinstruction

Duringthetest,itisnecessarytodesignatesomeonetosuperviseandgiveverbalinstructionloudly.Duringthetest,thetestingpersonnelmustbeconcentrated.Whenabnormalcasetakesplace,itisnecessarytoinvestigatethereasonbeforecontinuethetest.

Y

5

Fallingfromheight

Ifspecialtoolsforworkingatheightarerequired,itisnecessarytotakemeasurestoprotecttheceramicparticlesfrombeingdamagedandprotectworkersfromfallingdown.

6

AfterinsulationresistancemeasurementandDCtestarefinished,donotthoroughlydischargethetesteditems.

Inordertoprotecttheequipmentandsecurepersonalsafety,itisnecessarytodischargethetesteditemsthoroughlyafterDCtestandinsulationresistancemeasurementarecompleted.

7

Workersblunderintowrongroomanddonotkeepsafedistanceawayfromtheelectrifiedbody

Workpermitsystem,worklicensesystem,worksupervisionsystem,workcease,transferandterminationmustbecarriedout.Thetestingpersonnelmustkeepasafedistancewhichcannotbelessthanthevaluewritteninthe‘safetyregulations’awayfromtheelec