1号办公楼清单工程量计算式Word格式文档下载.docx
《1号办公楼清单工程量计算式Word格式文档下载.docx》由会员分享,可在线阅读,更多相关《1号办公楼清单工程量计算式Word格式文档下载.docx(86页珍藏版)》请在冰豆网上搜索。
![1号办公楼清单工程量计算式Word格式文档下载.docx](https://file1.bdocx.com/fileroot1/2022-10/13/ab3fe956-7c5a-458b-8346-0dca9490c25f/ab3fe956-7c5a-458b-8346-0dca9490c25f1.gif)
52.2
参照《2014省建筑工程消耗量》下册垂直运输工程定额说明:
塔吊基础开挖土方52.2m3
5
回填方
269.37
基础回填:
V=挖方体积-室外地坪以下基础体积=504+8.05-40.32(垫层)-251.85(满堂基础)-0.7×
0.6×
0.55×
20(柱子)-24.72×
0.55(砖基础)-0.149×
0.55(构造柱)=201.58m3
室回填:
V=主墙间面积回填厚度
大厅:
(6.9-0.2)×
(6+0.3-0.25+0.1)×
(0.45-0.25)=8.24m3
办公室:
(6+0.35-0.25-0.1+6-0.2+6-0.2+3.3+0.35-0.25-0.1)×
(6+0.3-0.25-0.1)×
(0.45-0.236)
=26.61m3
走廊:
(3-0.2)×
(22.9-0.252)×
(0.45-0.236)=13.57m3
楼梯间:
(3.3-0.1+0.35-0.25)×
(0.45-0.236)=4.34m3
会议室:
(0.45-0.25)
=7.97m3
厕所:
[(6+0.35-0.25-0.2-0.1)×
(4.5+0.3-0.25-0.1)+(6-0.35-0.25-0.1)×
(1.5-0.2)]×
(0.45-0.234)
=7.06m3
室回填:
8.24+26.61+13.57+4.34+7.97+7.06=67.79m3
小计:
201.58+67.79=269.37m3
6
塔吊基础回填方
8.3
塔吊基础回填方8.3m3
附录D砌筑工程
7
砖基础,M5水泥砂浆
24.72
砖基础高1.0m。
外墙砖基础厚250mm墙砖基础厚200mm
外墙砖基础:
L=(22.9+15.6)×
2-(0.7×
10+0.6×
8)=65.2m
砖基础:
L=(6-0.6)×
6+(4.5+0.3-0.25-0.1)+(6+0.35-0.25-0.1)=42.85m
V=65.2×
0.25×
1.0+42.85×
0.2×
1.0-(0.25×
1.0×
+0.03×
2×
2)=24.87-(Z1)0.149=24.72m3
8
粒砌块墙体,M5泥合砂浆
177.55
外墙砖厚250mm,墙砖厚200mm
外墙V=65.2×
(3.6-0.7)×
3层=141.81m3
墙V=(6-0.6)×
6×
3层+[(4.5+0.3-0.25-0.1)+(6+0.35-0.25-0.1)]×
(3.6-0.5)×
2层+[(4.5+0.3-0.25-0.1)+(6+0.35-0.25-0.1)]×
(3.6-0.15)×
1层=76.54m3
女儿墙:
V=(22.9-0.25+15.6-0.25)×
0.54
=10.26m3
扣门窗所占体积:
-0.9×
2.4×
20+0.75×
2.1×
6+
4.2×
2.9×
0.25+1.5×
18+3×
9+3.3×
5)=-48.83m3
扣过梁体积:
-0.69m3
扣构造柱体积:
-(1.69-0.149)=-1.54m3
141.81+76.54+10.26-48.83-0.69
-1.54=177.55m3
9
台阶平台处3:
7灰土垫层
2.43
V=(1.8+1.2)/2×
0.3×
5.4=2.43m3
10
砾石灌浆垫层地面
46.34
(42.21+5.04+40.05+33.83+187.8)×
0.15=46.34m3
11
地面C10砼垫层
13.76
(42.21+5.04+40.05+187.8)×
0.05=13.76m3
附录E混凝土及钢筋混凝土工程
12
C15混凝土垫层
40.32
满堂基础基础垫层:
V=24×
0.1=40.32m3
13
2.7
塔吊基础垫层2.7m3
14
C30混凝土满堂基础
251.85
底板:
V=23.8×
16.6×
0.6=237.05m3
基础梁:
JZL1(4)V=0.5×
(0.8-0.6)×
2)=8.86m3JZL2(3)V=0.5×
2)=5.94m3
小计:
251.85m3
15
C30混凝设备基础
33.75
塔吊基础33.75m3
16
C30混凝土矩形柱
98.7
KZ1:
V=0.7×
(1.0+10.75)×
20(个)=98.7m3
17
C25混凝土构造柱
1.69
Z1:
V=0.25×
(1+1.8)×
2+0.25×
(5.4-3.6)×
2+马牙槎0.03×
(1+1.8)×
2+0.03×
1.8×
2=0.69m3
女儿墙上GZ1:
V=0.25×
0.54×
24+马牙槎0.03×
24=1.0m3小计:
1.69m3
18
C30混凝土有梁板
214.14
标高3.55、7.15处梁:
KL1(4)=0.3×
0.7×
(22.2-0.35×
2-0.7×
3)=4.07m3
KL2(4),KL3(4),KL4(4)同KL1(4)
3根×
4.07m3=12.21m3
L1
(1)=0.25×
0.5×
(6+0.35-0.3-0.15)=0.74m3
KL5(3)=0.3×
(15-0.3×
2-0.6×
2)=2.77m3
KL6(3),KL7(3),KL8(3),KL9(3)同KL5(3)
4根×
2.77=11.08m3
L2
(1)=0.25×
0.45×
(4.5-0.125)=0.49m3
4.07+12.21+0.74+2.77+11.08+0.49=31.36×
2层=62.72m3
标高10.75处梁:
WKL1(4)=0.3×
3)×
4=16.28m3
WKL2(3)=0.3×
2)×
5根=13.85m3
16.28+13.85=30.13m3
梁合计:
62.72+30.13=92.85m3
标高3.55、7.15处板:
100厚的板:
S=(6+0.35-0.3-0.25-0.15)×
(4.5-0.125)+(6+0.05-0.15)×
(1.5-0.125-0.15)+(3.3+0.35-0.15-0.3)×
(6-0.15)
+(22.2+0.35-0.3+0.35-0.3)×
(3-0.15×
2)=110.88m2
V=110.88×
0.1=11.09m3×
2层=22.18m3
150厚的板:
(6×
2+6.9+0.35-0.3×
3-0.15)×
=106.47m2
(6+6.9-0.15×
2-0.3)×
(6-0.15)=71.96m2
V=(106.47+71.96)×
0.15×
2层=53.53m3
标高10.75处板:
[(3.3+0.35-0.3-0.15)×
(6-0.15)×
2+(22.2+0.35×
2-0.3×
2)]×
0.1=97.65m2×
0.1=9.77m3
(6.9-0.15)×
2=18.43m3×
2=36.86m3
扣柱头:
(0.15+0.1)/2×
20×
3层=--3.15m3
板合计:
22.18+53.53+9.77+36.86-3.15=119.19m3
梁板总计:
92.85+119.19=212.04m3
19
C30混凝土直形楼梯
79.86
S=(3.3+0.35-0.1-0.25)×
(6+0.3-0.25-0.15)=39.93m2
×
2=79.86m2
20
C20混凝土散水
75
散水宽1.0m,长L=(22.9+2)×
2-(6.9-0.45×
2)+15.6×
=75mS=75×
1=75m2
21
C15混凝土台阶
㎡
7.56
S=(6.9-0.45×
0.9+(1.5-0.3)×
0.9×
2=7.56㎡
22
C25混凝土压顶
1.37
V=0.3×
0.06×
[(22.9-0.25)×
2+(15.6-0.25)×
2]=1.37m3
23
预制过梁,C25
0.73
M2过梁:
V=0.2×
0.12×
(0.9+0.25)×
20=0.55m3M3过梁:
(0.75+0.47)×
6=0.18m3
0.73m3
24
现浇混凝土圆钢φ6.5
t
1.045
1.045t(具体计算过程详钢筋工程量计算表)
25
现浇混凝土圆钢φ8
4.143
4.143t(具体计算过程详钢筋工程量计算表)
26
现浇混凝土圆钢φ10
25.283
25.283t(具体计算过程详钢筋工程量计算表)
27
现浇混凝土圆钢φ12
0.485
0.485t(具体计算过程详钢筋工程量计算表)
28
现浇混凝土Ⅱ级螺纹钢φ12
4.86
4.86t(具体计算过程详钢筋工程量计算表)
29
现浇混凝土Ⅱ级螺纹钢φ14
0.651
0.651t(具体计算过程详钢筋工程量计算表)
30
现浇混凝土Ⅱ级螺纹钢φ16
1.69t(具体计算过程详钢筋工程量计算表)
31
现浇混凝土Ⅱ级螺纹钢φ18
0.253
0.253t(具体计算过程详钢筋工程量计算表)
32
现浇混凝土Ⅱ级螺纹钢φ20
18.544
18.544t(具体计算过程详钢筋工程量计算表)
33
现浇混凝土Ⅱ级螺纹钢φ22
0.38
0.38t(具体计算过程详钢筋工程量计算表)
34
现浇混凝土Ⅱ级螺纹钢φ25
45.619
45.619t(具体计算过程详钢筋工程量计算表)
35