1、外文翻译高效生产一个关于采煤机截割的次序的问题精品翻译部分英文原文High Productivity A Question of Shearer Loader Cutting SequencesK. Nienhaus, A. K. Bayer & H. Haut, Aachen University of Technology, GER1 AbstractRecently, the focus in underground longwall coal mining has been on increasing the installed motor power of shearer loade
2、rs and armoured face conveyors (AFC), more sophisticated support control systems and longer face length, in order to reduce costs and achieve higher productivity. These efforts have resulted in higher output and previously unseen face advance rates. The trend towards “bigger and better” equipment an
3、d layout schemes, however, is rapidly nearing the limitations of technical and economical feasibility. To realise further productivity increases, organisational changes of longwall mining procedures looks like the only reasonable answer. The benefits of opti-mised shearer loader cutting sequences, l
4、eading to better performance, are discussed in this paper.2 IntroductionsTraditionally, in underground longwall mining operations, shearer loaders produce coal using either one of the following cutting sequences: uni-directional or bi-directional cycles. Besides these pre-dominant methods, alternati
5、ve mining cycles have also been developed and successfully applied in underground hard coal mines all over the world. The half-web cutting cycle as e.g. utilized in RAG Coal Internationals Twentymile Mine in Colorado, USA, and the “Opti-Cycle” of Matlas South African shortwall operation must be ment
6、ioned in this context. Other mines have also tested similar but modified cutting cycles resulting in improved output, e.g. improvements in terms of productiv-ity increases of up to 40 % are thought possible。Whereas the mentioned mines are applying the alternative cutting methods according to their s
7、pe-cific conditions, e.g. seam height or equipment used, this paper looks systematically at the differ-ent methods from a generalised point of view. A detailed description of the mining cycle for each cutting technique, including the illustration of productive and non-productive cycle times, will be
8、 followed by a brief presentation of the performed production capacity calculation and a summary of the technical restrictions of each system. Standardised equipment classes for different seam heights are defined, after the most suitable and most productive mining equipment for each class are se-lec
9、ted. Besides the technical parameters of the shearer loader and the AFC, the length of the long-wall face and the specific cutting energy of the coal are the main variables for each height class in the model. As a result of the capacity calculations, the different shearer cutting methods can be grap
10、hically compared in a standardised way showing the productivity of each method. Due to the general char-acter of the model, potential optimisations (resulting from changes in the cutting cycle and the benefits in terms of higher productivity of the mining operation) can be derived. 3 State-of-the-ar
11、t of shearer loader cutting sequencesThe question “Why are different cutting sequences applied in longwall mining?” has to be an-swered, before discussing the significant characteristics in terms of operational procedures. The major constraints and reasons for or against a special cutting method are
12、 the seam height and hard-ness of the coal, the geotechnical parameters of the coal seam and the geological setting of the mine influencing the caving properties as well as the subsidence and especially the length of the longwall face. For each mining environment the application of either sequence r
13、esults in different production rates and consequently advance rates of the face. The coal flow onto the AFC is another point that varies like the loads on the shearer loader, especially the ranging arms and the stresses and the wear on the picks. A thorough analysis is necessary to choose the best-s
14、uited mining cycle; therefore, general solutions do not guarantee optimal efficiency and productivity. A categorization of shearer loader cutting sequences is realised by four major parameters . Firstly, one can separate between mining methods, which mine coal in two directions meaning from the head
15、 to the tailgate and on the return run as well or in one direction only. Secondly, the way the mining sequence deals with the situation at the face ends, to advance face line after extract-ing the equivalent of a cutting web, is a characteristic parameter for each separate method. The nec-essary tra
16、vel distance while sumping varies between the sequences, as does the time needed to per-form this task, too. Another aspect defining the sequences is the proportion of the web cutting coal per run. Whereas traditionally the full web was used, the introduction of modern AFC and roof sup-port automati
17、on control systems allows for efficient operations using half web methods. The forth parameter identifying state of the art shearer loader cutting sequences is the opening created per run. Other than the partial or half-opening method like those used in Matlas “Opti-Cycle”, the cutting height is equ
18、al to the complete seam height including partings and soft hanging or footwall material. Bi-directional cutting sequenceThe bi-directional cutting sequence, depicted in Figure 1a, is characterised by two sumping opera-tions at the face ends in a complete cycle, which is accomplished during both the
19、forward and return trip. The whole longwall face advances each complete cycle at the equivalent of two web distances by the completion of each cycle. The leading drum of the shearer cuts the upper part of the seam while the rear drum cuts the bottom coal and cleans the floor coal. The main disadvant
20、ages of this cutting method are thought to be the unproductive time resulting from the face end activities and the complex operation. Therefore, the trend in recent years was to increase face length to reduce the relative impact of sumping in favour of longer production time.Uni-directional cutting
21、sequenceIn contrast to the bi-directional method, the shearer loader cuts the coal in one single direction when in uni-directional mode. On the return trip, the floor coal is loaded and the floor itself cleaned. The shearer haulage speeds on the return trips are restricted only by the operators move
22、ment through the longwall face, or the haulage motors in a fully automated operation. The sumping procedure starts in near the head gate, as shown in Figure 1b. The low machine utilisation because of cutting just one web per cycle is the main disadvantage of the uni-directional cutting sequence. Bes
23、ides the coal flow can be quite irregular depending on the position of the shearer in the cycle.Half web cutting sequence The main benefit of half web cutting sequences is the reduction of unproductive times in the mining cycle, which results in high machine utilisation. This is achieved by cutting
24、only a half web in mid face with bi-directional gate sequences as shown in Figure 2a. The full web is mined at the face ends, with lower speeds allowing faster shearer operation in both directions in mid seam. Beside the realisation of higher haulage speeds, the coal flow on the AFC is more balanced
25、 for shearer loader trips in both directions.Half-/partial-opening cutting sequenceThe advantage of the half- or, more precisely, partial- opening cutting sequence is the fact that the face is extracted in two passes. Figure 2b shows that the upper and middle part of the seam is cut during the pass
26、towards the tailgate. Whereas the last part of this trip for the equivalent of a ma-chine length the leading drum is raised to cut the roof to allow the roof support to be advanced. On the return trip the bottom coal is mined with the advantage of a free face and a smaller proportion of the leading
27、drum cutting coal; consequently leading to less restrictions of the haulage speed due to the specific cutting energy of the material. The shearer sumps in mid seam near the head gate to the full web without invoking unproductive cycle time. Like for the trip the tailgate the leading drum has to be l
28、owered a machine length ahead of the main gate.4 Production capacity calculationsA theoretical comparison of the productivity between different mining methods in general, or in this case between different shearer loader cutting cycles, is always based on numerous assumptions and technical and geolog
29、ical restrictions. As a result, this production capacity calculation does not claim to offer exact results, although it does indicate productivity trends and certain parameters for each analysed method. The model works with so-called height classes varying the seam thicknesses between 2m and 5m in s
30、teps of 50cm. Equipment is assigned to each class, having been selected by looking at the best-suited technical properties available on the market 4. Apart from the defined equipment, it is assumed that the seam is flat and no undulations or geological faults occur. In the model, the ventilation and
31、 the roof support system represent no restrictions to the production. Since the aim of this model is to show ways to further increases in longwall productivity, the calculation is based on a fully automated system with no manual operators required at the face. The haulage speed of the shearer is the
32、refore only restricted by the AFC capacity, the cutting motors and the haulage motors respectively. The variable parameters in this comparison of the four cutting sequences are, (besides seam thick-ness) the specific cutting energy of the coal to be cut and the length of the longwall face. The forme
33、r varying between 0.2 and 0.4kWh/m, the latter between 100m and 400m in 50m intervals. The 100m shortwalls were deliberately selected, since they are coming more into focus for various reasons. Geotechnical aspects, like e.g. the caving ability of the hanging wall and faults, restrict long-wall panels in many places to maximum face le
copyright@ 2008-2022 冰豆网网站版权所有
经营许可证编号:鄂ICP备2022015515号-1