1、设备施工方案英文版设备施工方案(英文版)陕西有色天宏瑞科硅材料有限责任公司Shaanxi Nonferrous Tianhong REC Silicon Materials Co., Ltd 电子及光伏新材料产业化项目Silane硅烷区机电安装工程M&E Installation for Silane Areas of Electrical and Photovoltaic Industrialized Project 设备安装方案Equipment Installation Scheme 编制/ Prepared by:_审核/ Checked by:_批准/ Approved by:_陕西
2、建工安装集团有限公司SCEGC Installation Group Co., Ltd2016年6月26日June 26, 2016CONTENT一、工程概况Section I. Project Overview陕西有色天宏瑞科硅材料有限责任公司电子及光伏新材料产业化项目Silane区机电安装工程施工工程位于陕西省榆林市榆佳工业园区。Silane area M & E installation project sites at Yujia industrial Park of Yulin city for Shaanxi NonferrousTianhong REC Silicon Mater
3、ials industrialization Co., Ltd 硅烷区设备安装种类多,其中包括泵类104台,整体容器类198台,整体塔器10台,换热器类97台,压缩机类5台,反应器类8台,储气罐4台,加热炉6台,鼓风机6台,离心机4台,过滤器,加热器类6台,风机4台,搅拌器4套等成套设备。设备结构平台等。分为冷氢化单元、冶金硅卸载站、金属氯化物处理单元、氯硅烷储罐区、精馏单元、硅烷冷冻水单元、热油炉单元、STG储罐区、STG储罐区冷冻机单元、雨淋阀室。硅烷充装站、硅烷压缩机及配电间。在本项目所要求的工期内完成安装施工工作所需测量,施工,检测,管理、单机调试和配合无负荷联动试车、有负荷联动试车、
4、调试工作等全过程的工作。Equipment installation works for silane areas vary, including 104 units, the overall container class 198 units, the overall tower 10 units, heat exchangers are 97 units, compressor 5 units, 8 reactors, 4 storage tanks, 6 heating furnaces, 6 blowers, 4 centrifuges, filter, 6 heaters, 4 fa
5、ns, stirrer 4 sets of complete sets of equipment. The equipment structure of the platform, in this project the required time to complete the installation of the construction work required measurement, construction, detection and management, the stand-alone debugging and with no load test, load linka
6、ge commissioning, commissioning the whole process.建设单位:陕西有色天宏瑞科硅材料有限责任公司Client: Shaanxi Nonferrous Tianhong REC Silicon Materials Co., Ltd.设计单位:福陆(中国)工程建设有限公司Designer: Fluor ( China) Engineering Co., Ltd.监理单位:陕西省工程监理有限责任公司Consultant: Shaanxi Engineering Consultant Co., Ltd施工单位:陕西建工安装集团有限公司Contractor
7、: SCEGC Installation Group Co., Ltd.二、编制依据Section II. Description Basis 1、建筑工程施工质量验收统一标准GB50300-20131. Unified standard for construction quality acceptance of building engineering GB50300-20132、工业安装工程施工质量验收统一标准 GB50252-2010 installation engineering construction quality acceptance unified standard GB
8、50252-20103、石油化工工程施工及验收统一标准SH3508-2011 engineering construction and acceptance of unified standard SH3508-20114、立式圆筒形钢制焊接储罐施工及验收规范 GB50128-20144. Specification for construction and acceptance of vertical cylindrical steel welded storage tanks GB50128-20145、机械设备安装工程施工及验收通用规范GB50231-20095. General spe
9、cification for construction and acceptance of mechanical equipment installation engineering GB50231-20096、石油化工机器设备安装工程施工及验收通用规范 SHT3538-20056. General specification for construction and acceptance of installation engineering of petrochemical machinery and equipment SHT3538-20057、压缩机、风机、泵安装工程施工及验收规范G
10、B50275-2010, fan, pump installation engineering construction and acceptance specifications GB50275-20108、起重设备安装工程施工及验收规范 GB50278-2010 equipment installation engineering construction and acceptance specifications GB50278-20109、石油化工静设备安装工程施工质量验收规范 GB50461-2008 static equipment installation engineering
11、 construction quality acceptance specification GB50461-2008三、施工方案Section III. Production Scheme硅烷区中化工设备多、工艺复杂,安装技术操作要求较高。各工艺单元联系密切、设备材质种类多、清洗要求高、吊装难度大。涉及到种反应器、塔器、换热器、机泵等众多化工设备,安装精度要求高;部分设备规格尺寸不大,可以整体到货。对于体积较大,在不影响吊装的前提下,尽量完成劳动保护的安装、防腐、绝热及附属管线安装。部分设备规格尺寸不大,可以整体到货。对于体积较大,在不影响吊装的前提下,尽量完成劳动保护的安装、防腐、绝热及附
12、属管线安装。Installation dimension relates to the requirements of many kinds of silane District chemical equipment, complex process, and the installation operation requirements higher. The process units are close contact with each other, the equipment material, and cleaning, hoisting difficulty. In respon
13、se, towers, heat exchangers, pumps and many other chemical equipment installation accuracy requirements; part of the equipment is small, can the overall arrival. For larger, in does not affect the hoisting of the premise, as far as possible to complete the work protection installation, anti-corrosio
14、n, insulation and subsidiary pipeline installation. Part of the equipment size is not big, can the overall arrival. The volume is large, without affecting the lifting the premise, as far as possible to complete the labor protection, anti-corrosion, insulation and subsidiary pipeline installation.有些大
15、型超限(超高、超重)设备需单独编制专项施工方案。Some large scale (super high, overweight) equipment requires preparing special construction program.设备安装前应具备的条件. Conditions prior to the installation works设备验收必须具备下述技术文件: Related document and specification for equipment acceptance Equipment acceptance must have the following
16、technical documents:(1)设备出厂合格证、说明书;(1).Equipment factory certificate, specification;(2)质量证明书;(2).Certificate of quality;(3)需要热处理的设备,要检查设备内外垫板、固定件的位置、数量、规格是否符合设计文件的规定。(3).The need for heat treatment equipment, to check the equipment inside and outside the plate, fixed position, quantity, specificatio
17、ns are in line with the provisions of the design documents.设备按以下内容进行检查: Equipment Inspection methods(1)箱号、箱数及包装情况;(2)设备名称、规格、型号、特性;(3)设备的外形尺寸和管口方位应符合设计文件要求;(3).Equipment size and nozzle orientation should meet the requirements of design documents;(4)设备表面不得有变形和超过规范允许的划痕、锈蚀;(4) .The surface of the equ
18、ipment shall not be deformed and exceed the allowable marks, corrosion;(5)设备内件及附件的规格、尺寸、数量应符合图纸要求;(5) Specifications, dimensions and quantities of equipment and accessories shall conform to the requirements of the drawing;(6)设备存放时,应合理支垫、敞口部位应加盖临时盲板。(6). when the equipment is stored, should be reason
19、able support pad, open mouth parts should be stamped with a temporary blind plate.基础验收 Foundation acceptance (1)设备安装前必须办理基础移交手续,土建专业应向安装专业提交基础交接证书及测量记录,并应在基础上明显地画出标高基准线及基础纵横中心线,在相应建、构筑物上应标有坐标轴线。交付安装的设备基础其强度必须达到设计要求,周围土方应回填、夯实、整平,地脚螺栓的螺纹部分应无损坏及锈蚀。(1) before installing the equipment, you must apply th
20、e basis of transfer procedures, the civil engineering should be submitted to professional installation based handover certificate and measurement record, and should be based on clearly draw elevation datum line and vertical and horizontal center line, in the corresponding construction, building mate
21、rial shall be marked with the coordinate axis.(2)对基础进行外观检查,不得有裂纹、蜂窝、空洞、露筋缺陷。按土建施工图检查重要设备的基础沉降观测点,应符合设计要求。(2).Visual inspection should be no cracks, honeycomb, voids, and reinforced defects. According to the construction plan of the important equipment to check the foundation settlement observation p
22、oints, should meet the design requirements.(3)按土建交接记录及设备制造图和设备布置图对基础的尺寸及位置进行复测检查。允许偏差应符合下表要求。(3).On the basis of the inspection, the civil engineering transfer records and equipment manufacturing drawings and equipment layout drawings, the base size and position shall be re tested.(4)对查出的问题,应以书面形式报告
23、给业主单位主管工程师,由其研究确定处理意见,施工单位不得擅自处理。(4).To identify the problem, should be reported in writing to the owner of the unit in charge of the engineer, to determine the treatment of their views, the construction unit shall not be handled without authorization.基础尺寸及位置的允许偏差Allowable deviation for base dimensi
24、on location项次SN偏差名称Deviation items允许偏差值Deviation allowable(mm)1基础坐标位置(纵、横轴线)Base coordinate location ( L and A direction )202基础各不同平面的标高Elevation of different level +0 -203基础上平面外形尺寸Based on the plane shape size凸台上平面外形尺寸Plane dimension of convex table凹穴尺寸 / recess dimension30-20+204基础上平面的水平度(包括地平上需安装设
25、备的部分)Based on the level of the plane (including the part of the device to be installed on the ground)每米/M5全长/ total length 105坚向偏差:Vertical deviation 每米/ per meter5全高/ total height106预埋地脚螺栓Anchor bolts embedded 标高(顶端)EL ( top)+20 0中心距(在根部和顶部两处测量)center distance ( survey from bottom and top )27预留地脚螺栓
26、孔:Reserved holes for anchor bolts中心位置Center 10深度Depth +20 0孔壁的铅垂度(全长)Verticality of holes (total length)+108带锚板的预埋活动地脚螺栓With anchor plate pre buried bolt activities标高Elevation +20 -0中心位置Center position 55水平度(带槽的锚板)Leveling ( anchor plate )5水平度(带螺纹孔的锚板)Leveling ( anchor plate with screw holes)2施工要点.
27、Construction focus设备进入现场的顺序应按吊装顺序进行。 into the field of the order should be carried out in accordance with the lifting sequence.设备安装前,应首先确定其标高、方位,然后根据基础验收情况按照规范要求准备垫铁,并在设备就位前把垫铁摆放好且找水平。 to be installed before, should first determine the elevation, azimuth, and then according to the basic acceptance o
28、f the situation in accordance with the requirements of the specification to prepare the pad iron, and the equipment in place to put the pad iron placed well and look for the level.立式设备就位后找正采用经纬仪进行测量,其垂直度误差必须控制在有关标准规范的要求之内;卧式设备就位后找正采用水平玻璃管进行测量,其水平度必须控制在有关标准规范的要求之内。 positioning equipment for the use o
29、f theodolite measuring, the verticality error must be controlled within the requirements of relevant standards; horizontal equipment in place to find is the level of glass tubes were measured and the level of degree must be controlled within the requirements of relevant standards.需要吊耳进行吊装的设备其吊耳应在设备制
30、造厂焊完,吊耳的规格、吊耳的位置及方位应符合吊装要求。经过热处理的设备,施工过程中应特别注意保护,严禁电焊二次打火。 lugs shall be in equipment manufacturing factory by welding if need to. Lug specifications, hanging ear position and orientation should meet the lifting requirement. After heat treatment equipment, in the construction process should pay spec
31、ial attention to the protection of, it is strictly prohibited to welding the two ignition.设备在中交前其内部均应清扫清洁,并作好封孔隐蔽记录。 should be cleaned and clean, and make the sealing holes hidden records before intermediate inspection. 静设备施工要点. Static Equipment Construction procedures 静止设备安装程序 Static equipment Installation Procedures (1)、安装前的准备:、设备安装前按设计图纸或技术文件要求,画定安装基准线及定位基准标记,找出设备垂直或水平找正基准点。对相互间有关连或衔接的设备,还应按关连或衔接的要求确定共同的基准。、检查设备的底座螺栓孔相对位置尺寸与实际预埋地脚螺栓位置偏差是否满足安装要求,如有问题要会同有关部门提出处理意见。、设备安装前应对管口方位进行检查,并做好安装标记(1)换热器冷却器类设备施工程序: (1). Heat exchanger, cooling equipment installation proce