1、吊车安装方案汇总安装工艺规程Installation process procedures1轨道的安装Installation of the rail1.1 安装前的准备Preparation before installation1) 熟悉规范、标准及图纸资料; Familiar specifications, standards and drawings;2) 审查安装轨道所需材料的材质、规格、数量是否满足技术要求; Review whether the mounting-rail materials quality, specification, quantity meet the te
2、chnical requirements;3) 检查施工通道、清理现场,达到安全施工、文明施工要求; Check the channels of construction, clean up the site, which can reach the requirements of safe construction and civilized construction;4) 制定安全措施,设置安全生产区,有专人对高空作业及重物起升作业区进行监视,安全绳设置要有足够的强度及稳固性; Develop safety measures, set safety production area, the
3、re is special assigned personnel responsible for monitoring work at height and weights lifting operation area and the safety rope set should have sufficient strength and stability;5) 准备轨道安装所需用的机械、工具、量具; Prepare required machinery, tools, measuring tools during rail installation;6) 检查轨道的质量:如发现有弯曲变形,应
4、校正后才能安装; Check the quality of the rail: if found bending and deformation, correct before installation;7) 吊车梁放线检查及标高测量: The crane beam paying off check and elevation measurements:a 用经纬仪测量吊车梁中心线,并留下标记(23米设置一个点);The theodolite is used to measure the crane beam centerline and leave marks (set a point ev
5、ery 2-3m);b 用水准仪测量吊车梁的水平标高,并作记录; Use water level to measure the crane beam and make records;C 吊车梁跨距用钢卷尺、弹簧称测量;注意弹簧称的示值应和检查大车轮距时一致; Crane beam span should bed with measure steel tape, spring balance; pay attention to the spring balance showed values consistent with those during measurement of the thr
6、ead of the gantry. 1.2 轨道安装Rail installation1.2.1 重轨(38kg/m以上)压板式安装程序(带钢垫板)Heavy rail (38kg / m or more) pressure plate installation procedure (with steel shim)1) 基准板安装1) The reference board is installed:在吊车梁上每隔2米左右固定一块垫板,要求标高(用水准仪测量)控制在2m以内,纵横向水平度以2mm/m水平仪找平;On the crane beam, fix a pad about every
7、 2m, required elevation (measured with water level) should be controlled within 2m, vertical and horizontal levelness should be made with 2mm / m spirit level;2) 轨道就位2) Rail in place:把经检查符合安装要求并下料的轨道按预选排好的顺序吊装就位;Hoist cut rails which meet the installation requirements and after inspection in place a
8、ccording to pre-determined order;3) 轨道找正、定位、紧固3) Rail alignment, positioning, fastening安装所用的工具、材料(螺栓、垫圈、压板、螺母等)用小桶或工具袋吊到吊车梁上,注意放好,以防掉下伤人;必要时也可对位穿好,但不紧固,用鱼尾板把轨道联接成一体,注意轨道接头应有2mm间隙,以保证热膨胀要求;根据中心线找正轨道,先固定基准位置,并测量检查安装数据,符合要求后,垫其它位置,要求垫平、垫实并固定,检查后把螺栓全部紧固。Installation tools and materials (bolts, washers,
9、clips, nuts, etc.) should be hanged to the crane beams with a keg or tool bag, and pay attention to putting them away, to prevent fall-against injuries; if necessary, counterpoint assembly can be made, but do not fasten them, and make coupling connection to the rail with fishplates, and pay attentio
10、n to the rail joint gap should be 2mm, to ensure the requirements of the thermal expansion; according to the centerline, find alignment for the rails, first fix the reference position and measure and check the installation data, and pad other positions after meeting the requirements, and pad and fix
11、 solid, fasten all of the bolts after checking.4) 测量检查4) Measurement and check:轨道安装找正后,用经纬仪、水准仪、钢卷尺、弹簧称等量具进行最后测量检查,质量符合安装技术要求和设计要求,并做记录,作为交工资料。After the rail mounting alignment, final measurement and check should be made with theodolite, level, steel tape, spring balance equal amount, and the qualit
12、y should meet the installation requirements and design requirements and make record make records well which shall be used as the hand over information.5) 质量检查符合要求后,将方垫圈与压板点焊,并每隔五组对焊一组。After quality check and meeting the quality requirements, make spot welding for square washers and the pressure plat
13、e, and one group of butt welding will be made every five groups.1.2.2 轻轨(24kg/m以下)、方钢轨道安装Installation of light rail (24kg / m or less) and square steel rail 1) 基准板安装1) Installation of the reference board:在吊车梁上每隔1.5米左右固定一块垫板,要求标高(用水准仪测量)控制在2mm以内。纵、横向水平度以2mm/m水平仪找平。Fix a pad about every 1.5m on the cr
14、ane beam and the elevation (measured with water level) should be controlled within 2mm. Vertical and horizontal levelness of 2mm / m and find leveling with spirit level.2) 轨道就位2) Rail in place:把经检查符合安装要求并下料的轨道按预选排好的顺序吊装就位;Hoist cut rails which meet the installation requirements and after inspection
15、in place according to pre-determined order;3) 轨道找正、定位、紧固、焊接:3) Rail alignment, positioning, fastening, welding:a 栓压板式安装找正、定位、紧固方法和重轨安装方法相同。Bolt pressure plate mounting alignment, positioning, fastening methods are the same as the heavy rail installation methods.b焊接式安装:在基准板位置进行找正,并点焊,待两条轨道所有基准板处都点焊完后
16、,进行测量检查,符合要求后,进行复垫固定并点焊,最后进行全面焊接。Welded installation: alignment at the position of the reference plate and make spot welding, and after all the reference plates of two rails are made spot welding, and meet the requirements after making measurement and inspection, re-pad, fix and make spot welding, and at last make full welding.4) 方钢轨道接头的宜在螺栓处,如不在螺栓处,应在接头下面放钢垫板。Square steel rail joint should be at the place of the bolt, i