国外工程现场管理规范性文件供货与安装的一般条款G.docx
《国外工程现场管理规范性文件供货与安装的一般条款G.docx》由会员分享,可在线阅读,更多相关《国外工程现场管理规范性文件供货与安装的一般条款G.docx(24页珍藏版)》请在冰豆网上搜索。
国外工程现场管理规范性文件供货与安装的一般条款G
GeneralConditionsforConstructionWorkforSupplyandErectOrders
TableofContents
1.Introduction
2.Definitions
3.TemporaryFacilities
4.ConstructionEquipment
5.VendorandhisPersonnel
6.MaterialsandStorage
7.InformationSuppliedbyCompany
8.InformationSuppliedbyVendor
9.Work
10.WorkingHours,Overtime,StandbyTime
11.Milestones,MilestoneDates,CompletionDate
12.InspectionandExpediting,Testing
13.PricesandRates
14.Changes.PricingofChanges
15.PhysicalProgress,Invoicing,Payment
16.Claims
17.UseoftheWorkandAcceptance
18.ReleaseofLiens,RetentionandBankGuarantee
19.Safety,Health,WelfareandEnvironmental(SHWE)
20.Security
21.PreservationandMaintenanceoftheSite
22.DirectionandApproval
23.CompliancewithLaw
24.Guarantees
25.TerminationforDefaultandPetitioninBankruptcy
26.Continuity
27.AuditRights
28.Title
29.Confidentiality
30.Patents
31.Insurance
32.Liability
33.HazardousSubstancesIndemnification
34.Suspension
35.Cancellation
36.Termination,Suspension,CancellationLiabilities
37.USAExportAdministrationRegulations
38.AssignmentandSubcontracting
39.ForceMajeure
40.ApplicableLaw
1.Introduction
1.1TheseGeneralConditionsforConstructionWorksupplementthe"InstructionsandConditionsCompanywhicharepartofthePURCHASEORDERforthesaleandsupplyofcertainspecifiedequipmentand/ormaterials.TheGeneralConditionsforConstructionWorkgoverntheconstructionportionofthePURCHASEORDERonly.Incaseofanydiscrepancyintermsofambiguityornonapplicabilitybetween"InstructionsandConditionsCompany"andtheseGeneralConditionsofConstructionWork,theseGeneralConditionsprevailovertheInstructionsandConditions.Specialconditionsmaybeaddedtothesegeneralconditionsif,intheopinionofCompanyand/orOWNER,suchisrequired.IncaseofanydiscrepancybetweentheseGeneralConditionsandtheagreedSpecialConditions,theSpecialConditionswillprevail.
1.2AnychangeormodificationoftheGeneralConditionsand/ortheSpecialConditionsandanyexceptionstheretobyVENDORinhisproposalorotherwiseshallonlybevalidandbindingwhenexpresslyagreeduponbybothpartiesandaddressedinfullintheSpecialConditionsandnotbywayofreferenceinthePURCHASEORDER.
1.3HeadingsandsubheadingsofarticlesandindicesusedintheseGeneralConditionsandintheSpecialConditionsareforconvenienceandeaseofreferenceonlyandinnowaydefine,limitordescribethescopeorintentofanyprovisionorofthetotalPURCHASEORDER.
2.Definitions
ThefollowingdefinitionsshallapplytotheconstructionpartofthePURCHASEORDER.Wordsimpartingthesingularonlyalsoincludethepluralandviceversawherethecontextrequires.
2.1PurchaseOrder
PURCHASEORDERshallmeanthecompleteCompanyPURCHASEORDERwiththeGeneralConditionsandSpecialConditionsforConstructionWork,alldocumentswhicharedeemedtobeincorporatedthereinbyreferenceandallagreedPURCHASEORDERamendments.
2.2Work
WORKshallmeanallconstructionworktobeperformedandservicestoberenderedbyVENDORundertheGeneralConditionsandSpecialConditionsofthePURCHASEORDERinrespectoftheconstructionwork.
2.3Subcontractor
SUBCONTRACTORshallmeananypersonorCompanyhavingaSUBCONTRACTwithVENDORfortheperformanceoftheWORKorpartofit.
2.4Company
CompanyshallmeantheCompanywhohasawardedthePURCHASEORDER,theirdesignatedrepresentatives,andtheirrepresentativeorhisappointedrepresentativeattheSITE.SuchawardmaybeinCompany'snameorinthenameand/oronbehalfoftheclientwithwhomCompanyhasacontract.
2.5Owner
OWNERshallmeantheclientwithwhomCompanyhasacontracttoperformwork.
2.6Site
SITEshallmeanthelocationofbothon-plotandoff-plotunitsandfacilitiesofOWNER'sPLANT.
2.7Plant
PLANTshallmeantheunitsandfacilitiestobeconstructedandofwhichtheWORKisapart.
2.8Materials
MATERIALSshallmeananymachinery,equipment,materialsandotheritems(includingtheinitialsparepartsspecifiedelsewhere)suppliedbyVENDORandintendedtobeincorporatedpermanentlyinthePLANToritsfacilities.
2.9SurplusMaterials
SURPLUSMATERIALSshallmeananyMATERIALSfoundtobesurplusuponacceptanceoftheWORKorearlier,withtheexceptionoftheinitialspareparts.
2.10ConstructionEquipment
CONSTRUCTIONEQUIPMENTshallmeananylifting,transporting,testing,calibrating,protecting,andothermaterialsandequipment,aircraft,watercraft,scaffolding,tools,implementsandsuchotheritemsasarerequiredfortheexecutionoftheWORKbutshallnotincludeMATERIALS.
2.11TemporaryFacilities
TEMPORARYFACILITIESshallmeananytemporaryyardsforthestorageand/ormaintenanceofCONSTRUCTIONEQUIPMENTand/orMATERIALS,anytemporaryoffices,WORKshops,changeroomsandotherbuildings,anytemporarysanitaryfacilitiesandinstallationsforutilitiesincludingtheconnectionstothepointsofsupply,anyofficeequipment,officesupplies,anyconsumablesusedintheTEMPORARYFACILITIESandsuchotheritemsasarerequiredfortheexecutionoftheWORKbutshallnotincludeMATERIALSorCONSTRUCTIONEQUIPMENT.
2.12VariationinScope
VARIATIONINSCOPEshallmeananyincreaseordecreaseintheWORK.
2.13Vendor
VENDORmeansthepartyperformingtheWORKunderthePURCHASEORDER.
2.14ExtraWork
EXTRAWORKshallmeananymodificationoralterationtoapartorpartsoftheWORKinprogressorcompleted.
2.15CompletionDate(s)
COMPLETIONDATE(s)shallmeanthedate(s)specifiedinthePURCHASEORDERforcompletionoftheWORK.
2.16Milestone
MILESTONEshallmeananeventthatformspartoftheWORKorastagethatapartoftheWORKhasreached,whereastheeventorstagehasbeendefinedinthePURCHASEORDER.
2.17MilestoneDate
MILESTONEDATEshallmeanthedateonwhichaMILESTONEmustbereached,whereasthedatehasbeendefinedinthePURCHASEORDER.
2.18Acceptance
ACCEPTANCEshallmeanCompany'sacknowledgementthattheWORKorpartoftheWORKcompletedhasbeenreviewedwithoutnotinganynonapprovednonconformanceswiththePURCHASEORDERbyissuingaCertificateofAcceptance.TheguaranteeperiodshallstartonthedateoftheissuanceoftheCertificateofAcceptance.
3.TemporaryFacilities
3.1CompanyshallmakeavailabletoVENDORfreeofchargeasufficientareaorsufficientareasoflandforvendor'sTEMPORARYFACILITIES.
3.2VENDORshallpromptlyremoveanyTEMPORARYFACILITIESwheninstructedbyCompanytodoso.
3.3VENDORshall,athisownexpense,supply,install,maintainandremovetheTEMPORARYFACILITIESthatVENDORmayrequire.PriortothesupplyVENDORshallsubmittoCompanyallVENDOR'srequirementsincludingdetaileddrawingswhereuponCompanywillestablishtheexactlocationoftheTEMPORARYFACILITIES.
3.4Companyshall,insofarastheydeemnecessary,providefreeofchargeasupplyofpotablewater,nonpotablewaterandelectricpower.VENDORshall,athisownexpense,provide,maintainandremoveanytemporarypipingsystems,cablesanddistributionboardsVENDORmayrequire,includingtheconnectionstothepointsofsupply.ConnectionstopointsofsupplyshallnotbemadewithoutpriorapprovalbyCompany.
3.5Waterandelectricpowershallbeusedconservatively.Electricpowershallnotbeusedforheatingorforstress-relievingpurposesorfortestingmicroprocessorsorcomputersystems.
3.6IncaseacentralsanitarysewersystemisavailableVENDORmay,athisownexpense,provideandremoveanytemporarysystemVENDORmayrequire,includingtheconnection(s)totheexistingsystem.ConnectionsshallnotbemadewithoutpriorapprovalbyCompany.
3.7VENDORisresponsibleforthesupply,installation,maintenanceandremovalofanytelephoneand/ortelexconnectionsVENDORmayrequire.Allcosts,includingbutnotlimitedtosubscriptionandusage,areforVENDOR'saccount.TheroutingofcablesmustbeapprovedbythetelephoneCompanyandCompanypriortotheirinstallation.
3.8VENDORshallnotremovefromtheSITEanyTEMPORARYFACILITIESwithoutthepriorapprovalbyCompany.
VENDORshallpromptlyremoveanyTEMPORARYFACILITIESwheninstructedbyCompanytodoso
3.9OnacceptanceoftheWORK,VENDORshallremoveallremainingTEMPORARYFACILITIESandleavethearea(s)inaconditionsatisfactorytoCompany.
OnacceptanceoftheWORK,VENDORshallremoveallremainingTEMPORARYFACILITIESandleavethearea(s)inaconditionsatisfactorytoCompany.
4.ConstructionEquipment
4.1VENDORshall,athisownexpense,supply,maintainandremovetheCONSTRUCTIONEQUIPMENTrequiredfortheexecutionoftheWORK.
4.2VENDORwarrantsthattheCONSTRUCTIONEQUIPMENTshallbedeployedattheSITEsuchthattheWORKisexecutedinanefficientandexpeditiousmanner.
4.3TheCONSTRUCTIONEQUIPMENTshallbeinfirst-classoperatingcondition,safeandsuitablefortheefficientexecutionoftheWORKandshallbeaccompaniedbyallsafety,testandoperatingcertificatesand/orrecordsrequiredbymanufacturerandauthorities.
VENDORshallconductregularsafetychecksespeciallyoncranes,vehiclesandscaffoldingtoensurecompliancewithsafetyregulations.
CONSTRUCTIONEQUIPMENTnotconformingwiththeforegoingshallpromptlyberemovedbyVENDORandreplacedwithCONSTRUCTIONEQUIPMENTacceptabletoCompanyand/orOWNERwithoutadditionalcosttoCompanyand/orOWNERandwithoutdelayingtheWORK.
4.4VENDORissolelyresponsibleforthesupplyofhisownfuels,lubricantsandotherproductsrequiredfortheexecutionoftheWORK.IncaseOWNERisamanufacturerofsuchp