监理月报SNPEPCSUPMSR11.docx
《监理月报SNPEPCSUPMSR11.docx》由会员分享,可在线阅读,更多相关《监理月报SNPEPCSUPMSR11.docx(83页珍藏版)》请在冰豆网上搜索。
监理月报SNPEPCSUPMSR11
×××监理工程有限公司
×××Supervising&ManagingCompany
SNP-EPC-SUP-MSR-11
×××水泥有限公司×××4600t/d
熟料水泥新型干法节能环保生产线
×××Shui’onCementCo.Ltd.×××4600t/dClinkerNewDryProcessEnergysaving&EnvironmentalProtectionProductionLine
监理月报第11期
SupervisionMonthly ReportNO.11
总监理工程师:
第11期
GeneralSupervisionEngineer:
×××
×××瑞安水泥×××项目部
×××Shui’onCementCo.Ltd.×××ProjectManagementDepartment
2009/11/30
1.工程概况Projectintroduction
工程基本情况Projectbasiccondition
工程名称:
×××4600t/d熟料水泥新型干法节能环保生产线
Projectname:
×××Shui’onCementCo.Ltd.×××4600t/dClinkerNewDryProcessEnergysaving&EnvironmentProtectionProductionLine
工程地点:
×××
Projectsite:
×××
工程性质:
自筹资金(2.7亿)
Capitalsource:
self-financing(270million)
建设单位:
×××项目筹建部
Constructionunit:
L×××ProjectPreparationDepartment
设计单位:
×××
Designby:
×××
勘察单位:
×××
Surveyorganization:
×××
施工单位:
×××
×××
合同工期ContractPeriod
2008年2月23开工,土建按单项工程180天,全部工程按300天完成,安装工程按210天,土建和安装交叉30天
February200823starts.Constructionworksbyasingle180-day,300daysbythetotalnumberofprojectscompleted;installationworksby210days,constructionandinstallationofa30-daycross
×××工程项目一览表Itemlist
单位工程名称
ItemName
各单项工程具体描述
Specificdescriptionofeachindividualproject
土建工程(A标)
CivilEngineering(A)
施工单位:
×××
ConstructionUnit:
×××
土建工程(B标)
CivilEngineering(B)
施工单位:
×××
Constructionunit:
×××
安装(A标)Installation(A)
施工单位:
×××
Constructionunit:
×××
安装(B标)Installation(B)
施工单位:
×××
Constructionunit:
×××
施工单位:
×××
ConstructionUnit:
×××
合同工期ContractPeriod
2009年6月15日开工,2010年2月15日竣工,合同工期自开工之日起240个日历日
June15,2009startedFebruary15,2010completionofthecontractperiodstartsfromthedateof240calendardays
2.施工基本情况Constructionbasicconditions
进入11月份,A标施工:
熟料库滑模至3.7m,转运站基础完成;窑头第一部分15.35m框架柱完成部分,梁板钢筋模板安装,窑头第四部分基础完成,设备基础完成部分,第五部分钢筋模板安装;中控室7.75m框架完成,12.25m框架脚手架搭设;煤粉制备8.5m框架完成,13.5m框架脚手架搭设;窑尾余热5.0m、6.0m框架完成,16.15m框架柱完成,梁板钢筋模板安装;原料粉磨磨房22.5m框架钢筋模板安装,喂料库16.5m框架钢筋模板安装,收尘器6.0m平面框架设备基础完成,窑灰仓基础完成,3.4m框架纲筋模板安装,风机房基础开挖;原料调配站19.0m框架完成,24.0m框架钢筋模板安装;原煤预均化堆场网架柱完成,环梁钢筋模板安装;石灰石预均化堆场轨道梁及网架基础、基础柱完成,网架地梁、轨道梁完成部分,转运站土方开挖;原料辅助堆场轨道梁完成,A轴、F轴基础完成,1轴、25-28/A-E轴基础基础柱施工;汽轮发电机房7.5m框架钢筋模板安装;机修车间基础施工;石膏破碎地基处理完成,基础钢筋模板安装;原煤卸车坑基础开挖;化学水基础承台完成;原料辅助破碎土方开挖;窑中1#\2#\3#墩土建主体完成,煤粉仓基础开挖;窑尾土建主体完成;石膏堆场土建主体完成。
B标施工:
水泥包装9-16轴5.6m至屋顶框架完成,17-20轴6.84m框架完成,9.84m、10.44m框架钢筋模板安装;水泥库1#、2#库滑模至15.305m,3#、4#库滑模至7.7m,7.7m梁板完成,5#、6#库6.6m汽车衡梁施工;水泥磨2至6轴13.0m框架框架完成,18.5m框架施工,1至2轴14.0m框架完成;行政办公楼4.2m框架施工;石灰石破碎及输送挡墙施工至±0.00m,地沟-3.8m底板施工,胶带机基础施工。
矿山施工:
钢筋混凝土挡墙完成;工业场地未开工;一废、二废道路路基施工,二废道路部分区域爆破施工;胶带机检修道路基本完成,路边毛石挡墙施工;南山头、北山头削顶;996与1011连接道路毛石挡墙施工。
安装:
A标安装,煤磨底板灌浆完成,支架正在安装;原料磨其中一台底板拼装完成,另一台正在拼装;原煤预均化堆场轨道梁钢轨安装90%,50%的地脚螺栓灌浆完成,下料机中柱在拼装;窑头空气冷却器二层框架扶梯灰斗安装完成,袋收尘立柱底梁安装完成;窑尾塔架二层完成,C5旋风筒安装完成。
B标安装,石膏堆场立柱横梁安装完成。
EnteredinNovember,AStandardConstruction:
ClinkerSiloslidingto3.7m,thebasisofthecompletionoftransferstations;Clinkercooling,dustcollectingandclinkerconveying15.35mframecolumnstocompletethefirstpartofpartoftheflat-slabsteeltemplatestoinstall,Clinkercoolingfourthpartofthebasisforthecompletionoftheequipmenttocompletethebasisofsection,PartVsteeltemplateinstallation;inthecontrolroom7.75mframetocomplete,12.25mputsupscaffoldingframe;coalgrindingandpulverized8.5mtocompletetheframework,13.5mputsupscaffoldingframe;SPboiler5.0m,6.0mtocompletetheframework,16.15mframeworkcolumnpartiallycompletedinstallationofflat-slabsteeltemplate;rawmaterialgrinding22.5mframeworkofthereinforcementtemplatesinstalledlibraries16.5mframeworkofthereinforcedfeedtemplatestoinstall,dustcollecting6.0mplaneequipmentfoundationcompleted,Thebasisofthecompletionofkilnduststorage,3.4mFrameworkClasstendonstemplatestoinstall,Fansroomfoundationexcavation;rawmaterialfeeding19.0mframeworkforthecompletionofthedeploymentofrawmaterialsfeeding,24.0msteelframetemplateinstallation;coalpre-blendingandconveyingofthepre-gridcolumnsarecomplete,ringbeamreinforcementtemplateinstallation;limestonepre-blendingandconveyingtrackbeamandgrid-based,Trusstobeam,beamtofinishpartofthetrack,completepartofthetransferstationearthexcavation;rawmaterialspre-blendingconveyingthecompletionofyardtrackbeam,A-axis,F-axis-basedcompletionofanaxis,25-28/AEAxis-basedfoundationcolumnconstruction;turbineandgeneratorroom7.5msteelframetemplateinstallation;machinerepairshopfoundationconstruction;gypsumcrushinggroundprocessingiscompleted,basicsteeltemplateinstallation;coalunloadingpitfoundationexcavation;chemicalwater-basedcompleted;materialsupportbrokenearthexcavation;kiln1#\2#\3#pierconstructionofthemaincompleted,coalstoragefoundationexcavation;preheater&precalcinerconstructionofthemaincompleted;gypsum/additivematerialcrushing,storageandconveyingtocompletethemainconstruction.
B-standardconstruction:
cementpacking9-16axis5.6mtotheroof,theframeworkofthecompletionof,17-20axis6.84mframetocomplete,9.84m,10.44mframeworkofthereinforcedtemplateinstallation;cementsilo1#,2#libraryslidingto15.305m,3#,4#libraryslidingto7.7m,7.7mflat-slabcompleted,5#,6#library6.6mTruckbeamconstruction;cementgrinding2to6-axis13.0mtocompletetheframeworkoftheframework,18.5mframeconstruction,1to2-axis14.0mframeworkcompleted;4.2mframeworkoftheadministrativebuildingconstruction;limestonecrushingandconveyingretainingwallconstructionto±0.00m,trench-3.8mfloorconstructionandfoundationconstructionadhesivetapemachine.
Mineconstruction:
reinforcedconcreteretainingwallcompleted;industrialsitefortheunstart;FirstwastedumpingsiteandSecondroadsubgradeconstruction,Secondroadspartofthedistrictwasteblasting;overhaulthebasiccompletionoftheroad,roadsiderubbleretainingwallconstruction;Mountainofnorthandsouthhillscuttop;996andthe1011roadconstructionofstoneretainingwall.
Installation:
Astandardinstallation,coalmillcompletedonthefloor,frameisbeinginstalled;rawmilloneofthebackplaneassemblycompleted,anotherisbeingassembled;coalpre-blendingandconveyingtrackbeamhomogenizingthepre-railinstallation90%,50%oftheanchorboltscompletedonthenextcolumninassemblingmaterialmachine;clinkercoolingaircoolerframesecondfloorofashbucketelevatorinstallationiscomplete,bagdustcollectorattheendofbeamcolumninstallationiscomplete;preheater&precalcinertocompletethesecondfloortower,C5cycloneinstalled.
B-standardinstallation,gypsum/additivematerialcrushing,storageandconveyingcolumnbeamsinstalled.
×××工、料、机配备情况?
.
表1Table1
人工Labor
工种
Typeofwork
土工Bricklayer
钢筋工Steelbender
木工/架子工
Carpentry/scaffolder
机、电Mechanical-electricalworker
普工
Worker
管理人员
Managingpersonnel
其它
Others
总人数
Total
人数
Amount
51
126
290
40+22
90
25
/
640
持证人数
PersonnelwithCertificate
51
126
290
62
80
25
/
630
主要
材料Mainmaterials
名称
Name
单位Unit
上月库存量Lastmonthstocks
本月进场量
Thismonthsiteenteringamount
本月库存量Thismonthstocks
本月消耗量Thismonthconsumption
水泥cement
T
/
袋装inbag108
散装bulk1326.74
/
/
钢筋fixture
T
/
93.838
/
/
外加剂Admixture
T
/
2
/
/
沙sand
M3
/
2854.3
/
/
石子stone
M3
/
2220.6
/
/
模板template
张piece
/
1900
/
/
钢管
steeltube
T
/
122.458
/
/
毛石
rubblestone
M3
/
268
/
/
灌浆
Groutingmaterial
T
/
4
/
/
主
要
机
械
Mainequipment
/
/
/
/
/
×××工、料、机配备情况
表2Table2
人工Labor
工种
Typeofwork
土工Bricklayer
钢筋工Steelbender
木工
Carpentry
机、电Mechanical-electricalworker
普工
Worker
管理人员
Managingpersonnel
其它
Others
总人数
Total
人数
Amount
5
10
5
70
15
8
/
113
持证人数
PersonnelwithCertificate
5
10
5
70
15
8
/
113
主要
材料Mainmaterials
名称
Name
单位Unit
上月库存量
Lastmonthstocks
本月进场量
Thismonthsiteenteringamount
本月库存量Thismonthstocks
本月消耗量
Thismonthconsumption
水泥
Cement
T
200
1523.98
500
1223.98
钢筋
Rebar
T
50
163.663
63.663
150
山砂
Sand
M3
1453
1729.6
1182.6
2000
外加剂
Admixture
T
4
14
8
10
石子
aggregation
M3
600
1518.9
800
1318.9
模板Template
M2
3000
2000
2000
3000
钢管
Steeltube
T
200
520.98
250
470.98
主
要
机
械
Mainequipment
名称
Name
生产厂家
Manufacturer
规格型号
Specification
进场日期Enteringsitedate
数量
Amount
/
/
/
/
/
此数据只供参考 Thisdataisforreferenceonly
×××工、料、机配备情况
表3Table3
人工Labor
工种
Typeofwork
架子工
Scaffoldworkers
钢筋工Steelbender
木工
Carpentry
机、电、车Mechanical-electricalandcar
worker
砼工、砌筑装饰工、爆破工
Concreteworker,decorativemasonryworker,blastingworker
管理人员
Managingpersonnel
其它
Others
总人数
Total
人数
Amount
/
/
/
/
/
40
217
257
持证人数
PersonnelwithCertificate
/
/
/
/
/
40
217
257
主要
材料Mainmaterials
名称
Name
单位Unit
上月库存量Lastmonthstocks
本月进场量
Thismonthsiteenteringamount
本月库存量Thismonthstocks
本月消耗量Thismonthconsumption
水泥
cement
T
/
40
/
/
砂石
stoneandsand
T
/
20
/
/
主
要
机
械Mainequipment
名称Name
生产厂家
Manufacturer
规格型号
Specification
进场日期Enteringsitedate
数量
Amount
挖土机Excavator
/
CAT320C
8
推土机Bulldozers
/
T160
1
压路机Roller
/
15-21T
1
空压机AirCompressor
/
20m3
15
发电机
/
/
1
此数据只供参考 Thisdataisforreferenceonly
3.对本月工程进度计划完成情况分析
Analysisofthecompletesituationoftheprojectschedulethismonth
3.1本月实际完成情况与计划进度比较:
Comparisonoftheactualcompletedworkthismonthandthescheduleworkthismonth:
3.1.1月实际完成情况与计划进度比较:
Comparisonoftheactualcompletedworkthismonthandthescheduleworkthismonth:
表4Table4
序号No.
工号
Itemno.
计划完成部