地下室转胎膜施工方案
地下室转胎膜施工方案
目录
目录.....................................................................................................................................1一、工程概况....................................................................................................................2二、编制依据....................................................................................................................2三、施工准备....................................................................................................................2四、施工工艺....................................................................................................................3五、操作工艺....................................................................................................................3六、砖胎模的砌筑要求....................................................................................................4七、质量保证....................................................................................................................5八、质量标准....................................................................................................................6九、安全及文明施工措施................................................................................................7
一、工程概况
工程名称:
武汉关山经贸还建小区成园11#、14#、15#楼
建设地点:
东新新技术开发区关山街建设单位:
武汉中杰投资有限公司设计单位:
武汉智业建筑设计有限公司监理单位:
湖北华泰工程建设监理有限公司施工单位:
武汉鸣辰建设集团有限公司建设规模:
本工程是武汉关山经贸还建小区成园11#、14#、15#楼,总建筑面积大约是140000平方米,其中地下室面积
大约是26000平方米,均为剪力墙框架结构。
11#楼地下1层,地
上33层;14#楼地下1层,地上32层;15#楼地下1层,地上33层。
二、编制依据
1、武汉关山经贸还建小区成园工程建筑及结构施工图2、建筑施工手册
3、《砖石工程施工验收规范》
4、《砌体工程施工质量验收规范》
三、施工准备作业条件
、基础垫层验收合格。
、柱子偏位在设计规定的范围内
、测量定位、弹好墙身线、轴线、检查定位线是否准确。
、材料及主要机具:
页岩砖、水泥、砂、大铲、刨锛、线坠、钢卷尺、灰槽、小水桶、砖夹子、小线、筛子、扫帚、八字靠尺板、钢筋卡子、铁抹子等。
四、施工工艺、工艺流程:
清底、弹线→拌制砂浆→确定组砌方法→砌筑→抹灰
五、操作工艺、清底、放线
、用扫帚把垫层扫干净,然后用细线进行定位弹线、拌制砂浆:
、砂浆配合比应采用重量比,并试验室确定,水泥砂浆强度等级为MU5水泥计量精度为±2%,砂±5%。
砖胎膜的砌筑沙浆采取的是1:
3砂浆配合比进行砌筑,经试验合格后方可使用。
、宜用人工搅拌,搅拌顺序为砂→水泥→水,搅拌均匀即可使用、砂浆应随拌随用,一般水泥砂浆和水泥混合砂浆须在拌成后3h和4h内使用完,不允许使用过夜砂浆,高温天气超30℃,砂浆应该在2h小时用完。
、确定组砌方法:
、集水坑、电梯井砖胎模组砌方法:
采用标砖满丁满条砌筑370厚。
砌体沿60度坡砌筑。
、电梯井、集水井土方于开挖方式采用爆破方式,造成基坑边坡宽度超宽,砌筑砖胎模时,在砌筑370厚墙体后向边坡超宽处砌体延伸砌筑。
、条基砖胎模组砌方法:
采用标砖砖满条砌筑120厚。
砌体沿60度砌筑。
、筏板基础砖胎模组砌方法:
采用标砖满丁满顺砌筑240厚。
里外咬槎,上下层错缝,采用“三一”砌砖法,严禁用水冲砂浆灌缝的方法。
砖胎模北侧240厚砌筑砖支腿。
砌筑:
、砖基础砌筑前,基础垫层表面应清扫干净,洒水湿润。
先盘墙角,每次盘角高度不应超过五层砖,随盘随靠平、吊直。
、砌基础墙应挂线,12墙单面挂线、24墙反手挂线。
、120砖胎模沿45度或60度坡砌筑,砌一层退一层,排砖均采用顺砖。
、基础标高不一致或有局部加深部位,应从最低处往上砌筑,应经常拉线检查,以保持砌体通顺、平直,防止砌成“螺丝”墙。
、要对照皮数杆的砖层及标高,如有偏差时,应在水平灰缝中逐渐调整,使墙的层数与皮数杆一致。
、抹灰:
先清扫干净,浇水湿润,随即抹灰,厚度为20mm,采用1:
3的水泥砂浆
六、砖胎模的砌筑要求、砖胎模施工注意事项
、砌筑砖胎膜时,很容易出现轴线位移的毛病,因此在坑槽上口应设置牢固的轴线控制桩,待墙身砌起后及时把轴线引到墙上,牵线施工。
、严格控制砖墙顶面标高,首先修平基底,然后以两边为准牵线施工。
需要时,立皮数杆。
、电梯基坑内开挖至设计标高,打垫层,砌筑砖胎模。
、为了节约材料,把断砖、烂砖利用在墙的两端等处或进行塞缝利用。
、独立基础砖胎模需要及时砌筑,深度h≤500mm的承台砖胎模采用120墙砌筑、深度500mm<h≤1200mm的承台砖胎模采用180墙砌筑要求砂浆饱满,随砌随勾砖缝,砖墙内侧用1:
3水泥砂浆抹灰,抹灰厚度20mm,提高砖墙整体强度和挡水能力。
砖胎模后土方待砖墙达到一定强度后再回填,采用木锤或木枋分层轻轻夯实,避免挤垮砖墙。
考虑到阴阳角卷材不好做防水。
采取了阴角用50mm50mm的圆角。
七、质量保证
1、根据图纸尺寸,已放好砖胎模墙外边线。
2、砖的品种、强度等级必须符合设计要求。
3、砂浆品种符合设计要求,强度必须符合设计要求。
4、砖砌体上下错缝,每间无四皮砖通缝。
5、砖砌体接槎处灰缝砂浆密实,缝、砖应平直;每处接槎部位水平灰缝厚度不
小于5mm或透亮的缺陷不超过5个。
6、预埋拉结筋的数量、长度均符合设计要求和施工规范的规定,留置间距偏差
不超过一皮砖。
7、灰砂砖在砌筑前晒水后含水率达到百分之四十即可砌筑。
8、基础表面应清扫干净,浇水湿润;先盘墙角,高度不超过五层砖,找平、吊
直,垫层局部应在第一层砖找平,采用满丁满缝,拉通线保持砌体通顺、平直,防止砌成“螺丝墙”;
9、砌体砂浆应饱满密实,实心砖体水平灰缝的砂浆饱满度应不小于80%,水
平和垂直灰缝宽度为1cm,砖角处严禁留直槎,灰缝应密实;
目录
目录.....................................................................................................................................1一、工程概况....................................................................................................................2二、编制依据....................................................................................................................2三、施工准备....................................................................................................................2四、施工工艺....................................................................................................................3五、操作工艺....................................................................................................................3六、砖胎模的砌筑要求....................................................................................................4七、质量保证....................................................................................................................5八、质量标准....................................................................................................................6九、安全及文明施工措施................................................................................................7
一、工程概况
工程名称:
武汉关山经贸还建小区成园11#、14#、15#楼
建设地点:
东新新技术开发区关山街建设单位:
武汉中杰投资有限公司设计单位:
武汉智业建筑设计有限公司监理单位:
湖北华泰工程建设监理有限公司施工单位:
武汉鸣辰建设集团有限公司建设规模:
本工程是武汉关山经贸还建小区成园11#、14#、15#楼,总建筑面积大约是140000平方米,其中地下室面积
大约是26000平方米,均为剪力墙框架结构。
11#楼地下1层,地
上33层;14#楼地下1层,地上32层;15#楼地下1层,地上33层。
二、编制依据
1、武汉关山经贸还建小区成园工程建筑及结构施工图2、建筑施工手册
3、《砖石工程施工验收规范》
4、《砌体工程施工质量验收规范》
三、施工准备作业条件
、基础垫层验收合格。
、柱子偏位在设计规定的范围内
、测量定位、弹好墙身线、轴线、检查定位线是否准确。
、材料及主要机具:
页岩砖、水泥、砂、大铲、刨锛、线坠、钢卷尺、灰槽、小水桶、砖夹子、小线、筛子、扫帚、八字靠尺板、钢筋卡子、铁抹子等。
四、施工工艺、工艺流程:
清底、弹线→拌制砂浆→确定组砌方法→砌筑→抹灰
五、操作工艺、清底、放线
、用扫帚把垫层扫干净,然后用细线进行定位弹线、拌制砂浆:
、砂浆配合比应采用重量比,并试验室确定,水泥砂浆强度等级为MU5水泥计量精度为±2%,砂±5%。
砖胎膜的砌筑沙浆采取的是1:
3砂浆配合比进行砌筑,经试验合格后方可使用。
、宜用人工搅拌,搅拌顺序为砂→水泥→水,搅拌均匀即可使用、砂浆应随拌随用,一般水泥砂浆和水泥混合砂浆须在拌成后3h和4h内使用完,不允许使用过夜砂浆,高温天气超30℃,砂浆应该在2h小时用完。
、确定组砌方法:
、集水坑、电梯井砖胎模组砌方法:
采用标砖满丁满条砌筑370厚。
砌体沿60度坡砌筑。
、电梯井、集水井土方于开挖方式采用爆破方式,造成基坑边坡宽度超宽,砌筑砖胎模时,在砌筑370厚墙体后向边坡超宽处砌体延伸砌筑。
、条基砖胎模组砌方法:
采用标砖砖满条砌筑120厚。
砌体沿60度砌筑。
、筏板基础砖胎模组砌方法:
采用标砖满丁满顺砌筑240厚。
里外咬槎,上下层错缝,采用“三一”砌砖法,严禁用水冲砂浆灌缝的方法。
砖胎模北侧240厚砌筑砖支腿。
砌筑:
、砖基础砌筑前,基础垫层表面应清扫干净,洒水湿润。
先盘墙角,每次盘角高度不应超过五层砖,随盘随靠平、吊直。
、砌基础墙应挂线,12墙单面挂线、24墙反手挂线。
、120砖胎模沿45度或60度坡砌筑,砌一层退一层,排砖均采用顺砖。
、基础标高不一致或有局部加深部位,应从最低处往上砌筑,应经常拉线检查,以保持砌体通顺、平直,防止砌成“螺丝”墙。
、要对照皮数杆的砖层及标高,如有偏差时,应在水平灰缝中逐渐调整,使墙的层数与皮数杆一致。
、抹灰:
先清扫干净,浇水湿润,随即抹灰,厚度为20mm,采用1:
3的水泥砂浆
六、砖胎模的砌筑要求、砖胎模施工注意事项
、砌筑砖胎膜时,很容易出现轴线位移的毛病,因此在坑槽上口应设置牢固的轴线控制桩,待墙身砌起后及时把轴线引到墙上,牵线施工。
、严格控制砖墙顶面标高,首先修平基底,然后以两边为准牵线施工。
需要时,立皮数杆。
、电梯基坑内开挖至设计标高,打垫层,砌筑砖胎模。
、为了节约材料,把断砖、烂砖利用在墙的两端等处或进行塞缝利用。
、独立基础砖胎模需要及时砌筑,深度h≤500mm的承台砖胎模采用120墙砌筑、深度500mm<h≤1200mm的承台砖胎模采用180墙砌筑要求砂浆饱满,随砌随勾砖缝,砖墙内侧用1:
3水泥砂浆抹灰,抹灰厚度20mm,提高砖墙整体强度和挡水能力。
砖胎模后土方待砖墙达到一定强度后再回填,采用木锤或木枋分层轻轻夯实,避免挤垮砖墙。
考虑到阴阳角卷材不好做防水。
采取了阴角用50mm50mm的圆角。
七、质量保证
1、根据图纸尺寸,已放好砖胎模墙外边线。
2、砖的品种、强度等级必须符合设计要求。
3、砂浆品种符合设计要求,强度必须符合设计要求。
4、砖砌体上下错缝,每间无四皮砖通缝。
5、砖砌体接槎处灰缝砂浆密实,缝、砖应平直;每处接槎部位水平灰缝厚度不
小于5mm或透亮的缺陷不超过5个。
6、预埋拉结筋的数量、长度均符合设计要求和施工规范的规定,留置间距偏差
不超过一皮砖。
7、灰砂砖在砌筑前晒水后含水率达到百分之四十即可砌筑。
8、基础表面应清扫干净,浇水湿润;先盘墙角,高度不超过五层砖,找平、吊
直,垫层局部应在第一层砖找平,采用满丁满缝,拉通线保持砌体通顺、平直,防止砌成“螺丝墙”;
9、砌体砂浆应饱满密实,实心砖体水平灰缝的砂浆饱满度应不小于80%,水
平和垂直灰缝宽度为1cm,砖角处严禁留直槎,灰缝应密实;