钻井作业流水账
FirstSpud/22”Section
1.Afterrigmove,checkwaterpumpsandwatersupplylinesduringequipmentinstallation.Filluptanksw/waterinadvance.Mix1000BBlsspudmud.
2.Afterinstallation,PTcirculatingsystemw/cleanwater.M/UDrillstring.Preparespud-in.
3.BHAforspud-inasfollowed:
BIT+NBRR(withFLOAT+TOTCORing)+SHOCKSUB+1
9.5"DC+STRR+2
9.5"DC+15
s8-1/4"DCS+5"HWDP
4.Drill22”holeto+/-750ft.
5.TheDo’sandDon’ts:
a)Usesinglepumpforfirstspud.Makecirculationbyusingjetcellarthroughdischargelinetoshaleshaker.Establishcirculation.
b)LowWOB,LowRMP(50-60)Lowstks(60-65)forfirst10ft.Thenincreasetooptimumdrillingparametersgradually.Afterdrill1joint,increasetheRPMandpumpstksto105-110RPMand95-100SPM.WOBincreaseswiththeDSweight.MaximumWOBis45-50KLBs.
c)Mostofwellsbeforehadlostcirculationwhiledrilling22”section.Iflosscirculationoccurs,continuedrillingwithwater&75*2SPM.Pump15-20HIVISpilleveryjointinordertocarrysands.
d)AverageROPshallbe30ft/hduringthissection.Mostofwellsbeforehadseverebitbouncing.Optimumdrillingparametersiscritical.
6.Bereadyforrunning18-5/8”CSG:
a)RemoveCSGprotector.Drift&measureallstands.Cleanthreads.
b)InstallCSGfloatshoeandweld.
c)InstallCSGcentralizers.Oneforeachforfirst5JTs,thenoneforevery3JTs.Installcementbasketonthebottomofthelastthirdjoint.Installonecentralizeraboveandonebelowcementbasket.
d)Preparecasingrunningtools:
slips(21),singlejoint,Btypecasingtong(usedasbackuptong),circulatinghead,Weatherfordcasingtongetc.
e)PrepareDPsusedforISCbasedonCSGlength.CheckandverifyDPcentralizeretc.
7.DrilltoCSGshoedepth,beforePOOH:
a)Pump100BBLsHIVISandcirculate20-30min.
b)Wipertripto9-1/2”DCoutofrotarytable.Ifanyobstruction,reamw/waterandpumpHIVISforcuttingscarrying.
c)Backtobottom.Pump50BBLsHIVIS&circulate(20min).Thenpump75PCFHIVISpilltobottom.
d)Wellsurvey.
8.POOH.L/Dreamer&SS.Don’tfillin.
9.M/UDPs(usedforISC)andrackbackinderrick.
10.RIHsurfacecasing.Checkfloatshoe.Runsomewaterwithfirstcasingatv-doortocheckfloatshoecondition.Threadlock(orusethreadlocker)tofirst3jointsorweldthem.
11.ContinuerunningCSG.M/UcirculatingheadattheV-doorinadvanceincaseofanyobstruction.
12.AfterrunningCSG,bereadyforcementingjob.ISC(Innerstringcement)isusuallyusedfor18-5/8”CSG.Beforecementing,running5”DP(withISCstinger)intoCSG.InsertISCstingerintofloatshoe.FillupDPandCSGannulusw/water.P/UandpulltheStringeroutoffloatshoe.Checkmudfluidlevelofannulus.Re-stabstinger.M/U411
4”Unionwith4”union
”circulatingsub.Circulate(InnerDPVolume).R/Ucementingline&cement.Afterfinishingpumpingcement,breakout4”unionanddropplug.Ifthereisnocementreturnsatcellar,atopcementjobisrequired.Beforetopcementjob,fillinwellborewithsomeSCMfirst.
13.Wellheadrectificationafter-cementing:
a)Prepare2bars,anchorlugsandwateroutletsforsupportingCSG.
b)Weldlegs,anchorlug,wateroutletsandunions.CutCSG(informForemanfirst).Theseshouldbedonewithin3hours.
17-1/2”Section(二开)
1.Beforespud=in,P/U17-1/2”bit,reamer,bitbreakerandothertoolsontodrillfloor.
2.BHAof17-1/2”sectionshouldbeasfollows:
BIT+NBRR(withFLOAT+TOTCORing)+SS+1Jt9.5"DC+STRR+2Jts9.5"DC+8Jt8-1/4"DCS+JAR+4Jts8-1/4"DCS+12Jts5"HWDP
3.M/UandRIH.Checkandverifythestringtally.
4.Hydro-testcasingwith2000psi.
5.Drillcementplugandfloatshoe.Displacewaterwithmud.
6.Drill17-1/2”holetoTDasfollow:
a)DrillwithlowparameterswhenreamerisoutofCSGshoe.80SPMw/singlepump65-70RPMWOB:
25-30KLBs;Commonparametersshouldbegraduallyincreasedto45-50KLBs,100-110RPM&75*2SPMw/doublepumps.
b)WhenHIGHROP,HIGHTORQUEoccursorcannotreachbottomafterM/UJT.PUMPHIVISandBACKREAM.
c)LCalwaysoccursindrill17-1/2”section.Drillw/waterwhenlosscirculationoccurs.Pump20BBLsHIVISforcarryingsands.
7.Preparationduringdrilling13-3/8”CSG
a)RemoveCSGprotector.Measure,drift&cleantheCSG.
b)M/UFS&FC.FCshouldbeconnectedtothe3rdboxandtackweld.
c)Installcentralizerasfollows:
Fixonecentralizereveryjointforthefirst10JTsunderconditionofLC.Thenoneevery3JTstosurface.Undernormalcondition,1centralizerforfirst5JTs,thenevery3JTstosurface.Fix1centralizerabove&1belowDVPKR.
d)Preparetoolsforrunning13-3/8”CSGasfollows:
13-3/8”CSGElevator,Slip(17pieces),singleelevator,CSGcirculationhead,WeatherfordCSGtong&CSGBushing.
e)M.U/P.U.landingjoint(withflange)&landingbase(onestage/primaryCSGhead)onpiperack.
f)ConnectDVPKRtoCSGasperForemanInstruction.
g)CheckTWO
(2)CAMERON2-1/16”gatevalves.
h)PrepareforN/UBOPandtestingtools.
8.Drill17-1/2”sectiontoCSGpoint:
Thesameprocedurewillbeconductedasthefirstsection:
∙PumpHI-VISpills&CHC.
∙WipertriptoCSGshoe.Backtobottom.
∙Sweepholew/HI-VIS&CHC.SpotHI-VISbeforePOOH.DropTOTCOSurvey.
∙POOH.L.D.Reamer&9-1/2”DC.
9.RunCSGandcementing.
a)BeforerunningCSG,cuttheflowlineof18-5/8”wellheadwiththeheightequaltotheheightbetweentwoflangesonlandingbase(betweenthetopoflandingbaseandbottomflange).Forinstance,theheightofFMCis17.5”toensurethetopflangeoflandingbasewillleveltheground.Cuta4”diameterholebeneaththescarfingformudreturnduringsecondstagecementing.
b)HoldPJSM.ForemansummarizesthecasingrunningproceduresandsomeDos&Don’ts.
c)FillupfirstCSGw/watertocheckfloatshoetoverifyit’sunblocked.ThenrunCSGasprocedure,payattentiontofillupmudandDVPFRposition.
d)AfterCSGrunningtobottom,connectlandingjoint&landingbaseontotheCSGstringonrigfloor.Connectbottomflangeonthelandingbaseto18-5/8”CSG.Extracareshouldbegiventosideoutletsoflandingbase,ensuringtheirdirection/theypoint-E-W.Wheninstallinggatevalve,thehandwheelpointsnorth.ThisisanimmutableruleofSaudiAramco.
e)M/Ucirculationheadinv-doorinadvance.Lineuptocirculateincaseofencounteringdrag.Afterreachingbottom,circulateasrequired(CSGinsidevolume).Connectcementinglines.Preparefirststagecementwithnecessaryhosesandbends.
f)Checkbackflowafterfirststagecementing,dropplug(orbomb),pumpittosetDV.ThenCONTpumpingtoopencirculationport.Prepareforsecondstagecementing.
g)Circulateexcesswater&slurrytopitw/suctionpump.CONTpumpinguntilclearinannulus.Load/releaseclosingplug.DisplaceslurrytocloseDVtool.
Note:
AssigncertainpersontoobservereturningandnotifyDrillerintimetorecordandcalculateremainedreplacementvolumeandreturnedslurry.
10.N/UandTestBOP
a)Aftercementing,weldthebottomflangeoflandingbaseand18-5/8”CSG,blankoff4”port.NippleupBOPs.PrepareP.T.
b)AfternipplingupBOPs,functiontestandRIHtestcup(cuptester).OneortwostandsHWDPbelowcup.Therearetwotypesofcup:
FMCandGRAY.Theusagedependsoncasinghead.
c)Aramcopressureteststandard:
Lowpressure-300psi;highPressure-2500psi(2000psiforannularpreventer).Holdpressurefor5or10min(basedonForemaninstruction).Testannular,manualgatevalvesondrillingspool&HCR.Checkvalveonkilllineside,chokeline,blindram,piperamandcasinghead(w/2000psi),emergencykillline,chokemanifold,upperandlowerKellycock,insideBOP,FOSVetc.
d)Testproceduresandmethods:
Connectpressuretestingtoolsandlinesasperfigure1.Circulateandfillupw/waterabovethecup,thenstartP.T.
Note:
1)Whentestingblindram,backbreaksinglefromthecup,thenpumptestfromchokeline.
2)WhentestingCSGheadw/cuptester,runcupatthe60ftbelowCSGhead,thenpumppressurefromchokeorkillline.
3)UsespecialtestingsubtotestKellycock,insideBOPetc.
4)Whentestingchokemanifold,shoulddofromoutsidetoinside.
5)It’sforbiddentoreleasepressurefromwellheadaytime.
6)Aftercompletionthetesting,fillupthetestingsheet,handoveracopytoforemanwiththepressurecurvechart.TheoriginaldocumentssignedbyForemanshouldbekeptbyToolpusher.
12-1/4”Section(三开)
Drill12-1/4″Hole
1.Preparebit,reamer,bitbreaker,andBHA.
2.PU/MUBHAasfollows:
Bit+NBRR(withfloat+seat)+8-1/4″DC×2+reamer+8-1/4″DC×15+jar+8-1/4″DC×2+X.O+5″HWDP+5″DP
3.RIHandcheckstringinventory/depth.Recorddepthofcompression(thedepthofDVPKRorsomeremainedplug).Pressuretestw/waterto1500Psi(or300PsiasForemanrequired).DrillplugandDVPKRwiththeparameterasfollows:
20~30KLB,70RPMand80~90spmw/singlepump.
AfterdrillingoutofDV,pressuretestforcasingagain.
ContinueRIHtotagcementandchecktallytoconfirmdepthandrecordit.
Drillplugandaccessoriestill15′upperofFCandretest.
ContdrillingplugandFS,replacewaterw/mud.
4.AfterdrillingoutFSandcement,drill12-1/4″holewiththesameparametersthatdrillingtheplugtillreamerisoutofshoe.Thendrillwiththefollowingparameters:
45~50KLB,105~110RPMand65spmwithdoublepump.
5.12-1/4″section(2300~4100FT)isthemostcomplicatedintervalwhichincludedWASIAandSHUAIBA.
A.WASIAisawater-bearingformationandsomeshaleformationwillexpandafterabsorbingwaterfrom2600~3500FT.Usemudnotwatertodrillthissection.TheROPwillbeveryhighwit