MeasuringtheImpactofReworkonConstructionCostPerformance
Bon-GangHwang1,
StephenR.Thomas,M.ASCE2,
CarlT.Haas,M.ASCE3,
andCarlosH.Caldas,M.ASCE4
1AssistantProfessor,Dept.ofBuilding,NationalUniv.ofSingapore,Singapore117566.E-mail:
bdghbg@nus.edu.sg
2AssociateDirector,ConstructionIndustryInstitute,Austin,TX78759-5316.E-mail:
sthomas@mail.utexas.edu
3Professor,Dept.ofCivilEngineering,Univ.ofWaterloo,WaterlooON,CanadaN2L3G1.E-mail:
chaas@civmail.uwaterloo.ca
4AssistantProfessor,Dept.ofCivil,Architectural,andEnvironmentalEngineering,Univ.ofTexasatAustin,Austin,TX78712-0276.E-mail:
caldas@mail.utexas.edu
(Accepted23September2008)
Introduction
Constructionprojectsoftenexperiencecostandscheduleoverrunsandreworkisasignificantfactorthatdirectlycontributestotheseoverruns.ResearchbytheConstructionIndustryInstitute(CII)revealsthatdirectcostscausedbyreworkaverage5%oftotalconstructioncosts(CII200511).ConsideringthattheU.S.constructionindustryexpended$1,502billionin2004fortotalinstalledcosts(BureauofEconomicAnalysis20065),almost$75billionwaswastedondirectcostscausedbyreworkinthatyearalone.Therefore,reworkmustbeconsideredasignificantfactoraffectingcostperformanceintheconstructionindustry.
Severalresearchefforts(O’ConnerandTucker198623;CII19897;Davisetal.198912;Buratietal.19924;Loveetal.1999a20,b21;Love2002b16;Fayeketal.200313;LoveandEdwards200417)haveattemptedtoidentifyandclassifytherootcausesofrework,andtoquantifyitsoverallextent.Employingthemetric,totalfieldreworkfactor,andtheclassificationofreworksourcesdevelopedbyCII,thispaperassessesthedirectimpactsofreworkonconstructioncostperformanceusingdatafrom359actualprojects.Morespecifically,theobjectivesoftheresearchdescribedinthispaperwere:
(1)toidentifytheimpactsofreworkonconstructioncostperformanceforvariouscharacteristicsofprojects;
(2)todeterminetheimpactsofdifferentsourcesofreworkonconstructioncostperformance;and(3)toisolatetherootcausesofreworkandrecommendpossiblesolutionsforthosecauses.
Bycomparingtheimpactsofreworkaccordingtoprojectcharacteristicsandbymeasuringsourcesofrework,thoseprojectsmostaffectedbyreworkareidentified.Additionally,thosesourcesofreworkhavingthebiggestimpactonconstructioncostperformancearediscussed.Aftertheanalysisofthecostimpactofreworkissummarized,therootcausesofreworkwillbeassessedandpossiblesolutionscanbesuggested.
Therecognitionofthevariousimpactsofreworkisimportantforprojectmanagers.Forthoseprojectsonwhichcosttendstobemoreaffectedbyrework,projectmanagersshouldfocusonminimizingreworkbydevelopingsystemsforaddressingthesourcesofrework.Preprojectandqualitymanagementplansshouldbedraftedwithanunderstandingofthecausesofreworkinordertominimizeitsimpact.Thispaperprovidesanunderstandingoftheimpactofreworkonconstructioncostperformance,thushelpingtoreducereworkandimproveprojectcostperformance.
Backgroundtop
AccordingtoLove(2002b)16reworkhasvariousdefinitionsandinterpretationswithintheconstructionmanagementliterature:
termsforitinclude“qualitydeviations”(Buratietal.19924),“nonconformance”(Abdul-Rahman19951),“defects”(JosephsonandHammarlund199914),and“qualityfailures”(Barberetal.20003).Loveetal.(2000)22characterizereworkastheunnecessaryeffortofredoingaprocessoractivitythatwasincorrectlyimplementedthefirsttime.Similarly,fieldreworkisdefinedasactivitiesthathavetobedonemorethanonceoractivitiesthatremoveworkpreviouslyinstalledaspartofaproject(CII20018).BaseduponCII’sdefinition,Fayeketal.(2003)13proposedadefinitionofreworkthataddstheconstraintthatreworkcausedbyscopechangesandchangeordersfromownersshouldnotbeclassifiedasrework.Inthesenseofconformance,therearetwomaindefinitionsofrework(Love2002b16;Fayeketal.200313).Thefirstdefinitionisthatreworkistheprocessbywhichanitemismadetoconformtotheoriginalrequirementsbycompletionorcorrection(Ashford19922).TheseconddefinitiongivenbytheConstructionIndustryDevelopmentAgency(1995)6holdsthatreworkinvolvesdoingsomethingatleastoneextratimeduetononconformancetorequirements.Althoughthewordingofthedefinitionsandinterpretationsofreworkvary,thereisacommontheme—reworkmeanshavingtoredoworkduetononconformancewithrequirements.
Severalstudies