DefiningRiskResponsePlans
You’veidentifiedyourrisks,analyzedthemfortheirimpactsontheproject,assignedprobabilitiesandimpactvalues,determinedanexpectedvalue,andrankedtheminorder.You’vealsodeterminedwhichoftherisks,givenallthoseconditions,requireresponseplans.Thischapterdiscusseswhatriskresponseplansare,thetechniquesfordevelopingresponseplans,andhowtodocumentandwriteplansforthoserisksthathaveahighprobabilityandhighimpactontheproject.Let’sgettoit.
RiskResponsePlanning
RiskResponsePlanningistheprocessofdecidingwhatactionstotaketoeducethreats(especiallytoscheduleandcost)whiletakingadvantageofheopportunitiesotherriskspresent.
Typically,you’llwanttodevelopriskresponseplansforriskswiththepotentialforhighprobabilityandhighimpact.Itisn’tefficienttospenttimewritingresponseplansforrisksyou’vedeterminedaren’tlikelytooccurandwon’timpacttheprojectsignificantlyiftheydo.Forexample,ifI’mbuildingatouristcenterintheMojaveDesert,Iwouldn’tspendtimeonariskresponseplanforthepossibilityofrain(ItdoesrainintheMojaveanaverageofinchesperyear),sothepossibilityexists,butit’shighlyunlikelyitwouldimpactmyproject.I’lldealwiththesetypesofrisksinthe“ContingencyPlanning”sectionalittlelaterinthischapter.
Rememberthatriskmanagementplanning,includingthedevelopmentofriskresponseplans,isn’taone-timeexercise.Asyouprogressthroughtheprojectandlearnmoreaboutpotentialriskevents,you’llreevaluatetheirimpacts,whichmayrequireachangeinstrategytodealwiththeriskandaneworrevisedresponseplan.AndeventhoughI’vefocusedprimarilyonrisksthatpreventyoufrommeetingthegoalsoftheproject,don’tforgetthatriskscanproduceopportunities.
UncertainCertainty
Onethingiscertain:
yourprojectdoeshaverisks,andifyouchoosetoignorethem,yourprojectwillhaveanuncertainoutcome.Allprojectriskiscloselylinkedwiththeavailabilityofinformationandcommunication,orthelackthereof,asI’vetalkedaboutpreviously.Themoreinformationyouhave,themorelikelyyou’reabletopredicttheriskeventanditsimpacts.
Andthebetteryou’reabletopredictriskimpacts,thebetteryou’llbeatcreatingriskresponseplans.
Whenthinkingaboutriskresponseplans,keepinmindthatriskout-comesgenerallyfallintothreecategories:
*Knownriskswithpredictableoutcomes
*Knownriskswithuncertainoutcomes
*Unknownriskswithunpredictableoutcomes
Thesearefairlystraightforward.Aknownriskissomethingyouknowhasthepotentialtohappen.Thetermpredictableoutcomesimpliesyouknowwithreasonablecertaintywhattheimpactsandoutcomesoftheriskeventswouldbeiftheyoccurred.Unpredictableoutcomesareimpactsandconsequencesoftheriskeventthataren’tfullyidentifiedorknown.Let’suseasimpleexampletoexplaineachoftheseoutcomes.You’vedecidedtopaintyourgaragedoorthisweekend.Oneriskthatcouldkeepyoufromcompletingthisprojectistheweather.Noproblem—youcruisetheInternetandcheckoutthelocalforecast,whichpredictsclearandsunnyskies,withlittlepossibilityofshowers.Youhavethemeanstolearnabouttheweather(theInternetsite)andtodeterminethecertaintyoftheimpact(a10percentchanceofshowers).Thatmeansyouknow,withpredictablecertainty,thatthisriskhasalowchanceofoccurring.Knownriskswithuncertainoutcomesaremoredifficultbecause,well,theiroutcomesaren’tcertain.However,theamountofuncertaintycouldvary.Youmay,forexample,knowit’sgoingtorainbutnotknowwhenit’llstartorhowlongit’llcontinue.Whenyou’refacingprojectriskswithuncertainoutcomes,Irecommendlearningeverythingyoucanabouttheriskanditspossibleimpacts.(Sincetheimpactsareunpredictable,thisisn’talwayspossible.)Youshouldinterviewstakeholders,researchpastprojects,andtrytomoveasfarfromtheuncertaintyendofthespectrumasyoucan.Themoreyouknow,thebetter.
Thelastbulletlistedpreviously,unknownriskswithunpredictableout-comes,saysyoudon’tknowabouttheriskandyoudon’tknowaboutitsimpacts.It’sanunknownriskwithanunknownoutcome.Supposeyou’rehappilypaintingawayandarethree-quartersfinishedwhenaflockofgeesehappenstoflyrightoveryourhouse.Youguessedit.Anunknownriskwithanunpredictableoutcomehasoccurred.
Manyprojectdecisionsaremadewithoutbenefitofknowingallthefacts,andriskanalysisisnoexception.Risk,afterall,isprimarilyaboutuncertainty.Analyzingtheriskstellsyouaboutthepossibleoutcomesfortherisk,andtheresponseplanaddresseshowtodealwiththoseoutcomes.
Thegreateryourcertaintyoftheoutcome,theeasieritwillbetodevelopresponseplans.Forexample,ifyouknowrainisacertaintyonthedayyou’replanningonpaintingthegarage,youcandeviseresponseplansthatarefairlyprecise.Youcouldpostponethepaintingtoanotherdayandsweepthegaragefloorinstead.
Or,perhapsyouknowwithreasonablecertaintythattherainiscomingbutwon’tstartuntilearlyafternoon.Inthatcase,youcouldquicklypaintthedoorinthemorningwhilethesunisstillout(orthecloudsarerollingin)andthenflipopenthedoorsoit’sprotectedbythegarageceilinguntilitdries.
PurposeofPlanningforRisks
Thepurposeforriskplanningistodeterminethemostappropriateresponsetoreduce,control,ortakeadvantageoftheriskevent.Alongwithdeterminingtheresponse,you’llwanttomakecertainyou’rechoosingtherightstrategyfortheriskevent.Afterdeterminingthestrategytouse,you’lldevelopanactionplantoputthisstrategyintoplayshouldtheriskeventoccur.
Thesecondpurposeforriskplanningistodetermineariskowner.ItalkedaboutriskownersandtheirresponsibilityinChapter2,“IdentifyingandDocumentingRisks.”Oncetheplanisdeveloped,theriskowneristheoneheldaccountableforwatchingforrisktriggers,trackingtherisk,recommendingtheimplementationoftheresponseplanifthesituationwar-rantsit,andthenmonitoringtheeffectivenessoftheresponseplanonceit’simplemented.
Riskresponseplanningalsohasanaddedbenefit.Whenriskeventsdooccur,you’llbeabletoremaincalm,cool,andlevelheadedaboutwhattodo.
RatherthanreactinglikeourfriendNed,you’llcalmlyreachfortheresponseplandocumentandknowwhattodo.Whenyou’reinpanicmode,theobjectistoresolvetheproblemasquicklyaspossible.Thatmeansyouusuallydealwiththingsthequickestandeasiestwayyoucanthinkofjusttogeteverythingundercontrol.Butgettingimmediatecontroldoesn’tnecessarilysolvetheprobleminthelongrun.Responseplanningallowsyoudeterminethebestmethodfordealingwitharisk,whichgivesyouahigherprobabilityofmeetingyourprojectgoals.
RiskResponseTechniques
Youhaveseveralstrategiesfordealingwithriskthathelpreduceorcontroltheimpactsofriskevents.Themostcommonstrategiesareasfollows:
*Avoidance
*Transference*Mitigation
*Acceptance
*Contingencyplanning
*Independentverificationandvalidation
Eachofthesetechniqueshasitsstrengthsandweaknesses.Beforedeterminingwhichstrategytouse,makecertainyouunderstandthetypeofriskyou’redealingwith,aswellastheseverityoftherisk.You’llwanttochoosethestrategythatwillbethemosteffectiveandcostefficientfordealingwiththeriskevent.Ifitcostsyoumoretorespondtotheriskthantheconsequencesoftheriskitself,youmaywanttoconsideradifferentstrategy.
Avoidance
Youmayhavealreadyguessedthattheriskavoidancetechniqueisaboutavoidingrisk.True.Itencompassesmorethanthat,however.Riskavoidancetechniquesincludethefollowing:
*Avoidingtheriskaltogether
*Eliminatingthecauseoftheriskevent
*Changingtheprojectplantoprotecttheobjectivesfromtheriskevent
Let’slookatsomeexamplesforeachtechnique.Avoidingtheriskaltogetherimpliesthatyouknowtheoutcomesoftheriskwithrelativecertaintyandcantakestepstokeeptheriskeventfromoccurring.SupposeNedandthephoto-shootteamareheadedtotheairporttocatchtheirflighttoParis.InkeepingwithNed’susualmanner,hehasheldeveryoneuptothelastsecond.Iftheyleaveanylater,theywon’thavetimetocheckthemillionpiecesofluggageNedisbringingandgetthroughsecurityintimetocatchtheflight.Sherry,thequick-thinkingprojectmanager,decidestodoatrafficcheckbeforeleaving.ShelogsontotheInternetandfindsthere’sbeenamajoraccidentonthehighwaytheywereplanningontakingtotheairport.Toavoiddelaysandkeepthemfrommissingtheflight,Sherrydecidesonanalternateroutethatbypassestheaccidentandavoidstheriskevent.
Eliminatingthecauseoftheriskisatechniquethatworkssomethinglikethis.Sherryknowsthattheteam’sluggagelookslikeeveryotherpieceofluggagethey’relikelytoseeonanairportconveyorbelt.Theteamiscarryingsomesensitivecompanyinformationandafewpiecesofspecializedequipment.Sherrycaneliminatethecauseofthisriskbycarryingthecompanymaterialandspecializedequipmentonboardintheircarryones.
OneoftheobjectivesofthephotoassignmentistoshootpicturesofParisiansdoingeverydaytasks—strollingthroughthepark,eatingatside-walkcafés,shopping,andsoon—outsideintheopenair.A