砖混施工组织设计论文文档格式.docx
《砖混施工组织设计论文文档格式.docx》由会员分享,可在线阅读,更多相关《砖混施工组织设计论文文档格式.docx(41页珍藏版)》请在冰豆网上搜索。
Abstract
TheconstructionorganizationplanisaimattheXi’anHigh-techDistrict1#residentialbuildingprojectconstructionthePlatform.Theconstructionorganizationplanisconstructstheconstructionorganization’scoreandthesoul,andisconceivestotheengineeringconstructionprojectentireprocessideawiththeconcretearrangement,usedfortoinstructconstructionitementireprocesseachactivitythetechnology,theeconomicalandorgnization’scomprehensivedocument.Whenestablishtotheprojectmanagementorganizationeatablishment,theconstructionoveralldeployedthattheconstructionpreparation,themainbranchsub-itemprojectjobpractice,theprojectqualitysafeguardmeasure,thesecurityandthecivilizedconstructionmeasure,thelocationmanagementmeasureandsoonmanyfactorsconsideredfullyasfaraspossible.Prominentscientificnature,serviceabilityandpointed,isguaranteedthathighquality,thelowconstruction,thesecurity,civilized,completecompletelytheconstructionworkimportanteconomicaltechnicalpaperhighspeed.Accordingtotheprojectdesignfeatures,combinedwiththedifficultoftheproject,takingfullyintoaccountthesocialimportanceofthisproject,constructionorganizationsinthedesigndetailtoensurethatthesystemconstruction,labor,machineryequipment,aswellastheconstruction,engineeringquality,safetyandcivilizedconstructionmanagementandoverallcoordinationofthevariousmeasures.thisdesignmainlyincludesthefollowingcontent:
Theprojectconstructionorganizationdesigns,teChineseandEnglishtranslation,theconstructionfloor-plan.Inordertoguaranteethatthetime,thequalityandthesecurity,thecivilizedworksite,saveconditionsandcost,establishesthepointedconstructionorganizationplan,eachbranchsub-itemprojectscharacteristic,thestrctueralfeature,theconstructiondifficultydegreetimeandthequalityrequirement,establishthepracticalandfeasibleplanofconstruction.Instructstheconstructionsmoothlycostengineeringprojecttheconstruction,thecontrolengineeringcost,thefoundationhighqualityproject.
Keywords:
organizationdesign;
constructiondeployment;
constructionmethod;
engineeringquality;
schedule
1.绪论..........................................................1
1.1研究的背景和意义........................................1
1.2研究的对象及任务........................................1
1.3研究的目的..............................................1
2.编制依据及说明...............................................1
3.工程概况.....................................................2
3.1建筑设计特点............................................2
3.2结构设计特点............................................3
4.现场平面布置.................................................4
4.1平面布置原则............................................4
4.2施工现场平面布置图......................................4
4.3施工道路................................................4
4.4材料堆放................................................4
5.施工方案.....................................................4
5.1施工准备................................................4
5.2施工现场临时用电........................................4
5.3施工现场临时用水........................................5
5.4施工测量................................................5
5.5沉降观测周期的确定......................................5
5.6主要分项工程的施工方法...................................6
5.6.1钢筋砼工程..........................................6
5.6.2钢筋工程............................................7
5.6.3设备安装工程........................................8
5.6.4装饰工程.............................................8
5.6.5脚手架工程...........................................9
5.6.6砖砌体工程...........................................9
5.6.7模板工程............................................10
5.6.8屋面工程............................................11
5.6.9基础工程............................................12
6.施工组织及施工进度计划.......................................13
6.1施工段的划分............................................13
6.2主要工序................................................13
6.3劳动力安排..............................................14
6.4施工管理机构和项目经理部的组成..........................14
6.5项目部班子主要成员及技术力量的配备......................15
6.6现场质量管理组织机构....................................15
6.7项目部的组成与要求.......................................16
6.8项目经理常驻现场的保证措施..............................16
6.9施工进度计划及措施......................................16
6.9.1进度计划监督管理....................................16
6.9.2施工进度计划........................................16
6.10施工协调配合...........................................17
7.质量保证措施.................................................17
7.1施工质量把关措施.......................................17
7.2施工现场监督检查.......................................18
8.工期保证措施.................................................18
8.1建立严格的施工进度计划检查制度.........................18
8.2保证材料及外加工构件的供应.............................18
8.3土建与安装的配合协调工作...............................18
8.4实行资金专款专用.......................................19
9.施工部署.....................................................19
9.1质量目标................................................19
9.2工期目标................................................19
9.3安全管理目标............................................19
9.4文明工地管理目标........................................20
9.5以科学管理为目标........................................20
9.6抓好施工现场环境建设....................................20
10.施工技术措施.................................................20
10.1采用新技术、新工艺.....................................21
10.2建立严格的技术管理体系.................................21
10.3施工技术过程控制.......................................21
10.4冬季施工管理工作.......................................21
10.5雨季施工管理工作.......................................23
11.机械设备配备情况.............................................23
12.安全施工措施.................................................24
12.1安全生产组织机构.......................................24
12.2安全保证体系...........................................24
12.3安全用电管理措施.......................................25
12.4现场保卫治安措施........................................25
12.5施工现场消防安全措施...................................25
12.6施工现场机械设备安全措施...............................26
12.7施工现场用电安全措施...................................26
12.8建筑施工安全措施.......................................26
12.9架子工程安全措施.......................................27
13.文明施工措施.................................................27
13.1创建文明工地的目标.....................................27
13.2文明工地管理体系的建立.................................27
13.3认真搞好厂容厂貌.......................................27
13.4进场材料堆放规范化.....................................28
13.5生产区文明施工管理.....................................28
13.6生活区文明工地管理.....................................29
13.7其它方面的文明工地管理.................................29
14.竣工交付使用后的回访工作.....................................29
附录.............................................................30
参考文献.........................................................33
致谢.............................................................34
1.绪论
1.1研究的背景及意义
随着我国经济的发展,建筑行业已经朝着多元化方向发展,建筑行业在我国经济发展中起着非常重要的作用。
科学合理的施工组织关系到工程的质量、成本管理、企业的经营效益,甚至关系到企业的生死存亡。
施工组织设计是对施工活动实行科学管理的重要手段,它具有战略部署和战术安排的双重作用。
它体现了实现基本建设计划和设计的要求,提供了各阶段的施工准备工作内容,协调施工过程中各施工单位、各施工工种、各项资源之间的相互关系。
施工组织设计是用来指导施工项目全过程各项活动的技术、经济和组织的综合性文件,是施工技术与施工项目管理有机结合的产物,它是工程开工后施工活动能有序、高效、科学合理地进行的保证。
1.2研究的对象及任务
在党和国家的的建设方针和政策指导下,从施工全局出发,根据各种具体条件拟定合理的施工方案,安排最佳的施工进度,设计最好的施工平面图。
把设计与施工、技术与经济、前方与后方、全局与个体。
施工中的各单位、各部门、各阶段以及个项目之间的关系很好的协调起来是工程取得最有效的成果。
在此次设计中是针对西安高新小区1#住宅楼做出最佳的施工组织设计。
1.3研究的目的
通过此次对西安高新小区1#住宅楼的施工组织方案的设计,让我们能够全面系统的掌握施工组织设计需要考虑的各种因素。
为以后的实际工作奠定好坚实的基础,在以后的工作中做出科学合理的施工组织设计。
2.编制依据及说明
本工程施工组织设计,主要依据目前国家对建设工程质量、工期、安全生产、文明施工、降低噪声、保护环境等一系列的具体化要求,依照《中华人民共和国建筑法》、《建设工程质量管理条例》、《国家现行建筑工程施工与验收技术规范》、《建筑安装工程质量检验评定标准》、《住宅楼招标文件》、《施工招标评定标办法》,《住宅施工图》、《答疑会纪要》以及根据政府建设行政主管部门制定的现行工程等有关配套文件,结合本工程实际,进行了全面而细致的编制。
我公司非常感谢建设单位对我方的信任,有幸参加本工程的投标。
本工程施工组织设计,是按照建设单位招标会通知精神和内容要求,经公司专题会议研究后,进行了认真而详细的编制,未提之处均按照施工图纸设计、国家现行技术规范、质量评定标准以及有关文件等要求的具体规定进行施工。
3.工程概况
3.1建筑设计特点
高新小区1#住宅楼位于西安市市区,为六层砖混结构,室内外高差0.45m,各层高3m,建筑物高度19.05米,建筑面积1517.70㎡,住宅楼为一梯两户,西侧为三室两厅,一厨一卫,东侧为三室两厅,一厨一卫一书房。
建筑做法及用料说明表:
项目
适用范围
类别
编号
附注
墙身砌体
全部
详见结构说明
砖墙墙身防潮层
防水水泥砂浆
潮1
设于未设圈梁处墙基—0.06m
散水
混凝土散水
散3
未注明处均距外墙皮1200mm
外墙饰面
丙烯酸外墙涂料
外13
内墙饰面
厨卫
釉面砖墙面
内35
规格200×
300贴至顶板底
其余
乳胶漆墙面
内17
白色乳胶漆三遍
踢脚线
同地面材料
踢1或踢15
高120mm
地面
铺地砖地面
地28
地砖规格300×
300
楼梯间
水泥砂浆面
地4
地砖规格600×
600
楼面
铺地砖楼面
(有防水)
楼41
地准规格300×
300,2mm厚聚氨酯防水涂料
水泥砂浆楼面
楼3
楼39
顶棚
全部
白色乳胶漆顶棚
棚5
屋面
水泥砂浆不上人屋面
屋II6
3mm厚SBS改性沥青卷材
油漆
木材面
调和漆二度,底油一度,满刮腻子
油6
2mm厚聚氨酯防水涂料;
25mm厚挤塑保温板;
木本色
金属面
调和漆二度,满刮腻子,防锈漆
油23
银白色
3.2结构设计特点
地基处理:
地基采用强夯,用3:
7灰土夯实0.5米厚
基础形式:
基础采用条形基础。
砌体材料:
±
0.000m以下,用MU10粘土砖,M10水泥沙浆砌筑;
0.000m以上采用承重多孔砖(KP1型),M5水泥混合砂浆砌筑。
结构:
基础垫层采用C10混凝土,基础、柱、梁、板及其他构建除注明意外,均为C25混凝土,钢筋工程采用国标03G101图集。
4.现场平面布置
4.1平面布置原则
平面布置力求科学、合理,充分利用有限的场地资源,最大限度的满足施工需要,确保既定的质量、工期、安全生产、文明施工四大目标的实现。
4.2施工现场平面布置图
《施工现场总平面布置图》附后
4.3施工道路
根据现场平面布置图和现场的实际情况,按场地内原来的排水坡向,对场地进行平整,修筑宽3.5米现场临时道路。
现场路基铺100毫米厚砂夹石,压路机压实,路面浇100毫米