凯德置地钢筋工程施工方案.docx
《凯德置地钢筋工程施工方案.docx》由会员分享,可在线阅读,更多相关《凯德置地钢筋工程施工方案.docx(24页珍藏版)》请在冰豆网上搜索。
![凯德置地钢筋工程施工方案.docx](https://file1.bdocx.com/fileroot1/2022-10/24/59ce5d81-b79a-4fdc-8544-ecf031cba29d/59ce5d81-b79a-4fdc-8544-ecf031cba29d1.gif)
凯德置地钢筋工程施工方案
目录
第一章编制依据····················································3第一节施工图纸·····················································3第二节主要规范、规程··············································3第二章工程概况·····················································3第一节总体简介·····················································3第二节结构概况·····················································4第三章施工部署及工期安排···········································5第一节施工目标·····················································5第二节项目组织机构·················································5第三节施工段划分···················································6第四节主要工程量物资采购及加工订货计划·····························6第五节劳动力计划···················································6第六节施工准备·····················································6第七节施工工期安排·················································9第四章主要施工技术方案·············································9第一节钢筋工程施工程序·············································9第二节钢筋放样·····················································9第三节钢筋加工·····················································9第四节钢筋的吊运··················································13第五节钢筋的连接··················································13第六节基础筏板钢筋绑扎············································14第七节墙、柱插筋···················································17第八节剪力墙钢筋绑扎··············································19第九节框架柱钢筋绑扎··············································23第十节顶板钢筋绑扎···············································24第十一节框架梁钢筋绑扎···········································26第十二节楼梯钢筋················································28第十三节后浇带处钢筋节点········································29第十四节人防工程施工注意的问题···································29第十五节专业交叉配合原则·········································29第五章工期保证措施················································30第六章工程质量目标保证措施、质量保证体系··························30第一节钢筋进场质量标准及验收·····································30第二节钢筋加工质量要求···········································30第三节钢筋加工质量要求···········································30第四节钢筋机械连接质量要求·······································31第七章安全生产文明施工············································32第一节钢筋机械的使用安全·········································32第二节钢筋吊运的安全要求··········································32第三节环保管理措施················································33第八章成品保护管理措施···········································33第九章应急救援预案················································34第十章季节性施工保证措施·········································34第一节雨季施工保证措施···········································35第二节夏季施工保证措施···········································35第十一章项目参见各方协调问题······································35
张家口凯德置地商业中心二期1#、3#高层商业楼钢筋工程施工方案
第一章编制依据第一节施工图纸
张家口凯德置地商业中心二期1#、3#高层商业楼施工图纸
第二节主要规范、规程
名称
编号
《混凝土结构工程施工质量验收规范》
GB50204-2011
《建筑机械使用安全技术规程》
JGJ33-2012
《建筑施工高处作业安全技术规范》
JGJ80-91
《施工现场临时用电安全技术规范》
JGJ46-2005
《混凝土结构施工图平面整体表示方法制图规则和构造详图》
11G101-1~3
《钢筋机械连接技术规程》
JGK107-2010
《人民防空工程防护设备选用图集》
RFJ01-2008
《防空地下室建筑设计》
FJ01~03(2007))
《防空地下室结构设计》
FG01~05(2007)
《人民防空工程施工及验收规范》
GB50134-2004
《人民防空地下室设计规范》
GB50038-2005
《施工现场安全防护场容卫生、环境保护及保卫标准》
DBJ01-83-2003
第二章工程概况
第一节总体简介
建筑总高度为1#47.93m,3#48.5m,地下三层,地上十三层
序号
项目
内容
1
工程名称
张家口凯德置地商业中心二期1#、3#高层商业楼
2
工程地址
张家口市经开区,南临朝阳大街,东临中兴路
3
建设单位
张家口鼎阳房地产开发有限公司
4
设计单位
北京京业国际工程技术有限公司
5
监理单位
张家口市建筑设计院有限责任公司
6
施工单位
张家口建筑工程集团有限公司
第二节结构概况
基础结构形式
筏板基础
主体结构形式
框架-剪力墙
层高
分别有2.1m,3.3m,3.5,4.2m,4.5m,4.8m,5.4m
第三章施工部署及工期安排
第一节施工目标
序号
项目
项目目标
1
质量目标
河北省优质工程
2
安全文明施工目标
无死亡事故发生,无重大安全事故发生,轻伤事故率小于2‰,达到河北省安全文明工地标准。
3
环境保护管理目标
坚持人文精神,营造绿色建筑
4
消防目标
杜绝火灾事故
5
科技进步目标
积极推广新工艺、新技术、新材料、新设备
第二节项目组织机构
序号
岗位
姓名
1
项目经理
罗鹏飞
2
技术负责人
高尚恒
3
质检员
张录谦
4
安全员
马英敏
5
安全员
张子龙
6
施工员
于东伟
7
施工员
温仕州
第三节施工段划分
1#基础划分4个施工段,主体划分为2个施工段;3#基础划分2个施工段,主体为一个施工段。
第四节主要工程量物资采购及加工订货计划
钢筋采购由采购部直接采购,钢筋工程所需的材料必须满足工期的要求。
第五节劳动力计划
序号
工种
地下施工阶段
主体施工阶段
人数
1
钢筋工
各90
各90
第六节施工准备
一、技术准备
1、认真审看图纸,了解设计意图,熟悉图纸内容,检查施工图是否完整、齐全,建筑与结构图在尺寸、标高及说明方面是否一致,掌握拟建工程的特点和结构形式。
2、开工前甲方、监理、设计、施工方进行图纸会审,作好“图纸会审记录”。
3、准备本工程所需用主要规程、规范、图集。
4、测量器具配置计划
序号
器具名称
数量
检测状态
1
钢卷尺
90
合格
二、施工用机械准备
机械设备名称
数量(台)
钢筋调直机
2
钢筋切断机
2
钢筋弯曲机
5
钢筋切割锯
2
钢筋套丝机
6
注:
其他手动工具每人自带。
三、材料准备
1、钢筋采购由采购部直接采购,钢筋工程所需的材料必须满足工期的要求。
四、钢筋检验
1、钢筋原材不同出厂日期、不同批号的钢筋有相应的出厂合格证;钢筋进场后,根据钢筋型号、出厂日期、钢筋批号等条件分别码放,并按规范要求进行现场抽样复试,复试合格后方可加工使用。
2、钢筋原材试验:
4、钢筋连接试验:
本工程钢筋采用直螺纹连接,凡直径≥16mm(含地梁部分)的钢筋采用直螺纹连接。
五、钢筋现场码放
1、钢筋料场放于钢筋加工区(详见施工组织设计总平面布置图)。
钢筋要架空堆放,下砌筑300mm高240厚砖墙。
在钢筋堆放处设置状态标识牌,表明钢筋种类(生产厂家、牌号、规格、材质、数量)和所处状态(待检、合格、不合格),必要时标明炉批号。
场地基层用混凝土硬化,并从中间向两边设排水坡度,避免基层出现积水,间距1500mm,在钢筋棚内,并应及时用于结构,若不能及时用上,则标注好规格、型号、尺寸以及应用部位等。
4、
第七节施工工期安排
在基础垫层及其他工序施工完毕以后,能进行钢筋绑扎时,安排施工人员入场,和其他工序配合施工进行钢筋的制作与安装(具体施工进度计划参施工组织计划)。
第四章主要施工技术方案
第一节钢筋工程施工程序
钢筋的配料及加工→钢筋吊运→钢筋安装→验收
第二节钢筋放样
根据工程的施工图纸及规范要求,对工程各部位进行详细的钢筋配置,配置过程中,若发现框架节点、暗柱及连梁节点钢筋过密,一定要先放样,提前采取措施,便于现场的加